W Power Group EOOD v Ming Yang Wind Power (International) Co Ltd
Jurisdiction | Singapore |
Judge | Thomas Bathurst IJ |
Judgment Date | 29 September 2023 |
Neutral Citation | [2023] SGHC(I) 15 |
Court | International Commercial Court (Singapore) |
Docket Number | Originating Application No 2 of 2023 (Summons No 13 of 2023) |
Hearing Date | 04 September 2023 |
Citation | [2023] SGHC(I) 15 |
Year | 2023 |
Plaintiff Counsel | Han Wah Teng (CTLC Law Corporation) |
Defendant Counsel | William Ong Boon Hwee, Ivan Lim Jun Rui and Wong Pei Ting (Allen & Gledhill LLP) |
Subject Matter | Civil Procedure,Costs,Security |
Published date | 29 September 2023 |
By a summons filed on 30 May 2023 Ming Yang Wind Power (International) Co. Ltd (“
The claimant is a company registered in Bulgaria. It described itself in the Statement of Claim as an international developer engaged in investing and developing wind farms in Bulgaria, Romania and other countries.
The defendant is a Chinese company incorporated in Hong Kong and is a wind turbine manufacturer engaged in the design, manufacture, construction, sales and services of wind turbines in the global market.
The claimant alleges that the claimant and defendant entered into a joint venture agreement on 3 July 2011 to establish a joint venture company for the purpose of developing two wind farm projects. It claimed that pursuant to the joint venture agreement, a joint venture company, MW Wind Power OOD (“
The claimant claims the defendant breached its obligation under the joint venture agreement essentially by failing to secure financing for the one of the two wind farm projects (“
The defendant has filed a somewhat detailed defence to the claim. Broadly speaking it states that following changes to the legal and regulatory regime introduced by the Bulgarian government which negatively affected renewable energy projects such as Project 2, Project 2 was no longer viable and the parties agreed not to proceed with it sometime in 2012. It denies any breach of the joint venture agreement and asserts the claimant is estopped from enforcing the agreement and has waived its right to do so. It also claims that the alleged causes of action are barred by s 6(1) of the Limitation Act 1959 and the claimant does not have standing to sue in respect of any alleged breaches of the joint venture agreement in relation to Project 2.
The above is an extremely broad summary of the claims which have been made and the defences to it but it is sufficient for the purpose of the present application.
The relevant rules and legislation This being a case transferred to the Singapore International Commercial Court (the “
Security for costs
…
Security for costs
The defendant made five points in support of its application. The first was that the claimant was ordinarily resident outside the jurisdiction so what it described as the threshold in Order 9 r 12(1)(
There was no dispute between the parties that the claimant was resident outside the jurisdiction. However, there was a dispute as to the effect. The defendant accepted the Court retains a discretion to refuse to grant security, even if that threshold was met but submitted that if the factors weighing for and against the grant of security were otherwise evenly balanced, then in those circumstances security should be granted. It referred to the decision of the Court of Appeal in
By contrast the claimant submitted that
As I am of the view that the factors are not evenly balanced it is unnecessary to resolve this...
To continue reading
Request your trial-
W Power Group EOOD v Ming Yang Wind Power (International) Company Ltd
...Power Group EOOD and Ming Yang Wind Power (International) Co Ltd [2023] SGHC(I) 15 Thomas Bathurst IJ Originating Application No 2 of 2023 (Summons No 13 of 2023) Singapore International Commercial Court Civil Procedure — Costs — Security — Company incorporated in Hong Kong seeking order th......
-
W Power Group EOOD v Ming Yang Wind Power (International) Co Ltd
...13 assessed in the amount of $6,000 inclusive of disbursements. 1 See W Power Group EOOD v Ming Yang Wind Power (International) Co Ltd [2023] SGHC(I) 15. 2 Claimant’s letter dated 13 October 2023; Claimant’s letter dated 14 October 3 Claimant’s written submissions dated 27 October 2023 at p......