Beow Hock Engineering Pte Ltd v Goh Eng Huat and another
Jurisdiction | Singapore |
Judge | James Leong Kiu Yiu |
Judgment Date | 17 February 2023 |
Neutral Citation | [2023] SGDC 31 |
Court | District Court (Singapore) |
Docket Number | District Court Originating Application 78 of 2022 |
Hearing Date | 19 January 2023,20 January 2023 |
Citation | [2023] SGDC 31 |
Year | 2023 |
Plaintiff Counsel | Samuel Pang and Jonathan Lim (Dentons Rodyk & Davidson LLP) |
Defendant Counsel | Chester Su (Drew & Napier LLC),Christine Chiam (Titanium Law Chambers LLC) |
Subject Matter | Building and Construction Law,Building and construction related contracts,Guarantees and bonds,Credit and Security,Performance bond |
Published date | 13 June 2023 |
This is the contractor claimant’s application to restrain the first defendant beneficiary’s call on a performance bond (“bond”) issued by the second defendant. The bond was issued with respect to works that the first defendant homeowner engaged the claimant contractor to undertake under a Letter of Award (“LOA”) dated 5 October 2020 for the continuation of the proposed erection of a 3-Storey Envelope Control Detached House on the first defendant’s property. In response to the call on the bond for $ 147,988.80 on 12 September 2022, the claimant filed the present application and DC/SUM 2924/2022 (“SUM 2924”) for an interim injunction against the first and second defendants. SUM 2924 was heard in the presence of all parties and granted by the Learned District Judge Tan May Tee on 23 September 2022.
After hearing submissions from counsel for the claimant and the first defendant (with counsel for the second defendant in attendance content to abide by the decision of the court), I find myself in broad agreement with the submissions of counsel for the claimant on the authority of the High Court decision in
Under the LOA, the value of the works was $ 1,479,988.00, the designated Architect was Mr Freddie H K Chia (“Mr Chia”) of Freddie H K Chia Architects while the Quantity Surveyor was BKG Consultants Pte Ltd. The LOA provided that the form of contract would be the Singapore Institute of Architects’ Articles and Conditions of Building Contract (Without Quantities) (2016) – 1st Edition (Updated 2017) (“SIA Conditions”).
Pursuant to the LOA, the claimant was engaged by the first defendant in October 2020 to take over the building works from the first defendant’s previous contractor following the demise of Mr Juan Peck Foon (“Mr Juan”), who was the Design Consultant for the project to redevelop the first defendant’s existing family home. The claimant had been recommended to the first defendant by Ms Frances Ng Poh Joo, the wife of Mr Juan who agreed to assist and was involved in the project between July 2020 and late February 2021.
The Building and Construction Authority Permit to Commence Works (“BCA Permit”) for the project was issued on 12 November 2020. It listed Mr Chia as the Qualified Person for Architectural Work (“Architectural QP”).
The LOA dated 5 October 2020 provides for a contract period of eight (8) calendar months from the date of the BCA Permit. Based on a Final Quotation dated 7 October 2020, the claimants say it should be nine (9) calendar months. Given that the LOA was signed on 5 October 2020, eight (8) months appear to be what was contractually agreed although nothing turns on this for present purposes since both dates have been clearly exceeded.
This was followed by a series of events that culminated in the first defendant’s call on the bond and termination of the contract on 12 September 2022. While parties dispute the effect of the correspondence, they do not dispute the fact of the correspondence as outlined below.
On 9 September 2022, Mr Ho issued a Termination Certificate stating that the owners were entitled to terminate the contract.
As outlined in the claimant’s written submissions and elaborated at the hearing, the claimants submit that:
To continue reading
Request your trial