Labroy Offshore Ltd v Master Marine AS and others
Jurisdiction | Singapore |
Judge | Andrew Ang J |
Judgment Date | 27 October 2011 |
Neutral Citation | [2011] SGHC 234 |
Court | High Court (Singapore) |
Docket Number | Originating Summons No 305 of 2011 |
Published date | 23 April 2012 |
Year | 2011 |
Hearing Date | 19 May 2011,06 June 2011 |
Plaintiff Counsel | Steven Lim (Clasis LLC), and Prakash P Mulani and Bhaskaran Sivasamy (M&A Law Corporation) |
Defendant Counsel | Chan Leng Sun and Joanne Chia (Ang & Partners),Lee Eng Beng SC and Lynette Koh (Rajah &Tann LLP) |
Subject Matter | Banking,Contractual Interpretation |
Citation | [2011] SGHC 234 |
The plaintiff, Labroy Offshore Ltd (“Labroy”) entered into a construction contract dated 28 March 2007 (“the Construction Contract”) with the first defendant, Master Marine AS (“MM”) under which Labroy was to construct a self-elevating offshore unit (“the Rig”) for MM. Under the Construction Contract, MM was to pay the contract price in six instalments according to certain milestones. The first five instalments were deemed to be “advances” to Labroy, with the sixth and final instalment due upon delivery. Labroy was obliged to provide Refund Guarantees for repayment of each of the first five instalments, which it did by arranging banker’s guarantees from the second, third and fourth defendants in MM’s favour (“the Refund Guarantees”) to guarantee the refund of MM’s advances upon certain contingencies. The second, third and fourth defendants are Oversea-Chinese Banking Corporation Ltd, United Overseas Bank Ltd and DBS Bank Pte Ltd respectively (collectively, “the Banks”). MM later purported to rescind the Construction Contract under various articles thereof and issued demands for payment under the Refund Guarantees to the Banks. Labroy applied for an injunction to restrain the Banks from paying MM and to enjoin MM from receiving payment thereby.
After hearing the submissions of Labroy, MM and the Banks, I granted Labroy’s application for an injunction against MM. There was no need to make an order against the Banks because they adopted the same position as Labroy. On MM’s request, I reserved my decision on the question of costs. I set out below my reasons for allowing Labroy’s application against MM.
Background factsAs the factual matrix of this case is fairly complex, it will be helpful to explain first the relevant provisions of the Construction Contract and the Refund Guarantees respectively, before explaining the genesis of the dispute.
The Construction Contract and the Refund Guarantees As explained above at
The Refund Guarantees (and not the Construction Contract) provide for three types of “demands”,
The first type of “demand” is the “Initial Demand”: under sub-para (b) of the first sub-para of para 3 of the Refund Guarantees – the sub-clauses are unfortunately not numbered – the Banks are obliged to make payment to MM within 14 Singapore banking days following the receipt of a written demand from MM for refund, such demand stating that the Construction Contract has been cancelled or rescinded by MM.
However, if within five Singapore banking days from the date of the receipt of an Initial Demand the Banks receive notification from MM that Labroy disputes MM’s claim for refund and that the matter has been referred to arbitration, the Banks are entitled to defer payment of the sum claimed under the Initial Demand. The Banks would then only be liable to make payment of the sum eventually adjudged to be due to MM pursuant to an arbitration award or agreed pursuant to a settlement agreement. The sum would be payable immediately upon receipt from MM of a further written demand for such a sum. This is the second type of “demand”,
The third type, the “New Demand”, is that which gave rise to the contention between the parties. The fourth sub-para of para 3 of the Refund Guarantees set out the circumstances in which a New Demand may be made, and they are linked to Labroy’s obligation to provide replacement guarantees to MM. Under the Refund Guarantees, MM was entitled to request replacement guarantees from Labroy:
I pause here to clarify that although the language of Art 3.8 of the Construction Contract and the language of the Refund Guarantees differ in that Art 3.8 refers to “extensions to the Refund Guarantee” while the latter refer to “replacement guarantees”, all parties used the expressions “extensions to Refund Guarantee” and “replacement guarantees” interchangeably. When asked, all parties accepted that in effect the two were the same,
Upon realising that there would be a delay in the delivery of the Rig, MM sent letters to Labroy (dated 12 and 28 January, 14 February, 6 and 17 March and finally 6 April 2011) stating that given the anticipated delay in the delivery of the Rig, the validity period of the Refund Guarantees would have to be extended. While the content of these letters varied, they each ultimately contained some variation of the following:
All parties agreed that the final day for Labroy to procure extensions of the validity period of the Refund Guarantees from 30 April to 31 May 2011 was 12 April 2011. Labroy applied for the said extensions on 6 April 2011; on 8 April 2011 the Banks duly extended the Refund Guarantees to 31 May 2011. However, MM was only informed of these extensions on 12 April 2011.
MM rescinds the Construction Contract and invokes the Refund Guarantees On 11 April 2011, at 9.48pm, Pal Are Sund (“Pal”) from MM wrote to Ms Pearl Ann Jeyaraj of Labroy (“PAJ”) enquiring why Labroy had not sent MM “new [replacement guarantees] within the time frame given in the [Construction Contract]”. PAJ replied on the same day at 10.17pm informing Pal that she was told “that [Replacement Guarantees] will be issued tomorrow (14 working days prior to 30th April)” (
On 12 April 2011, MM sent Labroy a Notice of Rescission, purporting to rescind the contract on two grounds:
Later that day, after the purported rescission, MM served letters of demand to the Banks, seeking payment under the Refund Guarantees. These letters of demand stated that the Construction Contract had been rescinded pursuant to Labroy’s failure to provide extensions to and/or replacement of the Refund Guarantees and to deliver the Rig on the agreed delivery date. Specifically, two types of demands were made by MM:
To continue reading
Request your trial-
Master Marine AS v Labroy Offshore Ltd and others
...This is an appeal against the decision of the High Court judge (“the Judge”) in Labroy Offshore Ltd v Master Marine AS and others [2011] SGHC 234 (“GD”), granting an injunction restraining the second to fourth respondents (together, “the Banks”) from paying the appellant, Master Marine AS (......
-
Master Marine AS v Labroy Offshore Ltd and others
...This is an appeal against the decision of the High Court judge (“the Judge”) in Labroy Offshore Ltd v Master Marine AS and others [2011] SGHC 234 (“GD”), granting an injunction restraining the second to fourth respondents (together, “the Banks”) from paying the appellant, Master Marine AS (......
-
Banking Law
...a matter of construction, the demand for payment comes strictly within the terms of the bond. In Labroy Offshore Ltd v Master Marine AS[2011] SGHC 234 (Master Marine), the plaintiff, Labroy Offshore Ltd (Labroy) entered into a construction contract (Construction Contract) with the first def......
-
Banking Law
...when the demand for payment did not comply strictly with the terms of the performance guarantee: Labroy Offshore Ltd v Master Marine AS[2011] SGHC 234. 5.15 The High Court decision was reversed by the Court of Appeal discharging the injunction to restrain the Banks from making payment to MM......