Lee Wee Lick Terence (alias Li Weili Terence) v Chua Say Eng (formerly trading as Weng Fatt Construction Engineering) and another appeal
Jurisdiction | Singapore |
Judge | Chan Sek Keong CJ |
Judgment Date | 02 November 2012 |
Neutral Citation | [2012] SGCA 63 |
Court | Court of Appeal (Singapore) |
Docket Number | Civil Appeals Nos 44 and 46 of 2011 |
Published date | 14 November 2012 |
Year | 2012 |
Hearing Date | 17 October 2011 |
Plaintiff Counsel | Wong Soon Peng Adrian, Nelson Goh Kian Thong and Liew Mei Chun (Rajah & Tann LLP) and Koh Kok Kwang (CTLC Law Corporation) |
Defendant Counsel | Edwin Lee Peng Khoon and Poonaam Bai d/o Ramakrishnan Gnanasekaran (Eldan Law LLP) |
Citation | [2012] SGCA 63 |
Civil Appeal No 44 of 2011 (“CA 44 of 2011”) is an appeal by Lee Wee Lick Terence (“TL”) and Civil Appeal No 46 of 2011 (“CA 46 of 2011”) is a cross-appeal by Chua Say Eng (“CSE”) against the decision of a High Court Judge (“the Judge”) to set aside an adjudication determination made in favour of CSE under s 17 of the Building and Construction Industry Security of Payment Act (Cap 30B, 2006 Rev Ed) (“the Act”) (see
Before addressing the facts of this case, we ought to briefly set out the policy behind and the purpose of the Act and the scheme of adjudication that it provides for. According to the second reading speech for the Building and Construction Industry Security of Payment Bill 2004 (Bill 54 of 2004) (“the Bill”), the Bill was passed to solve a common problem in the construction industry of contractors (especially sub-contractors) going unpaid for work done or materials supplied. To help facilitate the cash-flow of contractors, the Act sought to establish “a fast and low cost adjudication system to resolve payment disputes” (see
Generally, the scheme prescribed by the Act has the following features. To paraphrase the Explanatory Statement attached to the Bill, the Act provides that any person who has carried out construction work or supplied goods or services under a construction contract or supply contract has a statutory entitlement to payment. The Act also establishes an adjudication procedure by which such a person may claim payment as well as provides for remedies when the adjudicated amount is not paid. A contractor obtains the right to seek adjudication after serving a payment claim in the prescribed form on the customer (ss 10 and 12 of the Act), to which the customer has to serve a payment response or else be barred from contesting the amount claimed before the adjudicator (ss 11 and 15(3)(
This whole process is characterised by strict time-lines. After adjudication, the adjudicated sum is payable within a short time (s 22(1) of the Act) and enforceable through various means (ss 23–27 of the Act), thus facilitating the contractor’s cash-flow. However, the adjudication outcome can be disputed (and any errors as to the amount payable accounted for) at a later arbitration or litigation that finally determines the parties’ contractual rights (ss 21(3) and 34(4) of the Act). Some of the provisions of the Act form the subject of this appeal and will be discussed below in greater detail.
Concerning the origin of the scheme under the Act, the then Minister of State for National Development stated the following in the second reading speech:
In the debate that followed the second reading speech, frequent comparison was made between the Bill and the Building and Construction Industry Security of Payment Act 1999 (Act 46 of 1999) (NSW) (“the NSW Act”). This piece of New South Wales legislation has a similar structure and purpose to the Act and seems to have informed the work of the Act’s drafters, although there are important differences between them. FactsThis Bill is modelled after similar legislation in other countries such as Australia, UK and New Zealand. For more than a year, the Building and Construction Authority (BCA) has consulted extensively with various stakeholders in the industry. These include the developers, professionals, main contractors, subcontractors, suppliers, and Government procurement agencies. The features of this Bill have been adapted to suit local conditions and have taken the stakeholders’ suggestions and views into account.
The material facts are as follows. On 16 August 2008, TL engaged CSE, a contractor, to convert his two-storey house at 1 Pasir Ris Heights into a three-storey house. Disputes arose, and this resulted in TL terminating the contract on 21 April 2010. In the letter of termination, TL required CSE to vacate the construction site by 12.00pm on 26 April 2010, which CSE did.
The Act applied to the contract between TL and CSE (“the Contract”) because it was a written contract for the carrying out of construction work on a residential property which required the approval of the Commissioner of Building Control under the Building Control Act (Cap 29, 1999 Rev Ed) (see ss 4(1) and 4(2)(
On 2 June 2010, CSE served a document described as “PAYMENT CLAIM NO. 6” (“PC6”) on TL by leaving it at TL’s last known address as stated in the Contract. PC6 was a claim for $140,450.40 for work done from June 2009 to 26 April 2010. There was no reference in PC6 that it was made or served under the Act. The contents of PC6 are as follows:
PAYMENT CLAIM NO. 6
CONSTRUCTION WORKS TO NO. 1 PASIR RIS HEIGHT SINGAPORE
QUOTATION REF: WFCE/1022/08 ACCEPTED ON 16 AUGUST 2008
ADDITIONAL WORKS FOR 2 ND FLOOR
QUOTATION DATED 5 NOV 2008 ACCEPTED ON 3 DECEMBER 2008 We submit our payment claim number 6 for work done from June 2009 to 26 April 2010:
|
|
|
|
|
|
We note that the details provided in the attachments to PC6 did not show when the works described were completed.
Details of the amount claimed are attached (2 pages).
TL did not serve on CSE a payment response within seven days as required by s 11(1)(
Ultimately, the Adjudicator identified the following issues to be determined by him:
At the conference, TL indicated that issues (a), (b) and (c) (see [10] above) were in the nature of jurisdictional challenges based on the decision of the High Court in
Upon TL’s failure to pay the amount awarded to CSE under the AD, CSE made an
The Assistant Registrar (“AR”) found in favour of CSE on all three of the grounds at [12] above (see
Before addressing the merits of the appeal, the Judge first considered the preliminary question of whether he could review the Adjudicator’s decision on the two issues raised by TL,
To continue reading
Request your trial-
Lee Wee Lick Terence v Chua Say Eng
...(alias Li Weili Terence) Plaintiff and Chua Say Eng (formerly trading as Weng Fatt Construction Engineering) and another appeal Defendant [2012] SGCA 63 Chan Sek Keong CJ , Andrew Phang Boon Leong JA and V K Rajah JA Civil Appeals Nos 44 and 46 of 2011 Court of Appeal Building and Construct......
-
JFC Builders Pte Ltd v LionCity Construction Co Pte Ltd
...its written judgment in Lee Wee Lick Terence (Li Weili Terence) v Chua Say Eng (formerly trading as Weng Fatt Construction Engineering) [2012] SGCA 63 (“Lee Wee Lick”) after I had given my oral decision. I will refer to that judgment as “the CA Judgment”. In the CA Judgment, the Court of Ap......
-
Shin Khai Construction Pte Ltd v FL Wong Construction Pte Ltd
...by the Court of Appeal in Lee Wee Lick Terence @ Li Weili Terence v Chua Say Eng (formerly trading as Weng Fatt Construction Engineering) [2012] SGCA 63 (“Chua Say Eng”) (at [61]) as it was not in issue. The plaintiff, Shin Khai Construction Pte Ltd (“SK”), filed this application to set asi......