Soo Nam Thoong and another v Phang Song Hua
Jurisdiction | Singapore |
Judge | Chan Seng Onn J |
Judgment Date | 01 July 2011 |
Neutral Citation | [2011] SGHC 159 |
Court | High Court (Singapore) |
Hearing Date | 15 June 2011 |
Docket Number | Originating Summons No. 359 of 2011/K |
Plaintiff Counsel | Tan Lam Siong (L S Tan & Co) |
Defendant Counsel | Aqbal Singh s/o Kuldip Singh (Pinnacle Law LLC) |
Subject Matter | Land,Conveyance,Legal requisitions |
Published date | 06 July 2011 |
Originating Summons No. 359 of 2011/K deals with an application under s 4 of the Conveyancing and Law of Property Act (Cap 61, 1994 Rev Ed) (“CLPA”) regarding the sale of a two-storey shophouse at 145 and 145A Sims Avenue, Singapore 387467 (“the Property”). The Plaintiffs are asking for:
The Plaintiffs were granted the Option to purchase the Property, which was 217.5 sq m, for $2.85 million. In return for the Option, they paid an option fee of $28,500.00. On 15 April 2011, they exercised the Option and paid a further sum of $256,500 (10% of the purchase price minus the option fee). Following the exercise of the Option, the Plaintiffs’ solicitors sent their legal requisitions to the various relevant authorities, including the LTA. The original completion date of the Option was 10 June 2011.
In LTA’s reply contained in the 28 April 2011 Road Line Plan, the Plaintiffs’ solicitors noted that a substantial portion of the Property was coloured in red and required as Road Reserve. According to paragraph 3.1 of the Explanatory Note accompanying the 28 April 2011 Road Line Plan, the portions of land required as Road Reserve are to be:
set aside when development/redevelopment takes place on the subject lots
or when road construction/ improvement is carried out by the Land Transport Authority, whichever is earlier.(emphasis added)
The LTA confirmed in a letter dated 5 May 2011 that the land is required to be set aside when development/redevelopment takes place
The Plaintiffs estimated that about 40% of the Property was required as Road Reserve and will have to be set aside when either development/redevelopment
Clause 10 of the Option is set out as follows:
The sale and purchase herein shall be
subject to the Purchaser’s solicitors receiving satisfactory replies to their legal requisitions and applications for Interpretation Plans to the various Government Departments and Land Transport Authority (LTA) insofar as such replies/Interpretation Plan relate to the Property andif any of such replies and/or Interpretation Plan are found to be unsatisfactory then this Agreement may be rescinded at the Purchaser’s Option and in such event the Vendor shall forthwith refund to the Purchaser all monies paid by the Purchaser to the Vendor or the Vendor’s solicitors but without any interest, compensation or deductions whatsoever and thereupon neither party shall have any claim or demand against the other for costs, damages, compensation or otherwise.PROVIDED ALWAYS that:
[emphasis added in italics, emphasis in bold in original]
The Defendant’s solicitors replied on 29 April 2011 that the Plaintiffs had no right to rescind because of clause 10(
The dispute thus centred on the legal interpretation of clause 10(
The Plaintiffs’ interpretation gave clause 10 (
The Plaintiffs have thus read the words in the parentheses “(whether actual or proposed or to be implemented
The Defendant’s interpretation gave clause 10(
The Defendant further argued that the words in parentheses “merely set out 3 scenarios where the key structure of the clause will have an impact”, as follows2:
Under such an interpretation, the phrase “only if there is any redevelopment of the property” applies only to “to be implemented”. The Preferred Interpretation(a) “Actual” road line schemes or proposals affecting any part of the property. In other words the authorities have implemented schemes and proposals which are taking place currently.
(b) “Proposed” road line schemes or proposals affecting any part of the property. In other words the authorities contemplate the implementation of the schemes and proposals in the future. ...
(c) Road line schemes or proposals affecting any part of the property which are “to be implemented only if there is any redevelopment of the property”. In other words, these schemes or proposals will
not be implemented by the authorities unless and until the redevelopment of the property is initiated and commenced. …
The crux of the interpretation of clause 10(
First, the nature of clause 10 of the Option should be considered in its entirety. Clause 10 of the Option consists of the general provision allowing the Purchaser to rescind the Option if the replies to the legal requisitions are found to be
The key concept here is that of
context . No contract exists in a vacuum and, consequently, its language must be construed in the context in which the contract concerned has been made. We would go so far as to state that even if the plain language of the contract appears otherwise clear, the construction consequently placed on such language should not be inconsistent with the context in which the contract was entered into if this context is clear or even obvious, since the context and circumstances in which the contract was made reflect the...
To continue reading
Request your trial-
Contract Law
...had to the commercial purpose of the contract and circumstances in which it was made. The High Court in Soo Nam Thoong v Phang Song Hua[2011] SGHC 159 at [24] alluded to similar basic points. 11.49 Zurich Insurance prescribed a two-step framework in the interpretation of contracts. The firs......
-
Land Law
...In the circumstances, the court ruled in favour of the defendant vendor. Legal requisitions 19.48 In Soo Nam Thoong v Phang Song Hua[2011] SGHC 159 (Soo Nam), the plaintiff purchasers sought to rescind the option to purchase which they had validly exercised on the ground that the reply to t......