TSB Global Distributions Pte Ltd v Pure Projects (Singapore) Pte Ltd
Jurisdiction | Singapore |
Judge | Lee Li Choon |
Judgment Date | 30 December 2021 |
Neutral Citation | [2021] SGDC 290 |
Court | District Court (Singapore) |
Docket Number | District Court Suit No 409 of 2020 |
Published date | 02 March 2022 |
Year | 2021 |
Hearing Date | 02 September 2021,26 July 2021,02 November 2021,27 July 2021,19 February 2021 |
Plaintiff Counsel | Sureshan s/o T Kulaisingam and Samuel Ang Rong En (Sureshan LLC) |
Defendant Counsel | Chia Swee Chye Kelvin and Tan E Wei Bernard (Lumen Law Corporation) |
Citation | [2021] SGDC 290 |
The Plaintiff’s Claim and the Defendant’s Counterclaim in this suit involves the project relating to the conversion of the then Marina Bay Sands Theatre into three venues, namely, the Marquee nightclub, the KOMA restaurant and Avenue, a nightclub and restaurant. Marina Bay Sands (“MBS”) was the employer or owner of the said project and the Defendant was the Project Manager with its role described as
Pursuant to the engagement of the Plaintiff for the conversion relating to the Marquee nightclub, the Defendant first engaged the Plaintiff on 21
On 7 March 2019, the Plaintiff’s representative Ted Singh (“Mr Singh”) and the Defendant’s representative Jon Coney (“Mr Coney”) both signed off on a Handing/Taking Over Checklist (“the HTO Document”).
A few days after signing off on the HTO Document, on 11 March 2019, an incident occurred which resulted in the emission of water causing damage to the works, fixtures, and other properties on the Project site (“Water Damage Incident”). As a result of the Water Damage Incident, on 14 March 2019, the Defendant engaged the Plaintiff to carry out the replacement of the hoist system for the Marquee nightclub via “Quotation No. 2019-8140-PP-Damage-Hoist System” (“the Hoist Replacement Works” / “Hoist Replacement Quotation”).
On 29
On 12 April 2019, the Marquee nightclub opened as planned.
The Plaintiff’s ClaimThe Plaintiff’s Claim is in respect of Tax Invoice No. 19117 and Tax Invoice 19120.A. It is not disputed that the Defendant had not made any payment due under these two invoices.
In respect of the Plaintiff’s claim under Tax Invoice No. 19117, the Defendant avers in its defence that the works were incomplete in that the Plaintiff has not provided any certifications for the works3.
In respect of the Plaintiff’s claim under Tax Invoice 19120.A, the Defendant avers that it did not order for the works performed by the manpower stated therein and is therefore not liable to pay to the Plaintiff the alleged sum of $15,450.80 under this invoice4.
The Defendant’s CounterclaimIt is not disputed that the Defendant has made payment to the Plaintiff in respect of all the invoices issued for the Milos Truss Works, Movecat Hoist Works, PE Certification of Movecat Hoist Works, PE Certification of Supporting System and the Hoist Replacement Works, amounting to over $1.1 million or 96% of the total sum invoiced by the Plaintiff.
In response to the Plaintiff’s Claim, the Defendant counterclaims for damages for breach of contract and/or failure of consideration and unjust enrichment in relation to the Milos Truss Works, Movecat Hoist Works, PE Certification of Movecat Hoist Works, PE Certification of Supporting System and Hoist Replacement Works on the following grounds:
The Defendant also alleges that it is entitled to the refund of $28,034 that was paid to the Plaintiff on 18 March 2019 under Quotation 019-19135-PP-MOVECAT (“the Movecat Operator Quotation”) as the service was not provided and/or was abortive because the replacement hoists were not delivered.
In addition, the Defendant alleges that there has been overcharging in relation to the Plaintiff’s Tax Invoice Nos. 19112, 19114 and 19119 in the respective amounts of
In respect of the Defendant’s counterclaim, the Plaintiff counters that both parties’ representatives had signed off on the HTO Document on 7 March 2019 confirming with respect to the list of equipment delivered and installed by the Plaintiff as follows:
“The above works has been completed in respect as per the agreement and the Client’s directives and necessary requirements. And no rectification works is found during the handing/taking over of the work. The works are handed to (the Defendant) in a good and satisfactory condition.”
The Plaintiff also avers that by signing the HTO Document, the Defendant has also confirmed that,
“The system programme, configuration, testing and commissioning was successfully carried out and no rectification work is found during the system programme, configuration, testing and commissioning. The system programme, configuration, testing and commissioning of the work are taken over by (the Defendant) in a good and satisfactory condition.”
The Plaintiff avers that by reason of the HTO Document, the Defendant is estopped from raising the allegations in its counterclaim. The Plaintiff further avers that the issues belatedly raised by the Defendant in response to the Plaintiff’s claim for payment under Invoice Nos. 19117 and 19120.A after it had made payments without issue are but afterthoughts11.
Specifically, in respect of each item of the Defendant’s counterclaim, the Plaintiff avers as follows:
To continue reading
Request your trial