Sulzer Pumps Spain, SA v Hyflux Membrane Manufacturing (S) Pte Ltd
Jurisdiction | Singapore |
Judge | Aedit Abdullah J |
Judgment Date | 17 June 2020 |
Neutral Citation | [2020] SGHC 122 |
Year | 2020 |
Date | 17 June 2020 |
Published date | 23 June 2020 |
Hearing Date | 27 February 2020,23 October 2019 |
Plaintiff Counsel | Anparasan s/o Kamachi and Sumyutha Sivamani (WhiteFern LLC) |
Defendant Counsel | Sandosham Paul Rabindranath and Joan Peiyun Lim-Casanova (Cavenagh Law LLP),the second respondent unrepresented. |
Court | High Court (Singapore) |
Citation | [2020] SGHC 122 |
Docket Number | Originating Summons No 1323 of 2019 |
This is an application to discharge an
Having heard the parties at the
The first respondent was the sub-contractor for its related company, Hydrochem Pte Ltd, for a project concerning the design and construction of a desalination plant in Oman (the “project”).4 The owner of the project is a company owned by the Oman government (the “project owner”).5 The first respondent in turn engaged the applicant as its sub-contractor, through two purchase orders in 2015, which incorporated a term sheet, a document entitled “Section 2 - General Terms and Conditions” (the “General Terms and Conditions”), and some exhibits (collectively the “contract”).6 Pursuant to the contract, the applicant was to supply and install pumps for the first respondent.7
Clause 10 of the General Terms and Conditions is titled “Warranty” and sets out the warranty obligations of the applicant. Under cl 10.6 of the General Terms and Conditions, the applicant was to provide an unconditional first demand bank guarantee to the first respondent as security for its warranty obligations owed to the first respondent.8 In September 2017, the applicant obtained the guarantee from the second respondent in favour of the first respondent, and delivered the guarantee to the first respondent.9 The guarantee took the form of an unconditional first demand bond.10
The applicant manufactured the pumps, delivered them to the first respondent, and installed them under the first respondent’s supervision.11 However, the first respondent soon encountered difficulties with the pumps, which repeatedly failed between November 2017 and May 2019.12 The first respondent alleges that the recurring failure of the pumps was caused by design flaws which were only rectified by the applicant in May 2019, and that the applicant was hence in breach of its warranty obligations.13 In contrast, the applicant denies the existence of such design flaws, contending instead that the failures were caused by the first respondent’s use of the pumps outside of the recommended and permitted flow and speed range.14
In October 2019, the first respondent called on the bond.15 The applicant tried to negotiate with the first respondent by suggesting that the first respondent withdraw its call on the bond in exchange for an extension of the same. However, the first respondent did not respond favourably to this proposal.16 The applicant thus made an
I heard the applicant’s
However, parties did not come back before me until several months later. A part of the lapse of time was presumably caused by the first respondent’s change in solicitors.23 It is unclear if the delay might have been caused by issues arising out of Hyflux’s restructuring.
The first respondent’s arguments to discharge the injunctionThe first respondent raises some jurisdictional and preliminary arguments against the injunction.
First, an injunction cannot be free standing but there must be an underlying cause of action; here, the applicant’s originating summons contained no underlying cause of action.24
Second, the applicant breached its duty to make full and frank disclosure of all material facts to the court at the
In addition, the applicant had blatantly misrepresented a number of material facts, including: that the applicant knew the basis of the first respondent’s calling on the bond; that the first respondent failed to challenge the applicant’s technical findings for the malfunctioning of the pumps; that the first respondent’s emails did not explain why the pump failures were due to the applicant’s fault; and that the first respondent had accepted that the pump failures were not covered by the applicant’s warranty obligations.28 The first respondent argues that all of these allegations were untrue.
Third, under s 12A of the IAA, the court may grant an interim injunction if it is for the purpose of or in relation to an arbitration.29 However, there was no arbitration commenced at the time the
Fourth, the applicant did not come to court with clean hands as it commenced the proceedings in repudiatory breach of the arbitration agreement.31
Fifth, no notice of the
Based on the above, the first respondent argues that the injunction should be discharged even before dealing with the substantive merits of the injunction.34
Further or alternatively, the first respondent argues that the injunction should also be discharged for substantive reasons.35 The first respondent argues that it is undisputed that the bond is an unconditional first demand bond.36 Such bond has to be paid on demand by the obligor to the beneficiary, even without proof of default.37 The courts should be slow to interfere with contractual arrangements freely entered into by the parties (
On the facts, there was no unconscionability.41 The correspondence and other documentary evidence showed that the first respondent genuinely and consistently believed that the applicant had breached its warranty obligations;42 the first respondent had consistently maintained that the pump failures were due to design flaws caused by the applicant. There was no evidence of
The applicant accepted that it is settled law that the courts would only intervene to prevent a beneficiary from calling on a performance guarantee if it could be shown that the call was either fraudulent or unconscionable (
Under the unconscionability exception, an injunction should be granted if it would be unfair for the beneficiary to realise his security pending the resolution of the substantive dispute (
To continue reading
Request your trial-
Tanoto Sau Ian v USP Group Ltd
...470 (folld) Siskina v Distos Compania Naviera SA [1979] AC 210 (refd) Sulzer Pumps Spain, SA v Hyflux Membrane Manufacturing (S) Pte Ltd [2020] 5 SLR 634 (folld) Tinkler v Revenue and Customs Commissioners [2021] 3 WLR 697 (refd) Virgin Atlantic Airways Ltd v Zodiac Seats UK Ltd [2014] AC 1......
-
First Construction & Engineering Pte Ltd v Yim Hon Yuen
...not. For the unconscionability exception, it has been established in Sulzer Pumps Spain, SA v Hyflux Membrane Manufacturing (S) Pte Ltd [2020] 5 SLR 634 that it applies to situations where the beneficiary’s conduct is sufficiently reprehensible to justify an injunction but does not amount t......
-
Banking Law
...SLR 571 at [11]. 88 CEX v CEY [2021] 3 SLR 571 at [20]. 89 CEX v CEY [2021] 3 SLR 571 at [11]. 90 CEX v CEY [2021] 3 SLR 571 at [22]. 91 [2020] 5 SLR 634. 92 Sulzer Pumps Spain SA v Hyflux Membrane Manufacturing (S) Pte Ltd [2020] 5 SLR 634 at [35]–[40]. 93 Sulzer Pumps Spain SA v Hyflux Me......
-
Building and Construction Law
...Construction Industry Payments Act 2004 (Qld). 55 Samsung C&T Corp v Soon Li Heng Civil Engineering Pte Ltd [2020] 2 SLR 955 at [58]. 56 [2020] SGHC 122. 57 Sulzer Pumps Spain SA v Hyflux Membrane Manufacturing (S) Pte Ltd [2020] SGHC 122 at [31]. 58 Sulzer Pumps Spain SA v Hyflux Membrane ......