HP Construction & Engineering Pte Ltd v Chin Ivan
Jurisdiction | Singapore |
Judge | Edmund Leow JC |
Judgment Date | 10 July 2014 |
Neutral Citation | [2014] SGHC 137 |
Year | 2014 |
Date | 10 July 2014 |
Published date | 03 September 2014 |
Hearing Date | 12 June 2014,23 May 2014 |
Plaintiff Counsel | John Chung and Priscylia Wu (Kelvin Chia Partnership) |
Citation | [2014] SGHC 137 |
Defendant Counsel | Joseph Lee, Tan Yee Siong and Ross Tan (Rodyk & Davidson LLP) defendant/respondent. |
Court | High Court (Singapore) |
Docket Number | Suit No 180 of 2014 (Registrar's Appeal No 124 of 2014) |
This is an appeal against the decision of the Assistant Registrar to grant a stay of proceedings pursuant to s 6 of the Arbitration Act (Cap 10, 2002 Rev Ed).
The plaintiff/appellant, H P Construction & Engineering Pte Ltd (“the Plaintiff”), was the main contractor for the construction of two detached houses on two lots of land located at Sentosa Cove, Singapore. The defendant/respondent, Ivan Chin (“the Defendant”), had employed the Plaintiff under a building contract dated 5 May 2009 (“the Contract”) for a sum of $8,000,000.
The Contract incorporated the Singapore Institute of Architects Articles and Conditions of Building Contract (Lump Sum Contract) 7th Edition, April 2005 (“the SIA Conditions”). Under the SIA Conditions, the Plaintiff was entitled to progress payments by way of periodic valuation of works carried out which were certified by the architect appointed for the project.1 The architect appointed for the project was Philip Lee Pang Kee (“the Architect”), and the quantity surveyor was Turner & Townsend Pte Ltd (“the Quantity Surveyor”).2
On 11 July 2012, the Architect issued two Architect’s Instructions (AI/131/HP/019 and AI/132/HP/019) (“the AIs”), one for each parcel of land. The AIs approved a number of items on the Plaintiff’s list of proposed variation works, including the items numbered 173, 174, 280 and 281 (“the Disputed Items”). These Disputed Items related to claims for: 3
Subsequently, the Plaintiff raised Payment Claim No 32 claiming for a sum of $1,171,646.37 pertaining to work done on the project up to 28 September 2012.4 Of that sum, the amount of $614,375 related to the Disputed Items.5 The Quantity Surveyor provided an interim valuation of $120,000 for the Extended Preliminaries claims .6 The Quantity Surveyor did not provide an interim valuation for the extension of the Defects Liability Period claims.7 The Architect then certified the Quantity Surveyor’s interim valuation in Progress Certificate No 32 which amounted to the sum of $321,383.94,8 for which the due date of payment was 10 December 2012.9
Close to a year later, on 26 September 2013, the Plaintiff raised its final payment claim for the sum of $720,417.29. This claim also contained the Disputed Items.10 The Quantity Surveyor valued the Disputed Items at $334,000 (this time including the extension of Defects Liability Period claim).11 Subsequently, the Architect certified the Quantity Surveyor’s valuation in Final Certificate No 33 dated 27 September 2013 for the sum of $720,417.28,12 for which the due date of payment was 5 November 2013.13
However, despite repeated requests, the Defendant did not pay the sum amounting to $1,041,801.22 (“the Outstanding Certified Sum”) which is the total sum that the Architect had certified as being due from the Defendant to the Plaintiff under Progress Certificate No 32 and Final Certificate No 33.14
The Defendant refused to pay the said sums for various reasons, including the allegation that the works carried out by the Plaintiff were defective and should not have been certified by the Architect in the first place. The Defendant also alleged that he had a counterclaim for loss of rental, liquidated damages and rectification works that had to be carried out by third parties.15
On 29 October 2013, the Plaintiff referred the dispute for adjudication under the Building and Construction Industry Security of Payment Act (Cap 30B, 2006 Rev Ed) (“the SOP Act”) for the Outstanding Certified Sum, but the adjudicator dismissed the Plaintiff’s claims for ignoring or failing to recognise the timelines for the Defendant’s payment response as stipulated under the SIA Conditions.16 The Defendant alleged that it was only when the Plaintiff commenced adjudication proceedings against him that he was served a copy of the Plaintiff’s final payment claim.17
Subsequently, on 13 February 2014, the Plaintiff brought Suit No 180 of 2014 against the Defendant claiming for the Outstanding Certified Sum, as well as interest amounting to $30,700.34.18
In response, on 7 March 2014, the Defendant applied,
The Defendant’s allegation of fraud was primarily premised on a letter dated 21 March 2014 from the Architect replying to the Defendant’s queries as to why he had to pay for the Disputed Items (“the Letter”). The Architect’s response was, in substance, as follows:20
As informed by HP Construction & Engineering Pte Ltd, the above items covered are requested by Owner/ID Axis and to be verified by QS Towner and Turner.
In summary, the Defendant’s case before the Assistant Registrar was that the Plaintiff had misrepresented to the Architect that the Defendant had agreed to,
In his 3rd affidavit, the Plaintiff’s managing director, Mr Seah Hwa Peng, denied making the Alleged Misrepresentations to the Architect.22 It was also confirmed at the hearing before the Assistant Registrar that there was no such agreement between the parties.23
After hearing the parties, the Assistant Registrar granted the stay sought on the basis that there appeared to be a
The Plaintiff filed a Notice of Appeal on 10 April 2014.
Clauses of the ContractIn the present proceedings, it is clear that unless the Defendant is able to show that the validity of the Certificates is in dispute, no stay of proceedings can be granted in respect of the Plaintiff’s claim, which is based on the Certificates. The reason for this is because Certificates issued by the Architect under the Contract enjoy “temporary finality” pursuant to cl 31(13) of the SIA Conditions, which states:
No certificate of the Architect under this Contract shall be final and binding in any dispute between the Employer and the Contractor, whether before an arbitrator or in the Courts, save only that,
in the absence of fraud or improper pressure or interference by either party , full effect by way of Summary Judgment or Interim Award or otherwise shall,in the absence of express provision , be given to all decisions and certificates of the Architect (other than a Cost of Termination Certificate or a Termination Delay Certificate under clause 32(8) of these Conditions), whether for payment or otherwise, until final judgment or award, as the case may be, and until such final judgment or award such decision or certificates shall (save as aforesaid and subject to sub-clause (6) of this condition) be binding on the Employer and the Contractor in relation to any matter which, under the terms of the Contract, the Architect has a fact taken into account or allowed or disallowed, or any disputed matter upon which under the terms of the Contract he has as a fact ruled, in his certificates or otherwise.The Architect shall in all matters certify strictly in accordance with the terms of the Contract . In any case of doubt the Architect shall, at the request of either party, state in writing within 28 days whether he has as a fact taken account of or allowed or disallowed or ruled upon any matter in his certificates, if so identifying any certificate and indicating the amount (if any) taken into account or allowed or disallowed, or the nature of any ruling made by him, as the case may be. [emphasis added]
In other words, under cl 31(13) of the SIA Conditions, no certificate of the architect shall bind the employer and contractor permanently. However, architect’s certificates do have temporary effect, for they bind the parties in the interim period pending final determination of the dispute by arbitration or court proceedings. In the meantime, architect’s certificates may be enforced by way of summary judgment or interim award—unless there is fraud, improper pressure or interference by either party, or an express provision stipulating otherwise. As explained by L P Thean J in
To continue reading
Request your trial-
Ser Kim Koi v GTMS Construction Pte Ltd
...Fenice Investments Inc v Jerram Falkus Construction Ltd [2009] EWHC 3272 (TCC) (refd) H P Construction & Engineering PteLtd v Chin Ivan [2014] 3 SLR 1318 (refd) Homburg Houtimport BV v Agrosin Pte Ltd (The Starsin) [2004] 1 AC 715 (refd) Lojan Properties Pte Ltd v Tropicon Contractors Pte L......
-
Akrobat Pte Ltd v Enovate System Pte Ltd
...Corp v Chinese Chamber Realty Pte Ltd [2004] 1 SLR(R) 382 (“Samsung”) at [25]; H P Construction & Engineering Pte Ltd v Chin Ivan [2014] 3 SLR 1318 at [42][]. 55 Once the defendant sets up a prima facie case of a dispute, the burden shifts to the plaintiff to satisfy the court that there is......
-
Syncworks Pte Ltd v Fucom Construction Pte Ltd
...between the parties which falls within the terms of the arbitration agreement: H P Construction & Engineering Pte Ltd v Chin Ivan [2014] 3 SLR 1318 at [32] and [42]; Tjong Very Sumito at [23]. In assessing whether there is such a dispute, courts adopt a holistic and common-sense approach. C......
-
Chin Ivan v H P Construction & Engineering Pte Ltd
...and referred to arbitration in light of this. The Judge’s decision is reported as H P Construction & Engineering Pte Ltd v Chin Ivan [2014] 3 SLR 1318 (“the Judgment”). At the conclusion of the appeal, we were satisfied that irregularities affecting the Disputed Certificates rendered them i......
-
Contract administration
...Conditions is … invalid if it is not issued in strict compliance with the contract”: HP Construction & Engineering Pte Ltd v Chin Ivan [2014] SGHC 137 at [19], per Edmund Leow JC (see also at [53]). his 390 ContraCt aDMiniStration (v) Issue of certiicate 5.109 Construction and engineering c......
-
Arbitration
...question of the standard of the existence of dispute was raised for consideration in H P Construction & Engineering Pte Ltd v Chin Ivan[2014] 3 SLR 1318 (H P Construction). The defendant had employed the plaintiff as the main contractor for the construction of houses in Sentosa Cove. The bu......
-
Building and Construction Law
...is expected to attract considerable interest from the construction industry. 7.11 In H P Construction & Engineering Pte Ltd v Chin Ivan[2014]3 SLR 1318 (H P Construction), the building contract incorporated the Singapore Institute of Architects (SIA) Articles and Conditions of Building Cont......
-
Building and Construction Law
...are raised by an employer to hold back payments which are due to a contractor. 7.2 In H P Construction & Engineering Pte Ltd v Chin Ivan[2014] 3 SLR 1318 (reviewed in (2014) SAL Ann Rev 102 at 105–109, paras 7.11–7.21), an employer resisted the enforcement of two architect's certificates on......