CEX v CEY and another
Court | High Court (Singapore) |
Judge | Lee Seiu Kin J |
Judgment Date | 18 May 2020 |
Neutral Citation | [2020] SGHC 100 |
Citation | [2020] SGHC 100 |
Published date | 22 May 2020 |
Plaintiff Counsel | Tan Shien Loon Lawrence, Chan Ying Keet Jasmine and Poonaam Bai (Eldan Law LLP) |
Defendant Counsel | Phua Cheng Sye Charles (Comlaw LLC),Yeo Teng Yung Christopher (Legal Solutions LLC) |
Docket Number | Originating Summons No 933 of 2019 |
Hearing Date | 15 January 2020 |
Date | 18 May 2020 |
Subject Matter | Building and Construction Industry Security of Payment Act (Cap 30B, 2006 Rev Ed),Building and Construction Law,Setting aside adjudication determination,Unconscionability |
CEY is the unfortunate developer for six strata detached houses at [redacted] (“the Project”). It has faced numerous delays in construction works and the present application is not the first one that it has resisted. Given its misfortunes, CEY could have been forgiven for being anxious, frustrated and even impatient with further delays in the construction. But when it pushed CEX, its main contractor, to proceed with illegal construction works and terminated CEX’s employment for its failure to do so, any sympathy for CEY quickly evaporated. In the circumstances, I found that CEY had let its impatience get the best of it and that it had acted unconscionably in calling on the performance bond. Accordingly I granted CEX an injunction, restraining CEY from calling on the performance bond. Though CEX brought this application on both grounds of fraud and unconscionability, I based my decision primarily on the unconscionability exception. I now set out my reasons in full.
FactsCEX took over the project as its main contractor on 9 May 20171 when it accepted a letter of award dated 4 May 2017.2 Pursuant to cl 9.1 of the letter of award,3 CEX procured a performance bond from CEZ in favour of CEY.4
It suffices at this juncture to say that the project was beset with delays. CEY took the view that the delays were attributable to CEX’s persistent failure to carry out the contract with due diligence and expedition. CEX argued that many of the delays were beyond its control and pointed to, amongst other things, the hospitalisation and subsequent death of Mr. John Seah, the architectural qualified person for the Project (“Mr. Seah”).
Mr. Seah took ill and was hospitalized on 7 January 2019. 5 In a letter dated the same day, he attempted to authorise one Mr. Ng Hoe Theong (“Mr Ng”) to “cover [his] duties”.6 On that authority, Mr. Ng issued a notice to proceed with due diligence and due expedition (“the Notice to Proceed”) to CEX. Mr. Seah himself would later pass away on 24 January 2019.7 There was no new architectural qualified person formally appointed until 27 February 2019.8
Notwithstanding Mr. Seah’s demise on 24 January 2019, Mr. Ng would later issue a termination certificate “on behalf of [Mr. Seah]”9 on 19 February 2019, stating that CEX had “failed and [was] still failing to proceed with due diligence or expedition in its Works”. Relying on the termination certificate and on account of “[CEX’s] persistent failure to carry out the Contract works with due diligence and expedition”,10 CEY issued a notice of termination on 20 February 2019.11 CEX denied any breaches12 and promptly served a notice of arbitration the following day, claiming that, amongst other things, its employment had been wrongfully terminated.13
CEY later sought to recover losses arising from CEX’s alleged breaches of contract. These complaints were collated and conveyed in a letter of demand seeking S$3,921,039.68, such sum being CEY’s estimated expenses for hiring a replacement contractor.14 CEX refused to pay the sum15 and CEY subsequently called on the performance bond on 19 July 2019.16
Issues to be determinedThe first issue concerns the statutory interpretation of s 6(5) of the Building Control Act (Cap 29, 1999 Rev Ed) (“the Act”). In particular, the question is whether the holder of a permit to carry out structural works ceases to be a qualified person should the permit holder take ill and become otherwise incapacitated (“The Interpretation Issue”). This is relevant in ascertaining whether it was illegal for CEX to carry on construction works when Mr. Seah took ill on 7 January 2019.
The second issue is whether the call on the performance bond should be restrained (“The Performance Bond Issue”). The nature of the performance bond and its terms were not disputed. This was an on-demand performance bond. There was no contention that the demand was being technically defective. The issue was whether an injunction restraining the call ought to be granted on the ground of unconscionability.
Applicable legal principles The unconscionability exception For a while, there was some uncertainty about the unconscionability exception in Singapore. Following
The judicial dichotomy was settled by the Court of Appeal in
Instructive as these propositions are, uncertainty still lingers in the jurisprudence. The precise scope of unconscionability remains undefined. The courts have of course, sensibly, refused to provide an exhaustive definition:
I pause to clarify three things about the factual matrices I have just described in the paragraph above. First, this is not an exhaustive list of circumstances where unconscionability arises. The list is not and will probably never be closed. Indeed, the present case involves a factor that is not captured by any of the above listed categories (see [68]). These factors are simply circumstances that have recurred often enough. Second, no single factor is dispositive. The weight attached to each factor will vary from case to case depending on the strength of the evidence. Every case must be examined with careful regard to the
To continue reading
Request your trial-
Sulzer Pumps Spain, SA v Hyflux Membrane Manufacturing (S) Pte Ltd and another
...fides, but this is meant to cover the various formulations of unconscionability. Guidance can also be drawn from CEX v CEY and another [2020] SGHC 100, which has helpfully undertaken a survey of the cases where a bond has been restrained on grounds of unconscionability, and found that uncon......
- Damai City Sdn Bhd v McC Overseas (M) Sdn Bhd& Other Appeals
-
First Construction & Engineering Pte Ltd v Yim Hon Yuen
...the burden of proving a strong prima facie case of unconscionability. The framework to be applied was outlined in CEX v CEY and another [2021] 3 SLR 571. In the plaintiff’s written submissions, it was relying on both grounds of fraud and unconscionability in its application to restrain the ......
-
Banking Law
...Pte Ltd [2020] 2 SLR 955 at [22]. 84 Samsung C&T Corp v Soon Li Heng Civil Engineering Pte Ltd [2020] 2 SLR 955 at [58]. 85 CEX v CEY [2021] 3 SLR 571. 86 Cap 29, 1999 Rev Ed. 87 CEX v CEY [2021] 3 SLR 571 at [11]. 88 CEX v CEY [2021] 3 SLR 571 at [20]. 89 CEX v CEY [2021] 3 SLR 571 at [11]......
-
Building and Construction Law
...OGSP Engineering Pte Ltd [2020] SGHC 165 at [120]. 29 Comfort Management Pte Ltd v OGSP Engineering Pte Ltd [2020] SGHC 165 at [126]. 30 [2021] 3 SLR 571. 31 CEX v CEY [2021] 3 SLR 571 at [10]; JBE Properties Pte Ltd v Gammon Pte Ltd [2011] 2 SLR 47 at [11]. 32 CEX v CEY [2021] 3 SLR 571 at......