Sembawang Engineering Pte Ltd v Priser Asia Engineering Pte Ltd

JudgeLim Teong Qwee JC
Judgment Date03 July 1992
Neutral Citation[1992] SGHC 182
Subject MatterSecurity for costs,Factors to be considered,Arbitration,s 388 Companies Act (Cap 50, 1990 Ed),O 23 Rules of the Supreme Court 1970,Plaintiff company impecunious,Security,Civil Procedure,s 27 Arbitration Act (Cap 10),Costs,Arbitration proceedings,Court's discretion to order security for costs
Year1992
Citation[1992] SGHC 182
CourtHigh Court (Singapore)
Plaintiff CounselLatiff Ibrahim and Tan Lay Pheng (Khattar Wong & Partners)
Published date19 September 2003
Defendant CounselYC Yang (Murphy & Dunbar)

By a contract dated 12 August 1989 (`the contract`) and made between the above-named Sembawang Engineering Pte Ltd (`Sembawang`) and Priser Asia Engineering Pte Ltd (`Priser`), Priser agreed, subject to the conditions of contract attached to the contract, to execute and complete the design, supply, installation, testing and commissioning of the electrical system (`the works`) for the Qatar General Petroleum Corp Living Quarters Platform (`the platform`) for $800,000. The platform was under construction by Sembawang at its yard in Singapore for delivery in the Gulf. The completion date for the works was 6 November 1989.

Priser commenced execution of the works in August 1989. Variations were ordered from time to time. Serious delay was encountered and on 6 November 1989 the works were not completed. The platform was originally scheduled to leave Singapore in January 1990 but eventually left on 28 February 1990. Priser did not complete the works by that date.

Paragraph 21 of the conditions of contract provide:

Terms of payment

Payment shall be made to [Priser] by progress payment 30 days after the receipt of invoice of work completed for the month, but subject to the percentage of work completed as certified by the engineer less 10% of the amount being retention fee, which shall be deemed payable after 12 (twelve) months from the date of issue of acceptance certificate and the provision of paras 6, 7 and 8 of standard conditions of contract and contract document Pt A.



I was informed from the Bar that no engineer was appointed for the purpose of the contract and no certificates were issued. Priser has issued six invoices, four of which Sembawang has paid. The particulars are:

Date Invoice No Amount Date of payment

28 August 1989 438/89 $81,144.90 31 October 1989

30 September 1989 441/89 $138,344.40 22 December 1989

31 October 1989 444/89 $192,537.00 13 January 1990

30 November 1989 448/89 $135,476.10 (Not paid)

30 December 1989 449/89 $71,551.80 8 March 1990

31 January 1990 452/89 $88,913.30 (Not paid)



It will be seen that the first progress payment was made more than 30 days after the invoice date. On 25 October 1989 Keppel Finance Ltd (`Keppel`) gave notice to Sembawang that Priser had assigned to it `all moneys owing by [Sembawang] in respect of all present and future jobs` and requested that all future payments for the account of Priser be made to Keppel. Following this, Sembawang made payment to Keppel in respect of invoice Nos 441/89, 444/89 and 449/89. Invoice No 438/89 was paid direct to Priser. Invoice No 448/89 was indorsed by Sembawang without any qualification but has not been paid. Invoice No 452/89 has not been indorsed by Sembawang.

By writ issued on 30 April 1990, Priser sued for the amount claimed to be payable under invoice No 448/89 but the action was stayed in view of a provision for arbitration in the contract. In December 1990 arbitration proceedings were commenced. Priser`s points of claim run into 50 paragraphs and a two-page appendix. Sembawang`s defence and counterclaim run into 51 paragraphs and 28 pages of annexures. The reply and defence to counterclaim run into 42 paragraphs. By a direction made by the arbitrator on 28 February 1992, the hearing will begin on 12 October 1992 and will continue until completion.

On 9 March 1992 Sembawang applied to court for an order for Priser to provide security for costs. The application was heard on 19 June 1992, and at the conclusion, I dismissed it with costs. I intimated to counsel that I would give my reasons later.

Jurisdiction

The application was made pursuant to s 27 of the Arbitration Act (Cap 10) and s 388 of the Companies Act (Cap 50, 1990 Ed). Section 27(1) of the Arbitration Act provides:

The Court shall have, for the purpose of and in relation to a reference, the same power of making orders in respect of any of the
...

To continue reading

Request your trial

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT