Shin Khai Construction Pte Ltd v FL Wong Construction Pte Ltd
Jurisdiction | Singapore |
Judge | Jordan Tan AR |
Judgment Date | 28 January 2013 |
Neutral Citation | [2013] SGHCR 4 |
Court | High Court (Singapore) |
Docket Number | Originating Summons No 1134 of 2012/Y |
Published date | 20 June 2013 |
Year | 2013 |
Hearing Date | 11 January 2013 |
Plaintiff Counsel | Edwin Lee Peng Khoon and Radika Mariapan (Eldan Law LLP) |
Defendant Counsel | John Lim Kwang Meng (Harry Elias Partnership LLP) |
Subject Matter | Building and Construction Law |
Citation | [2013] SGHCR 4 |
This case raises the question of whether an adjudication determination may be set aside on the ground that the adjudication application was lodged later than the period of entitlement stipulated under s 13(3)(
The plaintiff, Shin Khai Construction Pte Ltd (“SK”), filed this application to set aside an adjudication determination dated 15 November 2012 (“the Determination”) in respect of Adjudication Application No SOP AA0111 of 2012 (“the Adjudication Application”) on the grounds that the payment claim was formally defective and the Adjudication Application was lodged out of time.
BackgroundIn February 2012, SK, a general contractor, appointed the defendant, FL Wong Construction Pte Ltd (“FL”), a renovation contractor, to carry out works for a project, which was described as the “Proposed Erection of a Single-Storey Single-User Light Industrial Development with a 4-Storey Ancillary Office Building on Lot 04167M MK 07 at Tuas Avenue 11”. FL was to be paid $768,768. Under cl 1 of the Letter of Award (“the Contract”), the works to be carried out are to be based on bills of quantities and are subject to re-measurement and re-calculation.
On 25 September 2012, FL sent Payment Claim No 8 (“the Payment Claim”) to SK. That claim reads as follows:
[emphasis in original]
The attachment referred to under the heading “Accumulated Progress Interim Claim” contained a detailed breakdown of the work done in the month of September 2012 but only stated the sum claimed for each month from February to August 2012. FL received no response and on 18 October 2012, gave notice of its intention to adjudicate and proceeded to lodge the Adjudication Application. On the same day, SK sent FL an email alleging that it had faxed its payment response to FL on 15 October 2012. The Determination was issued on 15 November 2012.
Dissatisfied with the Determination, SK sought to set it aside on the following grounds:
With regard to the first ground, SK argued that the Payment Claim was defective because although it referred to the period “1.09.12 To 25.09.12”, it sought to claim payment for works done outside of that period, in particular, February to August 2012. SK also argued that the Payment Claim was defective because it only provided a detailed breakdown for September 2012 but not for February to August 2012. The Payment Claim therefore did not meet the requirements in s 10(3) of the Act and regulation 5(2) of the Building and Construction Industry Security of Payment Regulations (“the Regulations”) which read as follows:
[Section 10(3) of the Act]
[Regulation 5(2) of the Regulations]
As for the argument that FL had lodged the Adjudication Application out of time, SK argued that under s 13(3)(
In response, FL argued that it was clear that the Payment Claim was a monthly progress claim for September 2012 which also included a claim for work done for previous months which had not been paid. It argued that it was entitled to include the claim for the previous months under s 10(4) of the Act. It also pointed out that the claim for the previous months was the subject of previous payment claims. As for the argument that it had filed the Adjudication Application out of time, FL argued that there was a contractual clause in the form of cl 49 which provided that SK had ten days after receipt of a payment claim to evaluate and issue a payment certificate. FL argued that this payment certificate is intended to function also as a payment response and that instead of the default seven days under s 11(1)(
It is clear that the court has the power to set aside an adjudication determination under s 27(5) of the Act and O 95 of the Rules of Court (Cap 322, R 5, 2006 Rev Ed) and in deciding whether to do so, may review the validity of a payment claim (see
On the first issue of whether the Payment Claim complied with the formal requirements, I disagree with SK that the Payment Claim was defective for not being in compliance with s 10(3) of the Act and regulation 5(2) of the Regulations. First, in my view, although the Payment Claim could have been better drafted, it met the requisite standard under s 10(3)(
In totality, the use of the words “accumulated” on the first page of the Payment Claim accompanied by the reference to the attachment make it clear that: (1) the Payment Claim was in respect of an accumulated sum which included a period prior to September 2012, namely, February to August 2012; and (2) FL had added the sum claimed for the month of September 2012 to the outstanding sums.
As for providing a detailed breakdown as required under regulation 5(2) of the Regulations, I reject SK’s argument that FL needed to give a detailed breakdown for the other months
I note that FL had also sought to argue that the way SK had responded, in seeking to reduce the amount claimed by setting it off against sums incurred in months other than September 2012, showed that SK also understood that the Payment Claim was not limited to work done in September 2012. But, having found that the Payment Claim had complied with the formal requirements, there was no need for me to rely on this argument. After all, whether or not the respondent properly understood the Payment Claim was irrelevant to the court’s
To continue reading
Request your trial