Stargood Construction Pte Ltd v Shimizu Corp
Jurisdiction | Singapore |
Judge | Vincent Hoong JC |
Judgment Date | 06 November 2019 |
Neutral Citation | [2019] SGHC 261 |
Citation | [2019] SGHC 261 |
Court | High Court (Singapore) |
Published date | 30 April 2020 |
Docket Number | Originating Summons 1099 of 2019 |
Plaintiff Counsel | Chong Chi Chuin Christopher and Chen Zhihui (Drew & Napier LLC) |
Defendant Counsel | Lee Peng Khoon Edwin, Yong Boon On, Amanda Koh Jia Yi and Lee Shu Qing (Eldan Law LLP) |
Subject Matter | Building and Construction Law,Statutes and regulations,Building and Construction Industry Security of Payment Act,Adjudication determinations,Jurisdiction,Subcontracts,Claims by subcontractor after termination of subcontract |
Hearing Date | 21 October 2019 |
By Originating Summons No 1099 of 2019, the plaintiff seeks to set aside two adjudication determinations, namely Adjudication Determination No SOP/AA203/2019 (“AA 203”) and Adjudication Determination No SOP/AA245/2019 (“AA 245”). The plaintiff also seeks a declaration to serve a further payment claim on the defendant.
Having considered the parties’ submissions, I allow the plaintiff’s application. I agree with the plaintiff that the adjudicator in AA 203 was wrong to conclude that upon termination of the plaintiff’s employment under the subcontract (“the Sub-Contract”), the plaintiff was not entitled to submit a further payment claim and to enforce it by adjudication under the Building and Construction Industry Security of Payment Act (Cap 30B, 2006 Rev Ed) (“SOPA”). Given this finding in AA 203, it necessarily follows that the adjudicator in AA 245 was wrong in dismissing the plaintiff’s payment claim on the ground that the plaintiff was bound by the adjudicator’s determination in AA 203.
FactsThe plaintiff was one of the defendant’s subcontractors of a project at 79 Robinson Road, of which the defendant is the main contractor.1 The parties do not dispute that the defendant, by a notice of termination, terminated the plaintiff’s employment under the Sub-Contract2 pursuant to clause 33.2 of the Sub-Contract, which provides:3
At any time after the Project Director is satisfied that the Sub-Contractor has defaulted in respect of any of the grounds set out under Clause 33.1, the Project Director shall issue a Notice of Default to the Sub-Contractor specifying the default, and stating the Contractor’s intention to terminate the Sub-Contract unless the default is rectified within 7 days from the date of the said notice. If the Sub-Contractor fails to rectify the specified default within 7 days from the receipt of the Notice of Default, the Contractor shall be entitled, within any further notice to the Sub-Contractor,
to terminate the employment of the Sub-Contractor by issuing to the Sub-Contractor a Notice of Termination of [the] Sub-Contract. [emphasis added]
After the termination of the Sub-Contract, the plaintiff served Payment Claim No 12 (“PC 12”) on the defendant for the sum of $2,599,359.44.4 The defendant did not serve a payment response to PC 12.5 The plaintiff then proceeded to lodge AA 203.6 In its adjudication response, the defendant alleged,
The adjudicator dismissed AA 203 as he was found that PC 12 was improperly served on the defendant and alternatively, on jurisdictional grounds. The adjudicator referred to
Because the Project Director was
functus officio with respect to his certifying function, applying the reasoning inEngineering Construction (as set out above) andFES , no post-termination payment certification regime existed under the Sub-Contract. As such, the [plaintiff] no longer had an entitlement to serve a payment claim as the Project Director no longer had the power, under the Sub-Contract, to certify the same.
The adjudicator recognised that there was a conceptual difference between termination of a contract and the termination of one’s employment under a contract (
Before the adjudicator issued his AD for AA 203, the plaintiff served Payment Claim No 13 (“PC 13”), claiming the same sum as it did in PC 12. The defendant served its payment response, with its response amount stated as “nil”.10 The plaintiff did not apply to set aside AA 203 as it took the position that the adjudicator had based his determination on jurisdictional grounds and not on the substantive merits. AA 203 was therefore not binding in a subsequent adjudication under the SOPA. Hence, the plaintiff proceeded to commence AA 245.11 In its adjudication response to AA 245, the defendant argued,
… I accept the [defendant’s] submission and hold that the [plaintiff] is bound by the determinations of the issues determined by [the] learned adjudicator in the AD of SOP/AA203, in particular, in respect of the fundamental issue that upon termination of the Sub-Contract, the [plaintiff] was
not entitled to submit any further payment claim under the Sub-Contact and enforce it by adjudication under the [SOPA]. Consequently, it follows from the AD of SOP/AA 203 and section 21(1) of the [SOPA] that the [plaintiff] was also not entitled to submit PC 13 and PC13 is therefore invalid under section 10 of the [SOPA]. [emphasis in original]
The adjudicator accordingly dismissed AA 245.
The plaintiff’s case In the main, the plaintiff argues that the adjudicator in AA 203 was wrong in determining that the plaintiff was not entitled to issue a further payment claim under the Sub-Contract after termination. First, the adjudicator failed to give effect to Parliament’s intention that claims for work done or goods supplied before termination of a contract are valid.14 Second, that there are High Court decisions that were binding on the adjudicator to the effect that a claimant is entitled to serve payment claims and for them to be adjudicated upon notwithstanding termination.15 Finally, that the adjudicator for AA 203 had misconstrued and applied the principles in
The defendant contends that the application should be dismissed for the following reasons:
There are two issues to be determined:
Fundamentally,
In this case, there is no allegation that the final certificate has been issued, such that the project director is
The defendant’s notice of termination under clause 33.2 does not have the effect of terminating the entire Sub-Contract. It only serves to terminate the plaintiff’s
To continue reading
Request your trial-
CEQ v CER
...an accrued statutory entitlement to payment, which necessarily survives the termination.”: Stargood Construction Pte Ltd v Shimizu Corp [2019] SGHC 261 at [40] (“Stargood Construction”). The defendant then addressed the plaintiff’s submissions about Yau Lee’s applicability to the present ma......
-
Orion-One Residential Pte Ltd v Dong Cheng Construction Pte Ltd and another appeal
...v CER [2020] SGHC 70 (“the GD”) at [23]. One of the authorities relied on by the Judge was Stargood Construction Pte Ltd v Shimizu Corp [2019] SGHC 261, a decision which was reversed by this court in Shimizu Corp v Stargood Construction Pte Ltd [2020] 1 SLR 1338 (“Shimizu Corp”) subsequent ......
-
Shimizu Corporation v Stargood Construction Pte Ltd
...claim on Shimizu. Decision below The Judge framed two issues for determination (see Stargood Construction Pte Ltd v Shimizu Corporation [2019] SGHC 261 (“the Judgment”) at [11]): Whether the Project Director was functus officio when Stargood served PC 12 on Shimizu; and Whether Stargood was......
-
Contract administration
...at [1985] iCLr 298, which considers the third edition of the FiDiC red Book. 147 Stargood Construction Pte Ltd v Shimizu Corporation [2019] SGHC 261 at [14]–[16], per Vincent Hoong JC. 148 Clarke v Murray (1885) 11 VLr 817. See also paragraph 5.40. 364 ContraCt aDMiniStration 5.43 Finally, ......