Shimizu Corporation v Stargood Construction Pte Ltd
Jurisdiction | Singapore |
Judge | Sundaresh Menon CJ |
Judgment Date | 21 April 2020 |
Neutral Citation | [2020] SGCA 37 |
Date | 21 April 2020 |
Docket Number | Civil Appeal No 204 of 2019 |
Published date | 29 April 2020 |
Plaintiff Counsel | Yong Boon On, Amanda Koh Jia Yi and Lee Shu Qing (Eldan Law LLP) |
Defendant Counsel | Christopher Chong and Chen Zhihui (Drew & Napier LLC) |
Court | Court of Appeal (Singapore) |
Hearing Date | 02 March 2020 |
Subject Matter | Statutes and regulations,Building and Construction Law,Building and Construction Industry Security of Payment Act,Termination,Consequences |
Can a payment claim be served after termination of the contract? The intuitive response would be – it depends on the terms of the contract. After all, in
The dispute which led to this appeal concerned the submission of payment claims by the respondent, Stargood Construction Pte Ltd (“Stargood”) following the termination of a subcontract by the appellant, Shimizu Corporation (“Shimizu”). In determining the validity of the payment claims, the first port of call must necessarily be the terms of the contract, in particular the terms which governed the parties’ rights in the event of termination. Unfortunately, both parties did not pay sufficient attention to the terms of the subcontract dealing specifically with the consequences of a termination on account of a default by the subcontractor, Stargood. Reliance was instead placed on the recent amendment to s 2 of the SOPA in defining a contract to include “a construction contract … that has been terminated”. In the course of the hearing, the parties were directed to address this court on the effect of the termination provisions in relation to the right to submit payment claims post termination and how such provisions should operate in light of the recent SOPA amendment.
It was suggested that the SOPA was designed to provide a “dual railroad track system” such that the party seeking payment has the option to elect between the statutory and contractual entitlement to payment. Accordingly, a subcontractor can validly submit a payment claim under the SOPA notwithstanding the fact that such a payment claim would be contrary to the terms of the contract. In other words, the SOPA can override the express terms of the contract. However, in
The other intuitive response following the termination of a contract is that the person tasked with the certifying function might be rendered
Given this background, there are two issues which we shall address in this Judgment:
We begin by examining the facts of the case and the Judge’s reasoning.
FactsShimizu was engaged as the main contractor for a project located at 79 Robinson Road, Singapore. Stargood was engaged as one of Shimizu’s subcontractors for the project pursuant to a letter of acceptance dated 8 February 2018, which incorporated with amendments the Real Estate Developers’ Association of Singapore Design and Build Conditions of Contract (3rd Ed, 2013) (“the Subcontract”).
Under cl 6 of the Subcontract, Shimizu appointed a project director (“the Project Director”) to act on its behalf in respect of matters relating to the Subcontract, including the certification of progress payments. Clause 28 of the Subcontract provided for payment claims to be submitted by Stargood to the Project Director, who would in turn be responsible for issuing a payment response. The amount reflected in the payment response would be what was due from Shimizu to Stargood.
Following certain alleged breaches of the Subcontract on the part of Stargood, Shimizu issued a notice of default on 4 March 2019. This was followed on 22 March 2019 by an exercise of its termination rights under cl 33.2 of the Subcontract, which reads:
At any time after the Project Director is satisfied that the Sub-Contractor has defaulted in respect of any of the grounds set out under Clause 33.1, the Project Director shall issue a Notice of Default to the Sub-Contractor specifying the default, and stating the Contractor’s intention to terminate the Sub-Contract unless the default is rectified within 7 days from the date of the said notice. If the Sub-Contractor fails to rectify the specified default within 7 days from the receipt of the Notice of Default, the Contractor shall be entitled, without any further notice to the Sub-Contractor, to terminate the employment of the Sub-Contractor by issuing to the Sub-Contractor a Notice of Termination of [the] Sub-Contract.
On 30 April 2019, after termination of the Subcontract, Stargood served Payment Claim No 12 (“PC 12”) on Shimizu for the sum of $2,599,359.44 as payment for works done up till April 2019. Shimizu did not serve a payment response to PC 12. Stargood then proceeded to lodge Adjudication Determination No SOP/AA203/2019 (“AA 203”) on 4 June 2019. In its adjudication response, Shimizu claimed that: (a) PC 12 had not been properly served; and (b) PC 12 was outside the purview of the SOPA.
It appears that Stargood was alive to the possibility that PC 12 had been improperly served on Shimizu. It then elected to serve Payment Claim No 13 (“PC 13”) on 31 May 2019 prior to the commencement of AA 203, which was for all intents and purposes identical to PC 12, save that the claimed sum of $2,599,359.44 was stated to be for works done up till May 2019. Shimizu’s payment response to PC 13 served on 21 June 2019 stated the response amount as “nil”.
AA 203 was dismissed by the adjudicator on 27 June 2019 on two distinct grounds:
Stargood subsequently lodged Adjudication Determination No SOP/AA245/2019 (“AA 245”) on 5 July 2019 for the adjudication of PC 13. This was dismissed by the adjudicator on 6 August 2019 as he found that Stargood was bound by the determination in AA 203.
Following this, Stargood filed OS 1099 of 2019 (“OS 1099”) to set aside the adjudication determinations in AA 203 and AA 245. It also sought a declaration that it was entitled to serve a further payment claim on Shimizu.
Decision below The Judge framed two issues for determination (see
The Judge found that Shimizu had only terminated Stargood’s employment, rather than the entire Subcontract. He then found that the effect of the termination of Stargood’s employment meant that it could continue to avail itself of the payment certification process (Judgment at [13]–[16]). The Judge also found that the SOPA provided Stargood with an independent right to progress payments, even if the entire Subcontract had been terminated (Judgment at [18]–[21]). In doing so, the Judge reasoned that an interpretation holding that the SOPA did not apply to works done before termination of the Subcontract would place subcontractors and suppliers at the mercy of main contractors or employers, who could resist or delay payment by terminating the underlying contract on tenuous grounds. The Judge also thought it significant that the Building and Construction Industry Security of Payment (Amendment) Bill (No 38 of 2018) (“the 2018 Amendments”) amended the definition of a “contract” under the SOPA to include a “construction contract or a supply contract that has been terminated” (Judgment at [21]–[24]). The Judge thus set aside both adjudications and granted a declaration that Stargood was entitled to serve further payment claims on Shimizu for work done prior to termination of the subcontract (Judgment at [33]).
Parties’ cases Appellant’s case Shimizu argued that this court’s decision in
To continue reading
Request your trial-
Diamond Glass Enterprise Pte Ltd v Zhong Kai Construction Co Pte Ltd
...primary source for the interim payment procedure and obligations will be the contract (see Shimizu Corp v Stargood Construction Pte Ltd [2020] 1 SLR 1338 at [2]). Where the contract is deficient or silent, the provisions of the SOPA, like ss 5–8 and ss 10–12, will apply subject to the terms......
-
Orion-One Residential Pte Ltd v Dong Cheng Construction Pte Ltd and another appeal
...Pte Ltd v Shimizu Corp [2019] SGHC 261, a decision which was reversed by this court in Shimizu Corp v Stargood Construction Pte Ltd [2020] 1 SLR 1338 (“Shimizu Corp”) subsequent to the release of the judgment below. In Shimizu Corp at [2], we observed that “[i]n determining the validity of ......
-
Frontbuild Engineering & Construction Pte Ltd v JHJ Construction Pte Ltd
...SLR 791 (refd) SEF Construction Pte Ltd v Skoy Connected Pte Ltd [2010] 1 SLR 733 (distd) Shimizu Corp v Stargood Construction Pte Ltd [2020] 1 SLR 1338 (folld) Tan Cheng Bock v AG [2017] 2 SLR 850 (refd) Woon Brothers Investments Pte Ltd v MCST Plan No 461 [2011] 4 SLR 777 (refd) Legislati......
-
Can You Submit An Adjudication Application On A Payment Claim That Was Presented Just Before The Contract Was Terminated?
...Far East Square Pte Ltd v Yau Lee Construction (Singapore) Pte Ltd [2019] 2 SLR 189, Shimizu Corp v Stargood Construction Pte Ltd [2020] 1 SLR 1338 ("Shimizu") and Orion-One Residential Pte Ltd v Dong Cheng Construction Pte Ltd and another appeal [2021] 1 SLR 791 (at [39] - [42]), and disti......
-
Building and Construction Law
...Pte Ltd v JHJ Construction Pte Ltd [2021] 4 SLR 862 at [46], citing the holding of Shimizu Corp v Stargood Construction Pte Ltd [2020] 1 SLR 1338 at [30]. 97 Frontbuild Engineering & Construction Pte Ltd v JHJ Construction Pte Ltd [2021] 4 SLR 862 at [46], citing the Court of Appeal's state......
-
Building and Construction Law
...Asia Pacific Pte Ltd [2020] 2 SLR 1125 at [61]. 114 Façade Solution Pte Ltd v Mero Asia Pacific Pte Ltd [2020] 2 SLR 1125 at [64]. 115 [2020] 1 SLR 1338. 116 Adjudication Determination No SOP/AA203/2019. 117 Adjudication Determination No SOP/AA245/2019. 118 [2019] 2 SLR 189. 119 Far East Sq......