Soon Li Heng Civil Engineering Pte Ltd v Samsung C&T Corp and another
Jurisdiction | Singapore |
Judge | Ang Cheng Hock J |
Judgment Date | 12 November 2019 |
Neutral Citation | [2019] SGHC 267 |
Court | High Court (Singapore) |
Docket Number | Originating Summons No 439 of 2019 |
Published date | 15 November 2019 |
Year | 2019 |
Hearing Date | 14 June 2019,09 May 2019,15 July 2019 |
Plaintiff Counsel | Poon Guokun Nicholas (Breakpoint LLC) |
Defendant Counsel | Lee Peng Khoon Edwin and Er Hwee Lee Danna Dolly (Eldan Law LLP),The second defendant absent and unrepresented. |
Subject Matter | Credit and Security,Performance bond,Unconscionability |
Citation | [2019] SGHC 267 |
The present dispute arises from the first defendant’s call on a performance bond (“PB”) which is provided by the second defendant, a bank. By this application, the plaintiff seeks to restrain the first defendant’s call on the PB on the ground that the call was unconscionable.
Facts BackgroundThe first defendant was employed by the Land Transport Authority (“LTA”)1 as the main contractor for the construction of the Marine Parade Station and Tunnels for the Thomson-East Coast Line (“the Project”).2
As the main contractor, the first defendant engaged the plaintiff as its subcontractor to carry out excavation and disposal works for the Project.3 A Re-Measurement Sub-Contract (“the Subcontract”) dated 22 April 2016 was entered into between the parties.4 The value of the Subcontract was about S$16.5m. Pursuant to the Subcontract, a performance bond was furnished as security for the performance and completion of the Subcontract by the plaintiff (“the PB”).5 By the PB, the second defendant, the first defendant’s bankers, covenanted to pay up to S$826,713.53 on the first defendant’s demand.6
As part of the Subcontract, the plaintiff excavated three categories of material, namely (a) soil; (b) hardcore material; and (c) ground improvement and mixed material. The site of disposal for each of the above three categories depended on the type of the material:7
On 31 August 2018, the plaintiff served Payment Claim No. 20 (“PC 20”) on the first defendant for the sum of S$3,278,935.95.10 The first defendant issued its Payment Response, in the form of a payment certificate no. 20 (“PR 20”) stating that the plaintiff should instead pay the first defendant the sum of S$167,848.99.11 The dispute proceeded for adjudication proceedings (“SOP 372/2018”). The adjudicator determined that the first defendant was to pay the plaintiff S$2,473,295.20.12 I will refer to the adjudication determination as “1AD”. It was issued on 9 November 2018.
On 15 December 2018, the first defendant issued a “Notice of Dispute” to the plaintiff on the basis that “[the plaintiff’s] claims in [SOP 372/2018] are without merit and that the adjudicator in that case has failed to consider the claims in light of the contractual provisions in the Subcontract.”13 This was followed shortly by a letter issued by the first defendant to the plaintiff dated 17 December 2018 where the first defendant informed the plaintiff that it was invoking its contractual right to terminate the Subcontract under clause 18.2 of the Subcontract,14 which provides that “[i]f the [first defendant] decides it is necessary for [its] convenience, then the [first defendant] may at any time by notice to the [plaintiff] forthwith terminate the Subcontract …”.15
Thereafter, on 26 December 2018, the adjudicated sum under 1AD was paid by the first defendant to the plaintiff.16
Payment Claim 24On 31 December 2018, the plaintiff served on the first defendant its Payment Claim No 24 (“PC 24”).17
The first defendant raises an issue in relation to the final quantity of disposalAccording to the first defendant, sometime in January 2019, it compared figures for the amount of materials disposed of as stated in emails sent by the plaintiff to the LTA with the contents of PC 24. The first defendant found that there were discrepancies.18
On 14 January 2019, the first defendant wrote to the plaintiff. It asserted that the plaintiff had claimed in PC 24 that the “final quantity of disposal as of 16 December 2018” was 175,978 m
On 29 January 2019, the plaintiff replied to the first defendant. It pointed out that the adjudicator in 1AD had already dealt with the disputes between the parties and determined the correct method of measurement to apply, as per the Subcontract, to assess the quantities of the different materials excavated and disposed of. The plaintiff asserted that its claims for payment in PC 24 was in accordance with these same methods of measurement. The plaintiff went on to describe the first defendant’s calculations in its letter of 14 January 2019 as being based on some “hitherto undisclosed” method of measurement and weight conversion formula, which was not in accordance with the terms of the Subcontract.21
On 7 February 2019, the first defendant replied to assert that it was entitled to “challenge in arbitration” the reasoning which the adjudicator in SOP 372/2018 had adopted in coming to his determination.22 The letter went on to state:23
You have applied the wrong rates and/or quantity and claimed for items which you have no basis to claim for in Payment Claim No. 24 by misapplying the provisions in the Subcontract. Amongst others,
you have arrived at your claim amount by mixing methods of calculation, using both drawings and lorry loads for the purpose of overlapped counting upon a single item. You have therefore consistently over-claimed in your payment claims. [emphasis in original]
In that letter, the first defendant went on to accuse the plaintiff of making a
We should point out that our final disposal quantity certified in Payment Certificate No. 24 is 135,850 m This would mean that if you have consistently applied a single method of calculation be it based on drawings (135,850 m3 , which is very close to the figure of 136,462 m3 that you have reported to the LTA.3 ) or lorry (136,462 m3 ) there would have been no significant difference between the final quantity disposal figure reported by you to LTA and the figure claimed in your Payment Claim No. 24. [emphasis in original]
The plaintiff replied on 18 February 2019 to again point out that the first defendant was not adhering to the methods of measuring quantities that were set out in the Subcontract. The plaintiff also pointed out that the first defendant’s assertion that a figure of 136,462 m
The first defendant wrote on 27 February 2019 to state that it was relying on the plaintiff’s own data on the lorry loads and the weight of quantities reported to the LTA as being disposed of from the worksite. The first defendant also asserted that the conversion formula of 2000 kg/m
Around the same time when the first defendant raised the issue with the plaintiff in relation to the “final disposal quantity”, it also raised another issue in relation to “hardcore disposal”.
On 15 January 2019, the first defendant wrote to the plaintiff to request for clarification relating to “hardcore disposal”. It asserted that, from “official records” that the plaintiff had provided to the LTA, it could calculate that 109,365 m
On 17 January 2019, the plaintiff replied to point out that volumes referred to by the first defendant were never reported to the LTA. The plaintiff also pointed out that it had never claimed that 47,040 m
On 22 January 2019, the first defendant wrote to reiterate its position that there was a discrepancy with the hardcore disposal...
To continue reading
Request your trial-
CEX v CEY and another
...should accordingly be restrained: Newtech Engineering at [27] and Soon Li Heng Civil Engineering Pte Ltd v Samsung C&T Corp and another [2019] SGHC 267 at [61] to [81] (“Soon Li Heng”). In Newtech Engineering, “[t]he entire circumstances of the case suggested strongly that the [beneficiary]......
-
Sulzer Pumps Spain, SA v Hyflux Membrane Manufacturing (S) Pte Ltd and another
...on the part of the beneficiary circumstances (at [26] to [30]). In Soon Li Heng Civil Engineering Pte Ltd v Samsung C&T Corp and another [2019] SGHC 267, the court found that the beneficiary’s call on the bond was for the purposes of fulfilling claims which had already been rejected by an a......
-
Samsung C&T Corp v Soon Li Heng Civil Engineering Pte Ltd
...kinds of work and different types of material disposed of (Soon Li Heng Civil Engineering Pte Ltd v Samsung C&T Corp and another [2019] SGHC 267 (“the Judgment”) at [69]). Accordingly, he did not agree that the alleged new evidence to which Samsung had referred (see [10] above) entitled Sam......
-
Security for performance
...SGHC 163; BWN v BWO [2019] SGHC 94 at [19]–[21], per Ang Cheng Hock JC; Soon Li Heng Civil Engineering Pte Ltd v Samsung C&T Corporation [2019] SGHC 267 at [33]–[40], per Ang Cheng Hock J; Loi, “Two Decades of Restraining Unconscionable Calls on Performance Guarantees: From Royal Design to ......