Bocotra Construction Pte Ltd and Others v Attorney General (No 2)

JurisdictionSingapore
JudgeKarthigesu JA
Judgment Date23 May 1995
Neutral Citation[1995] SGCA 50
Docket NumberCivil Appeal No 168 of 1994
Date23 May 1995
Year1995
Published date19 September 2003
Plaintiff CounselMichael Khoo, Josephine Low and Cheah Kok Lim (Michael Khoo & BB Ong) and Ho Chien Mien (Allen & Gledhill)
Citation[1995] SGCA 50
Defendant CounselLee Seiu Kin and Lionel Yee (Attorney General's Chambers)
CourtCourt of Appeal (Singapore)
Subject MatterPrinciple of autonomy of guarantees from underlying contract,Need to establish clear case of fraud or unconscionability,Call for payment on bank guarantee,Credit and Security,Interim injunction to restrain intended call,Civil Procedure,Fraud or unconscionability as exception,Guarantees and indemnities,Injunction to restrain intended call on bank guarantee,Whether balance of convenience test applied in cases involving bank guarantees,Guarantee serving function of performance bond,Interim injunction,Whether guarantee properly construed to be a demand bond,Availability of interim declaratory relief in lieu of injunction,Performance bond,Injunctions,Construction of guarantee,Whether balance of convenience test relevant,Whether proof of default in performance of contract required before guaranteed sum payable,Whether court could examine disputes relating to underlying contract

Cur Adv Vult

This is an appeal against the order of Goh Joon Seng J made on 28 October 1994, dismissing the appellants` application for declaratory relief pursuant to an order made in arbitration proceedings between the parties on 25 February 1994. In a related matter which was concurrently heard before this Court of Appeal as CA 132/94 [reported in [1995] 2 SLR 523 ] (also referred to hereinafter as `the related appeal`), the learned judge had held that the interim order relating to the letter of guarantee No 957/88/875 made by Tun Mohamed Suffian, the arbitrator appointed, was not binding on the respondent because the award was invalid or void. At the conclusion of the hearing, we reserved judgments on both appeals. The factual background in respect of both appeals was similar, and we will refer to the facts as set out in our judgment in respect of CA 132/94. The abbreviated terms and references used in that judgment are also employed here.

The proceedings from which this appeal arose

The present appeal, like the related appeal, arose from a dispute relating to the arbitrator`s order on 25 February 1994 in the following terms:

... I hereby declare that the respondent is not entitled to demand or otherwise take any steps to call for payment of any sum under the letter of guarantee No 957/88/875 dated 13 August 1988 until such time as the respondent`s entitlement to make such or any call for payment under the said letter of guarantee has been determined in this arbitration.



On 22 March 1994, the appellants filed an originating summons praying for declaratory relief in terms and effect which reflect those provided by the arbitrator`s order.
The appellants prayed for the following reliefs:

(1) A declaration that the defendant whether acting by itself, its officers, servants or agents of any of them or otherwise howsoever is not entitled until after final award in the arbitration between the abovenamed parties has been made and published to the parties to:

(a) give, furnish or provide any written notice pursuant to the letter of guarantee No 957/88/874 for $31,288,888.80 (the guaranteed sum) dated 13 August 1988 issued by Standard Chartered Bank (the guarantee) to Standard Chartered Bank; and

(b) claim, collect, obtain, acquire or receive the guaranteed sum or any part thereof from the Standard Chartered Bank, its officers, servants or agents or otherwise howsoever.

(2) A declaration that on the true construction of the guarantee and in the circumstances the guaranteed sum or any part thereof is payable only on proof by the defendant of the plaintiffs` default under the contract dated 27 November 1987 made between the plaintiffs and the defendant.

...

(6) A declaration that the arbitrator was and is empowered to make an order pursuant to the agreed SIAC (sic) rules and particularly r 18(g) that the money payable under the bank`s letter of guarantee is property or a thing under the control of the defendant pending the final award and r 20.5.



The present proceedings were heard by Goh Joon Seng J immediately after the conclusion of the hearing in the related appeal.
Upon hearing the parties in that appeal, Goh Joon Seng J declared that the order of the arbitrator did not bind the PWD, founding his decision on three grounds: the arbitrator was not seised of the dispute relating to the guarantee, interim declaratory relief was unknown in law, and r 18(g) which the arbitrator relied on as the source of his power to make the order had been misinterpreted by the arbitrator. Consistent with that ruling and his grounds thereof, in dealing with the present appeal, Goh Joon Seng J dismissed the above prayers sought by the appellants and awarded the respondent the costs of both the proceedings.

The appeal

The issues which required consideration in the present appeal did not correspond entirely with those which arose in the related appeal, notwithstanding that the factual background was similar. Where appropriate, we shall make the relevant references to our reasons in respect of the related appeal. In this judgment, we shall deal with the appeal according to the specific prayers sought by the appellants.

(1) Prayer 2 - proof of default as a precondition for a call

In relation to prayer 2, the question was whether proof of the appellants` default in performance was required before the guaranteed sum (or part thereof) under the contract would become payable. The judge below declined to declare that this was the true construction of the guarantee. He held that the guarantee was not subject to any finding of default in performance on the appellants` part by the arbitrator. The judge opined that the guarantee was essentially a demand bond under which the bank would have to pay on demand the amount demanded up to the limit of the guaranteed sum.

On appeal, the appellants contended that the judge below had erred in so holding.
First, it was contended that the judge had failed to consider the relevance of the fact that the recital to the guarantee referred to cl 9 of the conditions. The recital states:

... whereas by cl 9 of the conditions of contract, the contractor must provide a bank guarantee for a sum equal to ten per cent (10%) of the contract sum, for the due performance of the contract.



On this basis, the appellants submitted that the contract itself had qualified the right of the respondent to make a demand on the guarantee.
Second, cl 1 contained an agreement by the bank to pay the respondent `forthwith on demand any sums not exceeding in the aggregate Singapore Dollars Thirty One Million Two Hundred and Eighty Eight Thousand Eight Hundred and Eighty Eight Cents Eighty only ($31,288,888.80) ... upon receipt of any written notice...`. Clause 5 in turn subjected the guarantee to a condition that a claim had to be made upon the bank by notice in writing, `within six (6) months from the expiry of this guarantee`. On this basis, the appellants submitted that on its face, this is not an unqualified absolute right to demand. Moreover, the determination of the validity of the guarantee was crucial for the purpose of ascertaining whether the respondent has made a claim within the inbuilt limitation period of six months under cl 5. Clause 4 specifies thus:

This guarantee is valid from the date hereof up to the date the engineer issues the maintenance certificate in accordance with cl 55 of the conditions of the contract.



The appellants therefore appeared to maintain that on account of the necessity to refer to the conditions to ascertain the expiry date of the guarantee, the contract and the guarantee were inextricably interlinked and should not be treated as independent contracts.


Finally, it was contended that cl 2 did not make the guarantee an unconditional one.
It would only operate after the receipt of the money following the call and must be read to refer to the determination of quantum by the respondent, rather than to the issue of liability. Clause 2 states:

On receipt of the guaranteed sum from us, you shall be entitled to utilized (sic) it to satisfy such liability of the contractor as you may determine, arising from or due to the default of the contractor. The balance of the guaranteed sum, if any, shall be refunded to us.



In short, the appellants contended that the guarantee should not be construed as a demand bond as its terms indicate otherwise.


A preliminary point was raised by the respondent in the written case, raising jurisdictional objections to the appellants` locus standi in such an action.
It was submitted that the guarantee is an independent contract between the bank and the respondent, the appellants not being parties to the guarantee. As no arguments in this respect were raised before us at the hearing of the appeal, we shall address our minds only to the submissions as presented.

As regards the substantive issues arising under prayer 2, some analysis of the terms of the guarantee was required at the outset.
It was not disputed that the guarantee was, in substance, a performance bond which had been issued by the bank to secure the appellants` due performance under the contract. The tendency of the English courts has been to treat performance bonds as unconditional provided there is a clear statement that the amount guaranteed is payable by the bank simply upon a written demand being made, even though there may be some indications to the contrary elsewhere in the document. In the present case, the judge below adopted the reasoning of the court in . In this case, the bank undertook `to pay the said amount on your written demand in the event that the supplier fails to execute the written performance`. The court held that the reference to the stipulated `event` of default in execution did not alter the fact that the money would become payable upon a written demand being made. The beneficiary of the bond was under no obligation to show a failure to perform by the supplier in order to call for payment. It may be noted that the court held this to be an unconditional performance bond despite the absence of any provision that contractual liability (or default) was to be determined by the beneficiary.

In , Staughton LJ opined that in cases of ambiguity there was `a bias or (rebuttable) presumption in favour of the construction which holds a performance bond to be conditioned upon documents rather than facts` (at p 500).
In the case of unconditional bonds, this would simply require the making of a written demand rather than proof of the facts, for example, of default or failure to perform. Ultimately, this raises a question of construction, and of examining the intent of the document. This approach is clearly borne out in numerous cases, including the two cited above. A recent authority for this proposition emanating from a source closer to home is that of the Malaysian Supreme Court in . Peh Swee Chin SCJ, delivering the court`s judgment, opined...

To continue reading

Request your trial
59 cases
  • New Civilbuild Pte Ltd v Guobena Sdn Bhd and Another
    • Singapore
    • High Court (Singapore)
    • 29 February 2000
    ... ... were required to design and complete the construction of the project by 31 July 1997. The main contract was ... Under cl 4.0 of the General Specifications of Materials and Workmanship (see 1AB85), ... there held that it was clear from the decision in Bocotra Construction Pte Ltd v A-G (No 2) [1995] 2 SLR 733 ... ...
  • GHL Pte Ltd v Unitrack Building Construction Pte Ltd and Another
    • Singapore
    • Court of Appeal (Singapore)
    • 14 August 1999
    ... ... The starting point is this court`s decision in Bocotra Construction Pte Ltd v A-G (No 2) [1995] 2 SLR 733 ... The facts of ... The Director-General of the Public Works Department (`PWD`) appointed the plaintiffs as ... initiated proceedings against the PWD (represented by the Attorney General) seeking, inter alia , a declaration that the PWD was not ... ...
  • Sin Kian Contractor Pte Ltd v Lian Kok Hong and Another
    • Singapore
    • High Court (Singapore)
    • 31 July 1999
    ...for the owner to call on the guarantee or to receive payment under it: at [25], [27], [28] and [31]. Bocotra Construction Pte Ltd v AG [1995] 2 SLR (R) 262; [1995] 2 SLR 733 (folld) Brody, White and Co Inc v Chemet Handel Trading (S) Pte Ltd [1992] 3 SLR (R) 146; [1993] 1 SLR 65 (refd) Carg......
  • BS Mount Sophia Pte Ltd v Join-Aim Pte Ltd
    • Singapore
    • Court of Appeal (Singapore)
    • 9 May 2012
    ...bond from calling on the bond (see, eg, the decisions of this court in Bocotra Construction Pte Ltd and others v Attorney-General [1995] 2 SLR(R) 262 (“Bocotra”) and JBE). In so far as the rationale for adopting unconscionability as a relevant ground is concerned, the following observations......
  • Request a trial to view additional results
12 books & journal articles
  • RESTRAINING A CALL ON A PERFORMANCE BOND: SHOULD ‘FRAUD OR UNCONSCIONABILITY’ BE THE NEW ORTHODOXY?
    • Singapore
    • Singapore Academy of Law Journal No. 2000, December 2000
    • 1 December 2000
    ...though there may be some contrary indications elsewhere in the document: Bocatra Construction Pte Ltd and Ors v Attorney General (No 2)[1995] 2 SLR 733, at 738; Esal (Commodities) Ltd v Oriental Credit Ltd[1985] 2 Lloyd’s Rep 546, at 549. Ultimately, it is a question of construction of the ......
  • Security for performance
    • United Kingdom
    • Construction Law. Volume II - Third Edition
    • 13 April 2020
    ...[2016] hCa 47 at [8], per French CJ. For Singaporean authorities, see: Bocotra Construction Pte Ltd v Attorney General (No 2) [1995] 2 SLr 733; Min hai Holdings Pte Ltd v Sunlabel Pte Ltd [1999] 2 SLr 368; McConnell Dowell Construction (Aust) Pty Ltd v Sembcorp Engineering & Constructions 1......
  • AN ANALYSIS OF RECENT JUDICIAL DEVELOPMENTS IN SELECTED AREAS OF CIVIL PROCEDURE
    • Singapore
    • Singapore Academy of Law Journal No. 1996, December 1996
    • 1 December 1996
    ...at p 576. Also see the related cases of Bocotra Construction Pte Ltd v A-G[1995] 2 SLR 170; Bocotra Construction Pte Ltd v A-G (No 2)[1995] 2 SLR 733. 114 Ie, r 18(g) of the Arbitration Rules of the Singapore International Arbitration Centre, which enables the court to ‘…order the preservat......
  • UNDUE INFLUENCE, UNCONSCIONABILITY AND GOOD FAITH
    • Singapore
    • Singapore Academy of Law Journal No. 1996, December 1996
    • 1 December 1996
    ...and Ettrick v Hunter[1993] AC 713 at 738, Birks and Chin, supra n 9, Chap 3. 98 Bocotra Construction Pte Ltd v Attorney General (No 2) [1995] 2 SLR 733 (CA), noted Locknie [1996] LMCLQ 33, Loke [1995] SJLS 682; followed by Sans International v Keppel Engineering (unreported, April 4 1996, C......
  • Request a trial to view additional results

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT