GTMS Construction Pte Ltd v Ser Kim Koi
Jurisdiction | Singapore |
Judge | Tan Siong Thye J |
Judgment Date | 04 November 2014 |
Neutral Citation | [2014] SGHC 232 |
Year | 2014 |
Date | 04 November 2014 |
Published date | 22 June 2016 |
Hearing Date | 04 September 2014 |
Plaintiff Counsel | Thulasidas s/o Rengasamy Suppramaniam (Ling Das & Partners) |
Citation | [2014] SGHC 232 |
Defendant Counsel | Yeo Boon Tat and Danna Dolly Er (MPillay),Chia Ho Choon and Wong Xunai (Khattarwong LLP) |
Court | High Court (Singapore) |
Docket Number | Suit No 50 of 2014 (Registrar's Appeal No 199 of 2014) |
The defendant, Ser Kim Koi, employed the plaintiff, GTMS Construction Pte Ltd, as the contractor for a building project. In the course of the project, the defendant refused to pay the plaintiff under two interim payments, notwithstanding that these sums were certificated and approved for payment by the defendant’s architect.
The defendant alleged that the certificates issued were tainted by “fraud, improper pressure or interference” as stated in cl 31(13) of the terms under the Singapore Institute of Architects Conditions of Building Contract (Lump Sum Contract, 9th Ed, 2011 Reprint) (“the SIA conditions”). If they were, the certificates could be set aside and the plaintiff would not be entitled to payment. The plaintiff disagreed and sued for payment.
At the hearing below, the plaintiff applied for summary judgment under O 14 r 1 of the Rules of Court (Cap 322, R 5, 2006 Rev Ed) (“the ROC”). His application was granted by the AR. Dissatisfied with the AR’s decision, the defendant appealed. I heard the appeal and dismissed it. He has appealed against my decision and I now give my reasons.
The factsThe ProjectThe defendant is the owner of Lot 98388L Mukim 04 at Leedon Park (Bukit Timah Planning Area).1 He engaged the plaintiff to build three two-storey detached houses on that plot of land (“the Project”).2
Chan Sau Yan Associates (“the Architect”) was engaged by the defendant as the architects of the Project via a Memorandum of Agreement dated 16 June 2009.3 The Architect is the second third party to these proceedings. The first third party to this action is the proprietor of the Architect, Chan Sau Yan.
The plaintiff was engaged as the Project’s building contractor pursuant to an open tender.4 Its contract with the defendant contained the SIA conditions.5 The dispute concerns the interpretation of certain terms found in the SIA conditions, particularly, cl 31(13).
The disputeOn or about 3 September 2013 and 6 November 2013, the Architect issued Interim Certificates (“IC”) No 25 and 26 (collectively known as “the Certificates”) for the payment of $390,951.96 and $189,250.21 respectively.6 Pursuant to the Certificates, the Plaintiff issued Invoice No 25 and 26 for $418,318.60 (inclusive of Goods and Services Tax (“GST”) of $27,366.64) and $202,497.72 (inclusive of GST of $13,247.51) respectively.7 In total, the claimed sum was $620,816.30.
The defendant refused to pay the claimed sums and missed the 30-day period within which he was required to pay the plaintiff.8 He felt that the Architect and the plaintiff had been acting together so that the Certificates were issued when they should not have been.
The defendant alleged that the Certificates had been tainted by the plaintiff’s fraud, improper pressure or interference as it had caused the Architect to issue the Certificates even though there were work defects, the Completion Certificate (“CC”) was prematurely issued and unwarranted time extensions were granted,
The plaintiff took the view that it was unjustified for the defendant to withhold payment that was certified by the Architect. It argued that cl 31 of the SIA Conditions entitled it to full payment of the claimed sum. The relevant portions of cl 31 reads as follows:
[emphasis added]
The plaintiff’s view was that the issues raised by the defendant did not show fraud, improper pressure, or interference. As the third party to the action, the Architect’s evidence (on behalf of both himself and the first third party) was also that the Architect had not been fraudulent or subject to any improper pressure or interference when he issued the Certificates.
The AR’s decisionThe plaintiff’s summary judgment application was heard by the AR on 23 May 2014.11 The application was granted by the AR, who ordered that:
The AR held that cl 31(13) made it clear that the court should not be concerned with “shoddy, poor or unsatisfactory workmanship”.12 Rather, the issue was whether the Certificates had been tainted by dishonesty or impropriety so that it was inequitable for them to stand.
The AR’s view was that the evidence did not raise any question regarding the Architect’s legitimate intentions in issuing the Certificates. Therefore he granted summary judgment to the plaintiff and the defendant appealed.
The issuesThe defendant’s appeal raised three issues arising from the Architect’s issuance of the Certificates despite the presence of work defects, an alleged premature issuance of the CC and unwarranted timeline extensions:
O 14 r 1 of the ROC reads as follows:
1. Application by plaintiff for summary judgment (O. 14, r. 1) Where a statement of claim has been served on a defendant and that defendant has served a defence to the statement of claim, the plaintiff may, on the ground that that defendant has no defence to a claim included in the writ, or to a particular part of such a claim, or has no defence to such a claim or part except as to the amount of any damages claimed, apply to the Court for judgment against that defendant.
The defendant alleged that the plaintiffs were not entitled to payment as the Architect who issued interim payment certificates had been influenced by the plaintiff’s fraud, improper pressure or interference.13 That being the case, temporary finality should not be a shield against excesses or abuses of power by the certifier (
The defendant submitted that the Certificates were tainted by fraud. The Court of Appeal in
The defendant also alleged that the Certificates were tainted by improper interference or pressure. In his view, a certifier must act fairly, independently and professionally, without the influence of any party in the certification process:
The defendant argued that the Architect had shown a “consistent pattern of reckless conduct” in his certification duties during the course of the Project.18 The following acts of the Architect could not have been done with honest belief, or without the influence of improper pressure or interference.
The CC was issued prematurelyFirst, the defendant submitted that cl 24(4) of the SIA conditions provided that the CC should only be issued when the Project appeared to be complete and complied with the contract in
To continue reading
Request your trial-
Ser Kim Koi v GTMS Construction Pte Ltd
...reg 27 Rules of Court (Cap 322, R 5, 2014 Rev Ed) O 14 [Editorial note: The decision from which this appeal arose is reported at [2015] 1 SLR 671.] Mohan Reviendran Pillay, Yeo Boon Tat and Danna Er (M Pillay) for the appellant; Thulasidas s/o Rengasamy Suppramaniam(Ling Das & Partners) for......
-
Ser Kim Koi v GTMS Construction Pte Ltd and others and another appeal
...between Mr Ser, GTMS, and Mr Chan. In GTMS Construction Pte Ltd v Ser Kim Koi (Chan Sau Yan and Chan Sau Yan Associates, third parties) [2015] 1 SLR 671, GTMS applied for summary judgment against Mr Ser on the basis of two Interim Payment Certificates 25 and 26 (“IC 25” and “IC 26” respecti......
-
PTPerusahaan Gas Negara (Persero) TBK v CRW Joint Operation
...(Oct) (refd) Gilbert-Ash (Northern) Ltd v Modern Engineering (Bristol) Ltd [1974] AC 689 (refd) GTMS Construction Pte Ltd v Ser Kim Koi [2015] 1 SLR 671 (refd) Modern Engineering (Bristol) Ltd v Gilbert-Ash (Northern) Ltd (1973) 71 LGR 162 (refd) Nikola Rotenberg v Sucafina SA [2011] 1 CLC ......
-
Litigation
...Co Ltd [2008] HKCFI 685 at [17], per DHCJ Wong SC. 727 ROC Order 14 rule 1 (Sing). See also GTMS Construction Pte Ltd v Ser Kim Koi [2014] SGHC 232 at [16], per Tan Siong hye J. 728 See Swain v Hillman [2001] 1 All ER 90 at 95, per Lord Woolf MR; Canyon Development Ltd v Far East Wagner Con......
-
Contract administration
...regard, Chin Ivan v HP Construction & Engineering Pte Ltd [2015] SGCA 14. 532 As to which, see GTMS Construction Pte Ltd v Ser Kim Koi [2014] SGHC 232 at [58]–[61], per Tan Siong hye J (appeal allowed, on unrelated grounds: [2016] SGCA 7). 533 Fraud, in this context, may include recklessnes......
-
Building and Construction Law
...agreed by the parties: at [49]. Construction dispute and summary judgment H P Construction and GTMS Construction Pte Ltd v Ser Kim Koi [2015] 1 SLR 671 7.86 The two recent cases that involved successful recovery of moneys by contractors based on the SIA Articles and Conditions of Building C......