SA Shee & Co (Pte) Ltd v Kaki Bukit Industrial Park Pte Ltd

JurisdictionSingapore
JudgeChao Hick Tin JA
Judgment Date11 February 2000
Neutral Citation[2000] SGCA 7
Date11 February 2000
Subject MatterStay of court proceedings,Whether judge's approach in granting application correct,s7 Arbitration Act (Cap 10, 1985 Rev Ed),Whether alleged agreements were "matters arising under or out of or in connection with" contract,Arbitration,Application for stay,"Matters arising under or out of or in connection with",Words and Phrases
Docket NumberCivil Appeal No 108 of 1999
Published date19 September 2003
Defendant CounselHoward Cashin and Lim Khoon (Lim Hua Yong & Co)
CourtCourt of Appeal (Singapore)
Plaintiff CounselVinodh Coomaraswamy (Shook Lin & Bok)

(delivering the grounds of judgment of the court): This was an appeal from the decision of the High Court in SIC 3257/99 in which it stayed the proceedings in Suit 658/99 pursuant to s 7 of the Arbitration Act (Cap 10) (the `Act`) upon the application of the defendants, who were the respondents in this appeal. At the conclusion of the hearing, we dismissed the appeal. We now give our reasons.

The facts

The respondents were the developer of a factory at Kaki Bukit Road 3 (the `project`). The appellants were a building contractor engaged by the respondents as the main contractor for the project pursuant to a building contract (the `contract`). The contract incorporated the Singapore Institute of Architects Conditions of Building Contract (the `SIA Conditions`). In the course of the works, the respondents failed to make payments under five interim certificates issued by the project architect. The appellants brought Suit 658/99 against the respondents to claim payment in respect of those five certificates, including interest and costs. The total amount outstanding under the five certificates was $5,469,137.04.

The respondents denied liability on two grounds.
The first was that the respondents had paid $2m to the appellants` director, Chwee Meng Chong (`Chwee`) and the appellants had agreed that this sum would go towards reducing the amount owed by the respondents to the appellants under the interim certificates. Secondly, the appellants had agreed that the balance of $3,469,137.04 need not be paid until a sum of $9.46m was paid to the respondents by the appellants` associated company, How Hwa Investment Pte Ltd. The background to the alleged two agreements is as follows.

In 1994, one Ho Mun Fei (`Ho`) and Chng Heng Tiu (`Chng`) jointly tendered for the project site and when they succeeded, they incorporated the respondent company and assigned to it the tender award.
Chng`s company, Chng Heng Tiu Pte Ltd and his associates (the `Chng group`), including Chwee, held 64% of the shares in the respondent company. Chwee himself held 5% of the shares in the respondent company. The other 36% was held by Ho and his brother (the `Ho group`).

The respondents commenced the development of the project.
In late 1997, there arose a dispute between the two groups and the Ho group decided to acquire the Chng group`s 64% shareholding in the respondents through their company, Straits International Resources Pte Ltd (`SIR`). On 1 December 1997, an agreement was entered into between members of the Chng group as vendors and SIR as purchasers of the former`s shareholding in the respondents. The purchase price was payable in instalments. In February 1998, SIR stopped payment on these instalments because of a dispute in respect of the agreement of 1 December 1997.

In the meantime, on 8 March 1998, the contract was awarded by the respondents to the appellants.
The link between the appellants and the respondents was in the person of Chwee, who besides being a 5% shareholder in the respondents, was also a majority shareholder and director of the appellants.

In October 1998, the Chng group and the Ho group decided to settle their dispute.
It was agreed that firstly, SIR would proceed with the purchase of the shares of the Chng`s group in the respondents at a reduced price. Secondly, the Chng group would purchase certain units in the project from the respondents for which they would pay 50% of the price up front. Payment for 30% of the sale price was effected. But a cheque for $9.46m, being for the remaining 20%, issued by the Chng group to the respondents, was dishonoured due to a lack of funds. The Chng group then assured the Ho group that funds would be available subsequently. The respondents alleged that as a result thereof, there was an agreement that the appellants would not insist on payment under the interim certificates until the Chng group had paid the $9.46m due to the respondents. In return, the respondents would not sue on the dishonoured cheque. The appellants, however, denied that they had agreed not to receive payment under the interim certificates until the Chng group had paid the $9.46m to the respondents. I shall hereinafter refer to this point as `the collateral agreement question`.

As regards the $2m allegedly paid to Chwee, $1m was allegedly paid to him by one Darwin Liman, an Indonesian businessman (on behalf of Ho Kok Cheong, the project manager of the respondents), in order to secure the discharge from bankruptcy of Ho Kok Cheong under a scheme of arrangement.
That object having failed, Chwee did not return the money. However, Chwee said he had returned the same. As for the other $1m, the respondents claimed that it was a deposit for the sale of shares in the respondents by the Chng group to SIR. This deposit was not yet returned to SIR and was under the control of Chwee as part of the Chng group. The respondents claimed that there was an agreement that the two sums of $1m in Chwee`s control would be used for the payment of the sums owing from the respondents to the appellants under the interim certificates for the project. Again, the appellants denied the existence of this agreement. In any event, the appellants said the two sums, if any, concerned Chwee in his personal capacity and did not concern the appellants. This point involving the two sums will be hereinafter referred to as the `$2m question`.

Notices to terminate

On 11 February 1999, the appellants sent a letter to the respondents giving them notice under cl 33(1)(b) of the SIA Conditions on the ground that the respondents had defaulted in making progress payments as certified by the architect. Clause 33(1)(b) provides:

(1) The Contractor shall be entitled by a written Notice of Termination given to the Employer to terminate his employment under the Contract on any of the following grounds:

...

(b) If the Employer does not pay the Contractor the amount due on any certificates within the Period for Honouring Certificates named in the Appendix hereto (unless and to the extent that under the terms of the Contract the Certificate has been superseded or corrected by a later Certificate or the Employer may be expressly empowered either not to pay, or to make deductions from, the sums shown as due in the certificate) and if such default is continued for 14 days after receipt by registered post or recorded delivery of a prior written notice from the Contractor stating that, failing payment within such further period of 14 days, Notice of Termination will be given under this Condition.



However, just two days later, and without waiting for the 14-day grace period laid down in cl 33(1)(b) to expire, by a letter dated 13 February 1999, the appellants, referring to the letter of 11 February 1999 and invoking cl 33(1)(b), gave the respondents the notice of termination of the contract.


On 22 February 1999, both parties held a meeting and agreed on a `mutual termination` of the contract.
Under the termination agreement, the architect and quantity surveyor would measure and certify the value of work done up to 22 February 1999 and the value of materials on site. The respondents would then pay the appellants such certified sum plus the outstanding sums under the interim certificates by 31 March 1999 and the appellants would vacate the site on that date.

On 24 February 1999, the respondents wrote to the appellants pointing out that the notice of termination of 13 February 1999 was invalid.
But they went on to point out that the matter had been superseded by the termination agreement of 22 February 1999.

However, disputes soon surfaced when the appellants claimed for loss of additional profit `due to further fall in material since award of contract.
` Quite inexplicably, the parties also started to argue if the termination notice of 13 February 1999 was valid. As a result, the appellants continued to remain on the site after 31 March 1999 and what amount was due from the respondents to the appellants could not be resolved. On 8 April 1999, the respondents rescinded the termination agreement and reserved their right to claim damages. The respondents also gave the appellants notice to vacate the site by 15 April 1999. The appellants did not comply with the respondents` notice to vacate. By their letter dated 22 April 1999, the respondents accepted the appellants` repudiation of the contract and reserved their right to claim damages. Eventually, the respondents recovered possession of the site by way of OS 627/99.

The litigation

On 21 April 1999, the respondents gave notice of arbitration to the appellants` solicitors pursuant to cl 37(1) of the SIA Conditions. On 3 May 1999, the appellants took out the writ of summons in Suit 658/99. On 19 May 1999, the respondents took out SIC 3257/99 to stay the proceedings pursuant to s 7 of the Act. On 28 May 1999, the appellants took out SIC 3480/99 for summary judgment on its claim. Both SIC applications were fixed for hearing before the learned Judicial Commissioner Lee Seiu Kin (the judge) on 21 June 1999.

The decision below

The learned judge below ordered that all proceedings in Suit 658/99 be stayed pending arbitration. In view of his order staying the proceedings, he did...

To continue reading

Request your trial
8 cases
  • PT Perusahaan Gas Negara (Persero) TBK v CRW Joint Operation
    • Singapore
    • High Court (Singapore)
    • 20 Julio 2010
    ...(Persero) v Dexia Bank SA [2007] 1 SLR (R) 597; [2007] 1 SLR 597 (refd) S A Shee & Co (Pte) Ltd v Kaki Bukit Industrial Park Pte Ltd [2000] 1 SLR (R) 192; [2000] 2 SLR 12 (folld) Soh Beng Tee & Co Pte Ltd v Fairmount Development Pte Ltd [2007] 3 SLR (R) 86; [2007] 3 SLR 86 (refd) Tiong Huat......
  • Sintal Enterprise Pte Ltd v Multiplex Constructions Pty Ltd
    • Singapore
    • High Court (Singapore)
    • 30 Septiembre 2004
    ...cases cited by the defendant starting with the Court of Appeal decision in SA Shee & Co (Pte) Ltd v Kaki Bukit Industrial Park Pte Ltd [2000] 2 SLR 12 where it was held, inter alia, that the answer to the question whether a dispute fell within an arbitration clause in a contract must depend......
  • The Body Shop (Singapore) Pte Ltd v Winmax Investment Pte Ltd and Another (Obayashi Corporation and Others, Third Parties)
    • Singapore
    • District Court (Singapore)
    • 26 Marzo 2004
    ...against a stay of proceedings: see The Asian Plutus [1990] SLR 543, S.A. Shee & Co Pte Ltd v Kaki Bukit Industrial Park Pte Ltd [2000] 2 SLR 12. 14. In Taunton-Collins v Cromie [1964] 1 WLR 633, the (English) Court of Appeal considered both the above competing principles. In that case, a ho......
  • Choi Peng Kum and another v Tan Poh Eng Construction Pte Ltd
    • Singapore
    • High Court (Singapore)
    • 5 Julio 2013
    ...clause read in the context of the SIA Conditions as a whole. As stated in SA Shee & Co (Pte) Ltd v Kaki Bukit Industrial Park Pte Ltd [2000] 1 SLR(R) 192 at [34]–[37], cited by the respondent, cl 32(8)(a) of the SIA Conditions may be relied on by an employer to withhold payment on interim c......
  • Request a trial to view additional results
4 books & journal articles
  • Contract administration
    • United Kingdom
    • Construction Law. Volume I - Third Edition
    • 13 Abril 2020
    ...at [31]–[36], per Warren Khoo L H J (considering an SIA form of contract); SA Shee & Co (Pte) Ltd v Kaki Bukit Industrial Park Pte Ltd [2000] 2 SLR 12 at [26] (concerning clause 31(11) of an SIA form). Summary judgment may, however, be refused if there is an arguable basis for the validity ......
  • Contract Law
    • Singapore
    • Singapore Academy of Law Annual Review No. 2000, December 2000
    • 1 Diciembre 2000
    ...Ahong Construction (S) Pte Ltd v United Boulevard Pte Ltd[2000] 1 SLR 749; SA Shee & Co (Pte) Ltd v Kaki Bukit Industrial Park Pte Ltd[2000] 2 SLR 12; Hong HUM Development Co (Pte) Ltd v Hiap Hong & Co Pte Ltd[2000] 2 SLR 609; and L & M Concrete Specialists Pte Ltd v United Eng Contractors ......
  • THE CONTRACTUAL BASIS OF THE ENFORCEMENT OF EXCLUSIVE AND NON-EXCLUSIVE CHOICE OF COURT AGREEMENTS
    • Singapore
    • Singapore Academy of Law Journal No. 2005, December 2005
    • 1 Diciembre 2005
    ...why the court should not stay the action to give effect to the agreement: SA Shee & Co (Pte) Ltd v Kaki Bukit Industrial Park Pte Ltd[2000] 2 SLR 12 at [39]. 71 Forum mandatory statutes may require the courts not to give effect to the jurisdiction agreement: The Epar[1984—1985] SLR 409. 72 ......
  • Building and Construction Law
    • Singapore
    • Singapore Academy of Law Annual Review No. 2000, December 2000
    • 1 Diciembre 2000
    ...termination Certificates of payment were again the subject of a dispute in SA Shee & Co (Pte) Ltd v Kaki Bukit Industrial Park Pte Ltd[2000] 2 SLR 12 before the Court of Appeal, this time involving an attempt by the contractor to terminate the contract under cl 33(1)(b) of the SIA Condition......

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT