Paragon Shipping Pte Ltd v Freight Connect (S) Pte Ltd
Jurisdiction | Singapore |
Judge | Judith Prakash J |
Judgment Date | 26 August 2014 |
Neutral Citation | [2014] SGHC 165 |
Court | High Court (Singapore) |
Docket Number | Suit No 855 of 2012 |
Year | 2014 |
Published date | 16 October 2015 |
Hearing Date | 19 February 2014,12 February 2014,06 November 2013,05 November 2013 |
Plaintiff Counsel | K Muralitherapany and Koh Seng Tee Edward (Joseph Tan Jude Benny LLP) |
Defendant Counsel | Navinder Singh and Amirul Hairi (Navin & Co LLP) |
Subject Matter | Admiralty and Shipping,Carriage of Goods by Sea,Voyage Charterparties,Contract,Discharge,Anticipatory Breach,Formation,Acceptance |
Citation | [2014] SGHC 165 |
The plaintiff and the defendant are Singapore companies in the business of providing transport services for the import and export of cargo by sea. Neither company is a ship owner or operator. Each of them deals with third party providers of vessels either directly or through another middleman.
This action arises out of arrangements made between the plaintiff and the defendant for the transport of machinery (“the cargo”) from the port of Nanwei in China to Singapore. The exact contractual arrangements are a matter of dispute: the plaintiff’s position is that there were two charter contracts (the “first fixture” and the “second fixture” respectively) between the plaintiff and the defendant by which the plaintiff agreed to supply a vessel to transport the cargo, the second fixture being concluded after the first fixture was cancelled by the defendant. The defendant’s position is that the first fixture was the only contract between the parties and that because the plaintiff breached the terms of the first fixture, the defendant had to ship the cargo by a vessel supplied by a third party.
The plaintiff has sued the defendant for loss of freight and demurrage and the defendant has made a counterclaim for damages for breach of contract and also loss of business arising from a letter written by the plaintiff to the defendant’s customer.
The following main issues arise from the pleadings, evidence and submissions:
All events referred to in this summary of what occurred took place in 2012.
The first fixtureIn July 2012, the defendant entered into a contract with a company called Herrenknecht Asia Headquarters Pte Ltd (“Herrenknecht”) to transport the cargo from China to Singapore and deliver it to Herrenknecht. At about the same time, the defendant’s general manager and director, Marcus Stephen Tan (“Mr Tan”) and its operations manager, Yesica Winata (“Ms Winata”), had discussions with the plaintiff’s director, Madeline Ong Kah Liang (“Ms Ong”), regarding the provision of a vessel to carry the cargo from the port of Nanwei, China, to Singapore.
On 26 July, the plaintiff and the defendant entered into the first fixture by which the plaintiff agreed to provide the vessel “MV Dahua” (the “
The charter contract between the plaintiff and the defendant was a voyage charter and a written document entitled “Fixture Note” was signed by both parties. It contained the following important terms:
02) Loading port: 1SBP Owners Berth Nanwei Port, Guangdong, PR China;
03) Discharging port: 1SBP Owners Berth Singapore;
04) Laycan: 10
th – 20th Aug, 2012;19) Others as per Gencon C/P 1994.
Clause 19 of the Fixture Note incorporated, as part of the first fixture, the terms of the standard form contract devised by The Baltic and International Maritime Council and codenamed “Gencon”. The plaintiff relied on cl 9 of Gencon (“cl 9”) to support its stand. Clause 9 provides:
Such option must be declared by the Charterers within 48 running hours after the receipt of the Owners’ notice. If the Charterers do not excise their option of cancelling, then this Charter Party shall be deemed to be amended such that the seventh day after the new readiness date stated in the Owners’ notification to the Charterers shall be the new cancelling date.
The provisions of sub-clause (b) of this Clause shall operate only once, and in case of the Vessel’s further delay, the Charterers shall have the option of cancelling the Charter Party as per sub-clause (a) of this Clause.
On 30 July, FLS informed the plaintiff that the ship’s agent for the
The defendant was anxious to ship the cargo as early as possible. On 7 August, and again the next day, the defendant wrote to the plaintiff asking for the status of the
The defendant did some investigation of its own and, allegedly, Mr Tan was advised that the
Kindly get the replacement vessel asap by today before noon hrs.
The plaintiff denied that the vessel was anywhere near North Korea. On the afternoon of 13 August, it informed the defendant that the vessel had berthed in Tianjin. On 14 August, FLS informed the plaintiff that due to continuing poor weather conditions and delays at the various ports in the region, the
By 16 August, the plaintiff was able to put forward some “options” (as Ms Ong called them) to the defendant regarding the shipment. In her e-mail sent at 1.35pm that day, Ms Ong told the defendant that the
Mr Tan was upset by that e-mail. In his response, he indicated that if the
It is from this point onwards that the parties’ accounts of what occurred diverge.
According to...
To continue reading
Request your trial-
Paragon Shipping Pte Ltd v Freight Connect (S) Pte Ltd
...Shipping Pte Ltd Plaintiff and Freight Connect (S) Pte Ltd Defendant [2014] SGHC 165 Judith Prakash J Suit No 855 of 2012 High Court Admiralty and Shipping—Carriage of goods by sea—Voyage charterparties—Cancellation clause in standard form contract codenamed ‘Gencon’—Whether disponent owner......