CEQ v CER
Jurisdiction | Singapore |
Judge | Lee Seiu Kin J |
Judgment Date | 06 April 2020 |
Neutral Citation | [2020] SGHC 70 |
Court | High Court (Singapore) |
Docket Number | Originating Summons No 1412 of 2019 |
Published date | 14 May 2020 |
Year | 2020 |
Hearing Date | 16 January 2020 |
Plaintiff Counsel | Ng Hweelon and Tay Ming Xun (Veritas Law Corporation) |
Defendant Counsel | Chong Chi Chuin Christopher and Josh Samuel Tan Wensu (Drew & Napier LLC) |
Citation | [2020] SGHC 70 |
This was an application to set aside an adjudication determination made pursuant to the Building and Construction Industry Security of Payment Act (Cap 30B, 2006 Rev Ed)(“the Act”). While the factual matrix itself is not complex, this case presents an interesting opportunity to examine the propositions set forth in
The plaintiff was the owner and developer of a residential flat development at [address redacted] (“the Project”). The defendant was the main contractor for the Project between 1 February 2016 and 2 March 2017.
Background to the disputeThe defendant was neither the first nor the last contractor to take on the Project. It took over from a previous contractor pursuant to a novation agreement dated 1 February 2016. This previous contractor had been engaged by the plaintiff pursuant to a contract dated 19 May 2015 (“the Contract”)1, which was novated to the defendant in its entirety.2 Pursuant to cl 3.2 of the novation agreement, the defendant procured the issuance of a performance bond for $1,279,150.00 by [ABC] Pte Ltd (the “performance bond”).3
The Contract had four important features which will prove crucial to the first issue (see [12]). Firstly, the Contract incorporated the REDAS Design and Build Conditions of Main Contract (3
The defendant’s employment was terminated by the plaintiff on 2 March 2017. On the same day, the plaintiff called on the performance bond and engaged another contractor for the Project (“[DEF Contractor]”).7 [DEF Contractor] completed the project around August 2017.8 By then, the professional parties involved in the project such as the ER, quantity surveyor, architect and professional engineers, had concluded their employment. In fact, they had wrapped up by May 2017.9
Little was heard from the defendant for almost two years. Then, from 7 March 2019 onwards, the defendant began serving payment claims on a regular, monthly basis. These claims are detailed below:10
| | | |
| | | |
| | | |
| | | |
| | | |
| | | |
| | | |
| | | |
Payment Claim 25 and the adjudication determination arising from SOP/AA 318/2019 are the subject of the present application.
Issues to be determinedThree issues were raised in this application, but only the first two warrant discussion. The last issue was simply a non-starter. For that issue, the plaintiff’s contention was that the adjudicator had not given it an opportunity to explain itself.11 Specifically, the plaintiff took umbrage at (a) the adjudicator’s observation that [DEF Contractor] was hired on short notice with no competitive tenders12 and (b) the adjudicator’s findings that the cost of rectifying defects would not have been as high as the plaintiff claimed in its adjudication response.13 Having not had a “fair chance” to address these matters, the plaintiff submitted that the adjudication was a breach of natural justice and accordingly, invalid.14
This was a wild attempt at enlisting the court’s aid in overturning an unfavourable adjudication determination. The position at law is clear – the courts will not review the merits of an adjudication determination:
There could have been an argument that the adjudicator’s decision was tainted by extraneous (and therefore irrelevant) considerations such as concerns about the
This left me with the two main issues for this application:
The adjudicator determined, firstly, that the defendant was entitled to be paid for works done up to the date of termination. In support of this, he cited s 5 of the Act which expressly provides that “[a]ny person who has carried out any construction work, or supplied any goods or service, under a contract is entitled to a [progress payment]”. In the absence of any statutory or contractual bars, the fact that these payment claims were served two years after employment termination was inconsequential.19
He then considered the Court of Appeal’s decision in
His reasoning was fourfold. First, the Contract was a REDAS Form of Contract, not an SIA one.20 Second, there was no provision under the REDAS Form of Contract for the appointment of any
To this, the plaintiff submitted in the present proceedings that
The defendant, in reply, began by addressing the larger issue of whether a payment claim can be made for works prior to termination. It argued that such payment claims are certainly valid, and cited two...
To continue reading
Request your trial-
CEQ v CER
...Seiu Kin J: Introduction The present application flows from my previous decision in CEQ v CER [2020] SGHC 70 (“CEQ v CER”) involving the same parties. In that decision, I dismissed the application to set aside an adjudication determination made pursuant to the Building and Construction Indu......
-
Orion-One Residential Pte Ltd v Dong Cheng Construction Pte Ltd and another appeal
...for the proposition that payment claims made for work done prior to termination of employment are perfectly valid” – see CEQ v CER [2020] SGHC 70 (“the GD”) at [23]. One of the authorities relied on by the Judge was Stargood Construction Pte Ltd v Shimizu Corp [2019] SGHC 261, a decision wh......