UTOC Engineering Pte Ltd v ASK Singapore Pte Ltd
Jurisdiction | Singapore |
Judge | Lee Seiu Kin J |
Judgment Date | 19 October 2017 |
Neutral Citation | [2017] SGHC 259 |
Court | High Court (Singapore) |
Docket Number | Suit No 449 of 2013 (Assessment of Damages No 8 of 2017) |
Published date | 26 October 2017 |
Year | 2017 |
Hearing Date | 11 April 2017,12 April 2017,24 May 2017 |
Plaintiff Counsel | M K Eusuff Ali, Chan Xian Wen Zara, and Yap En Li (Tan Rajah & Cheah) |
Defendant Counsel | Lee Hwee Khiam Anthony and Clement Chen (Bih Li & Lee LLP) |
Subject Matter | Damages,Assessment,Measure of damages,Settlement sum |
Citation | [2017] SGHC 259 |
This is assessment of damages no 8 of 2017 (“AD 8”) in suit no 449 of 2013 (“Suit 449”). The trial was bifurcated with the trial on liability heard in January 2016. On 27 April 2016, I gave judgment on liability in favour of the plaintiff and ordered damages to be assessed. The defendant’s appeal against this finding was dismissed by the Court of Appeal on 1 December 2016. The trial in AD 8 was heard on 11 and 12 April 2017. On 24 May 2017, after hearing submissions from both counsel, I assessed the damages at $5,024,732.85 and gave judgment for that sum. I now give my reasons.
Facts leading up to AD 8The plaintiff is a Singapore company with its principal business in plant construction for petrochemical, chemical, and pharmaceutical industries. The defendant is also a Singapore company and its principal business is the installation of thermal insulation and refractories. The plaintiff was engaged by Shell Eastern Petroleum Pte Ltd (“Shell”) as main contractor to carry out mechanical, piping and equipment works for ten furnaces at Shell’s complex in Pulau Utar, Singapore (“the ten furnaces”). As part of its works, Shell required the plaintiff to install the refractory lining in the ten furnaces (“the Refractory Works”). This required the plaintiff to lay refractory bricks on the inside walls of the furnaces in order to allow the furnace to be heated up to 1,000 degrees Celsius. Because the bricks would expand due to the heat, pins were attached to the furnace walls to prevent the bricks from shifting inwards. The pins were hooked to grooves in the bricks at several levels of the walls.
The plaintiff engaged the defendant as a specialist contractor to carry out the Refractory Works in around July 2008. After the works were completed in around July 2009, the furnaces were fired in 2010 and failures were found in all ten furnaces. Various panels of bricks were separated from the furnace walls and from their pins, and as a result, those walls were no longer insulated. Rectification works on all ten furnaces were completed by November 2013.
As a result of the need for rectification works, Shell claimed against the plaintiff for costs and expenses that it incurred. The plaintiff negotiated with Shell to reduce its claim and eventually reached a settlement with Shell in December 2011 (“the Settlement Agreement”).
Parties’ submissionsThe plaintiff’s claims and the defendant’s response to each head of claim are encapsulated in the following table:
| | |
| | |
| | |
| | |
| | |
| | |
| | |
Both parties agreed that the Settlement Agreement was reasonably reached and reasonable in nature. But they disagreed as to whether this meant that the court could take a line-by-line analysis of the sums the plaintiff claimed against the defendant pursuant to the Settlement Agreement the plaintiff reached with Shell.
The plaintiff submitted that the court could not do so and was bound by the settlement sum that Shell had quantified by applying the formula in the Settlement Agreement. It relied on the Court of Appeal decision in
The defendant agreed that
Accordingly, the defendant submitted that three invoices fell outside the scope of the formula in the Settlement Agreement (totalling $467,794.89):
The plaintiff’s response to the three invoices was that the defendant should have raised these objections when the plaintiff negotiated the Settlement Agreement with Shell. The defendant was invited to participate in the negotiations and indeed had participated initially, before pulling out subsequently. Having refused to participate, it could not now complain. As for Nelson Lim’s concessions in cross-examination, the plaintiff said that Nelson Lim was not a refractory specialist and his task was only to ensure that Shell charged the plaintiff for matters pertaining to the rectification works. If the defendant, a refractory specialist, wanted to challenge the specifics, it should have done so during the negotiation process.
The plaintiff said that since the defendant refused to participate, it could not use its expertise as a refractory specialist with the benefit of hindsight to assess whether the plaintiff should have accepted the invoices. The plaintiff relied on the English cases of
The plaintiff tendered a Table of Manpower Costs which showed that this sum was for the salaries of nine of the plaintiff’s staff. The nine staff were involved during the rectification works as supervisors. Hence, the plaintiff claimed for both their supervision of the rectification works as well as the equipment which they had to wear to do so.
The defendant said that the plaintiff’s Table of Manpower Costs was not sufficient evidence to support the plaintiff’s claim because it did not specify precisely what work was done by each staff member and how their shift to the rectification works from their normal jobs was a “
To continue reading
Request your trial