PPG Industries (Singapore) Pte Ltd v Compact Metal Industries Ltd
Jurisdiction | Singapore |
Judge | Chao Hick Tin JA |
Judgment Date | 14 March 2013 |
Neutral Citation | [2013] SGCA 23 |
Court | Court of Appeal (Singapore) |
Docket Number | Civil Appeal No 125 of 2011 |
Published date | 18 March 2013 |
Year | 2013 |
Hearing Date | 23 October 2012,15 October 2012,27 February 2013 |
Plaintiff Counsel | Nicholas Narayanan (Nicholas & Tan Partnership LLP) |
Defendant Counsel | Michael Por Hock Sing and Er Jing Xian Cindy (Michael Por Law Corporation) |
Subject Matter | Contract,Remedies,Remoteness of Damage,Damages,Assessment |
Citation | [2013] SGCA 23 |
This is the defendant’s appeal against the decision of the High Court judge (“the Judge”) in
Having carefully considered the arguments of both parties, we are of the view that the Judge’s decision and reasoning ought to be affirmed – with the exception of two particular issues (
The damages awarded by the Judge for the additional site preliminaries represented the costs incurred by the plaintiff’s subsidiary, Façade Master Pte Ltd (“Façade”), for the additional days of delay in the completion of the project that were caused by the defendant’s failure to provide paint of a satisfactory quality. These costs include staff salaries, transportation costs, equipment costs and utilities bills. The Judge awarded the plaintiff damages totalling $1,040,662.35 for 273 days’ worth of costs expended on additional site preliminaries. The Judge accepted,
Before us, the defendant argues that it is inequitable for the Judge to allow damages for 273 days of delay when the project’s architects, RSP Architects Planners & Engineers (Pte) Ltd (“RSP”), had granted extensions of time totalling 168 days to the project’s main contractor, Taisei Corporation (“Taisei”), and, as such, the project would have been delayed in any event even if there were no problems with the paint. In support of its position that the Judge’s decision to award 273 days’ worth of additional site preliminaries should be upheld by this court, the plaintiff essentially relies on Pickavance’s view that the paint tonality issue caused a critical delay of 273 days in the completion of the project with no concurrent causes of delay. The plaintiff also points out that the Judge accepted Pickavance’s view and that the defendant had made no arguments that challenged the analysis advanced by Pickavance in his expert evidence.
In our view, the sole issue that arises here is that of
In this regard, both parties’ expert witnesses on the issue of delay, namely Pickavance and Thomas Anthony Harker (“Harker”), proffered diametrically opposed views as to the cause of the 273 days of delay in the completion of the project. Pickavance opined that the defendant’s failure to provide paint of satisfactory quality
In our view, both experts’ positions are unreasonable and cannot, by any measure of logic and common sense, be accepted in their entirety (if at all). It cannot reasonably be said that the defendant’s breach of contract caused absolutely
On the other hand, it seemed (at least at first blush) that the defendant could not have been
We are left with two specific delaying events which are relevant to the present appeal; they are “No Noisy Work/Stop Work Orders” and “Exceptionally adverse weather conditions”, for which 78 days and 9 days of extensions of time, respectively, were granted by RSP. Both delaying events were not attributable to the defendant’s fault, but in all likelihood did contribute to the ultimate delay in the completion of the project. If work at the project site was ordered to stop or weather conditions were so adverse that works could not proceed, it stands to reason and common sense that these two delaying events would have consequently caused some measure of delay in the completion of the project, and it must follow that the defendant should not have been held liable for the delay in the completion of the project which was caused by...
To continue reading
Request your trial-
Ng Tze Chew Diana v Aikco Construction Pte Ltd
...own to counter Mr Goh’s evidence. As the Court of Appeal explained in PPG Industries (Singapore) Pte Ltd v Compact Metal Industries Ltd [2013] SGCA 23 at [10], the opinions of experts “will always remain as opinions and do not bind the court concerned.” It is thus entirely within the remit ......
-
Building and Construction Law
...such evidence may be of limited assistance to the court. 7.15 In PPG Industries (Singapore) Pte Ltd v Compact Metal Industries Ltd[2013] SGCA 23 (‘PPG Industries’), the Court of Appeal had to consider, inter alia, a claim for damages arising from additional site preliminaries. The case conc......