Management Corporation Strata Title Plan No 2827 v GBI Realty Pte Ltd and another
Jurisdiction | Singapore |
Judge | Woo Bih Li J |
Judgment Date | 23 April 2014 |
Neutral Citation | [2014] SGHC 86 |
Court | High Court (Singapore) |
Docket Number | Suit No 920 of 2009 (Registrar’s Appeal No 406 of 2013) |
Published date | 14 July 2014 |
Year | 2014 |
Hearing Date | 18 March 2014,13 January 2014 |
Plaintiff Counsel | Haridas Vasantha Devi (Sim Law Practice LLC) |
Defendant Counsel | Tan Yee Siong and Priscilla Wee (Rodyk & Davidson LLP),Henry Heng and Gina Tan (Legal Solutions LLC) (on watching brief) |
Subject Matter | Civil Procedure,Limitation,Parties,Joinder |
Citation | [2014] SGHC 86 |
This is an appeal from the decision of an Assistant Registrar (“the AR”). The AR allowed an application for the appellant’s statement of claim and action against the respondent to be struck out and dismissed respectively. After hearing arguments, I dismissed the appeal. I was in agreement with the AR that the appellant’s claim against the respondent was time-barred. I now state the reasons for my decision.
BackgroundThe striking-out application arose out of Suit No 920 of 2009 (“the Suit”). The appellant, Management Corporation Strata Title Plan No 2827 (“the MCST”), is the plaintiff in the Suit. The MCST is the management corporation of an industrial development at 59 Ubi Avenue 1, Bizlink Centre, Singapore 408938 (“the Development”). The respondent, Boustead Projects Pte Ltd (“Boustead”), is the second defendant in the Suit. Boustead is the main contractor which was engaged to design and construct the Development. GBI Realty Pte Ltd (“GBI Realty”) is the first defendant in the Suit. GBI Realty was the developer of the Development. Boustead was engaged by GBI Realty to design and construct the Development.
The Development consists of a single 7-storey building with access driveways and other amenities that surround the main building. The access driveways and other amenities were defined as “the Peripheral Regions” by Boustead for easy reference. I will adopt that definition as well. In the Suit, the MCST sought damages for negligent construction of the Development. The MCST claimed that GBI Realty and Boustead negligently failed to take appropriate preventive measures to deal with the soft marine clay subsoil which the Development was purportedly built on. The MCST alleged that the negligence led to a continuous sinking of the ground at the Peripheral Regions. This caused damage to the access driveways and other amenities.
The MCST commenced the Suit by issuing a writ of summons against GBI Realty on 27 October 2009. The writ did not include Boustead as a defendant. The writ was only amended to include Boustead as a defendant close to four years later, on 17 July 2013. The amended writ was served on Boustead on 30 July 2013.
Boustead applied to strike out the MCST’s claim and to dismiss its action against Boustead under O 18 r 19 of the Rules of Court (Cap 322, R 5, 2006 Rev Ed) (“ROC”) on the basis that the MCST’s claim against it was time-barred. The AR allowed the application. The MCST appealed. The sole question before me was whether the MCST’s claim against Boustead was time-barred.
The issuesThe limitation periods for claims are stipulated by the Limitation Act (Cap 163, 1996 Rev Ed) (“the Act”). There are two dates relevant to the application of these limitation periods. The first is the date the limitation period commences. The second is the date the action is brought. A claim will be time-barred if the time between the date of commencement of the limitation period and the date the action is brought exceeds the limitation period stipulated by the Act.
I will first deal with the date the action was brought against Boustead. It was not disputed that the action was brought against Boustead when it was joined to the proceedings as a party. According to
I pause to make an observation on
Under the ROC, Order 15 r 6 is substantially similar to O 15 r 6 of the UK Rules. I agree that the terms are clear and that a person only becomes a party to the proceedings when the writ, which has been amended to include that person as a defendant, is served on him.
In my view, however, there are good reasons why the person to be joined should be deemed to have become a party to the proceedings at the date the amended writ is filed (this was the holding in
Now that I have dealt with the date the action was brought against Boustead, I turn to the date of commencement of the limitation period. This was the substance of the dispute between the parties at the appeal. There were three issues I had to address:
I will give the reasons for my decision in respect of each of these issues after providing a brief sequence of events.
Sequence of eventsOn 1 March 2000, GBI Realty engaged Boustead to design and construct the Development.1 On 31 March 2003, a Temporary Occupation Permit (“TOP”) was issued in respect of the Development.2 The subsidiary proprietors likely took possession of the Development soon after the TOP was issued.3 On 10 November 2003, the MCST was constituted. On 8 January 2004, a Certificate of Statutory Completion was issued in respect of the Development.4
The MCST made a number of complaints about defects in the Development to Boustead between January 2004 and January 2005. On 30 March 2004, the MCST issued a letter of demand to Boustead in respect of defects at the Development. This letter of demand mentioned damage to the Peripheral Regions. It referred to a “[d]riveway sunkened-required [
Boustead carried out rectification works on the Development between April and August 2004 in response to the MCST’s various complaints. Nonetheless, the complaints from the MCST persisted. On 6 September 2004, Boustead sent a letter to the MCST stating that “the Defects Liability Period ... has already expired”, and that “[Boustead] cannot be held responsible for the defects”.6 Boustead nonetheless offered to conduct a subsequent site inspection out of goodwill.
In 2007, the MCST engaged CC Building Surveyor Pte Ltd (“CC”) to produce a report on the problem of soil settlement and related damage to the Development. The report titled “Inspection Report on Building Damage at Bizlink Centre” was dated 20 July 2007 (“the CC Report”). It was produced by Paul Crispin Casimir-Mrowzynski (“Mr Casimir”), a chartered building surveyor with CC, pursuant to a site inspection on 29 May 2007. The CC Report concluded that there was “severe settlement around the building”. Further, the settlement resulted from the soil not being “compacted adequately at the construction stage” and due to “insufficient support to the driveway and related structures”.7
On 21 July 2008, the MCST wrote to Boustead complaining of the “perennial sinking driveway problem”.8 The CC Report was appended to the letter. Boustead responded on 25 September 2008 stating that the sinking of the driveway was not due to inadequate compaction of the marine clay. Boustead’s response further stated that they were “no longer liable for any report of defects ... presented ... after such a long time”.9
On 8 September 2009, the MCST, through its solicitors, Sim Law Practice LLC (“Sim Law Practice”), wrote to GBI Realty (and not Boustead) requesting that the sinking driveway be rectified and threatening legal proceedings.
Legal proceedings were subsequently commenced with the issuance of a writ against one defendant only,
To continue reading
Request your trial-
MCST Plan No 2827 v GBI Realty Pte Ltd
...Corporation Strata Title Plan No 2827 Plaintiff and GBI Realty Pte Ltd and another Defendant [2014] SGHC 86 Woo Bih Li J Suit No 920 of 2009 (Registrar's Appeal No 406 of 2013) High Court Civil Procedure—Limitation—Negligence—Latent damage—What was date on which cause of action accrued Civi......
-
Litigation
...Van Ek Contracting Pty Ltd v Roads Corporation [2007] VSC 336. 133 Management Corporation Strata Title Plan no 2827 v GBI Realty Pte Ltd [2014] SGHC 86 at [10], per Woo Bi Li J. 134 his is the general efect for actions in contract and in tort under the Limitation Act 1980 (UK). See also Ron......
-
Defects
...1 SLr 704; Lian Kok Hong v Ow Wah Foong [2008] 4 SLr 165 at [24]; Management Corporation Strata Title Plan no. 2827 v GBI Realty Pte Ltd [2014] SGhC 86 at [25]–[28], per Woo Bi Li J; Millenia Pte Ltd v Dragages Singapore Pte Ltd [2018] SGhC 193 at [479]–[480], per Quentin Loh J. See also La......