Kwan Im Tong Chinese Temple and Another v Fong Choon Hung Construction Pte Ltd

JurisdictionSingapore
Judgment Date06 February 1998
Date06 February 1998
Docket NumberCivil Appeal No 100 of 1997
CourtCourt of Appeal (Singapore)
Kwan Im Tong Chinese Temple and another
Plaintiff
and
Fong Choon Hung Construction Pte Ltd
Defendant

[1998] SGCA 7

Yong Pung How CJ

,

M Karthigesu JA

and

L P Thean JA

Civil Appeal No 100 of 1997

Court of Appeal

Civil Procedure–Stay of proceedings–Referral of dispute to arbitration–Whether principles to summary judgment proceedings applicable for stay–Basis of application for stay–Whether case constituted disputed or undisputed claim–Whether there was question fit to be referred to arbitration–Section 7 Arbitration Act (Cap 10, 1985 Rev Ed)

The appellants (“the employers”) engaged the respondent (“the contractor”) to construct their new temple premises. The contract provided for any dispute or difference concerning the contract to be referred to arbitration. The contractor sued the employers for a sum due being an interim payment certified by the architect. The employers applied for a stay of proceedings pursuant to s 7 of the Arbitration Act (Cap 10, 1985 Rev Ed) on the ground that they had a cross-claim for damages for defective works and for liquidated damages for delay in completion.

The judge below refused the stay. He applied principles exercisable by a court in applications for summary judgments and held that the employers had not adduced material facts with sufficient particularity in support of their cross-claim to demonstrate that they had a bona fide defence to the contractor's prima facie valid claim. The employers appealed.

Held, allowing the appeal:

(1) While the application of summary judgment principles in determining whether there was a dispute to be referred to arbitration was not wrong, it should not be an exhaustive means of weighing the claims. Applications of stay such as the present one related to a larger issue of jurisdiction: at [10].

(2) The basis on which the application for stay was brought was a contract where parties had chosen arbitration over the litigation process as the forum for the resolution of their disputes. The court should, save in obvious cases, adopt a holistic and common sense approach to see if there was a dispute. If the defendant, therefore, makes out aprima facie case of a dispute the court should not embark on an examination of the validity of the dispute as though it were an application for summary judgment: at [11] and [14].

(3) In evaluating the affidavit evidence before him, the judge below was prematurely attempting to try the claims. To consider whether there was a question fit to be referred to arbitration, the court could not properly conclude in the light of affidavit evidence alone that the claim was so unanswerable that there was nothing to arbitrate: at [15] and [16].

Channel Tunnel Group Ltd and France Manche SA v Balfour Beatty Construction Ltd [1993] AC 334; [1993] 1 All ER 664; [1993] 1 Lloyd's Rep 291 (folld)

Gilbert-Ash (Northern) Ltd v Modern Engineering (Bristol) Ltd [1974] AC 689; [1973] 3 All ER 195 (refd)

Hayter v Nelson and Home Insurance Co [1990] 2 Lloyd's Rep 265 (refd)

Home and Overseas Insurance Co Ltd v Mentor Insurance Co (UK) Ltd (in liquidation) [1990] 1 WLR 153; [1989] 3 All ER 74; [1989] 1 Lloyd's Rep 473 (folld)

M Eregli, The [1981] 2 Lloyd's Rep 169 (refd)

Peak Construction Ltd v McKinney Foundations Ltd (1971) 69 LGR 1 (refd)

Uni-Navigation Pte Ltd v Wei Loong Shipping Pte Ltd [1992] 3 SLR (R) 595; [1993] 1 SLR 876 (folld)

Arbitration Act (Cap 10,1985 Rev Ed)s 7 (consd)

Rules of Court (Cap 322,R 5, 1997 Rev Ed)O 14

Khush Chopra (Khush Chopra) for the appellants

Charan Singh (Myintsoe Mohamed Yang & Selvaraj) for the respondent.

M Karthigesu JA

(delivering the grounds of judgment of the court):

1 The appellants, registered as Chinese Taoist temples (hereinafter referred to as “the employers”), engaged the respondents who are building contractors (hereinafter referred to as “the contractors”) to construct their new temple premises on Lot 2101 and 2099 Mukim 23 at Paya Lebar Road. On 4 November 1996, the contractors commenced an action in the Subordinate Courts for the sum of $55,590.42 being an interim payment duly certified by the architect. The employers applied to the High Court for a stay of the proceedings pursuant to s 7 of the Arbitration Act (Cap 10) on the ground that they had a cross-claim for damages for defective works and for liquidated damages for delay in completion. The High Court held that the court had a discretion under s 7 of the Arbitration Act whether to order a stay of legal proceedings; the discretion would not be exercised in favour of granting the stay where the party opposing the stay had shown cause to the contrary, as indeed the contractors had done in this case. A stay was therefore refused. The employers appealed against it. We allowed the appeal and now give our reasons. The High Court's judgment is reported at [1997] 1 SLR (R) 907.

Brief facts

2 The contract under which the contractors were engaged is not in the standard form supplied by the Singapore Institute of Architects. In the court below the employers were only able to produce the articles of agreement whereas before us they have sought to produce what is referred to in the articles as the appendix to the agreement. The...

To continue reading

Request your trial
32 cases
  • Novelty Pte Ltd v Amanresorts Ltd
    • Singapore
    • Court of Appeal (Singapore)
    • 31 March 2009
    ... ... and Amanresorts Ltd and another Defendant [2009] SGCA 13 ... its management upon completion of construction. Such “branding agreements” have been entered ... can be akin to engaging in a game of Chinese whispers. We propose to adopt a more reliable ... ...
  • Coop International Pte Ltd v Ebel SA
    • Singapore
    • High Court (Singapore)
    • 4 March 1998
    ...Koh Siak Poo v Perkayuan OKS Sdn Bhd [1989] 3 MLJ 164 (folld) Kwan Im Tong Chinese Temple v Fong Choon Hung Construction Pte Ltd [1998] 1 SLR (R) 401; [1998] 2 SLR 137 (folld) Overseas Union Insurance Ltd v AA Mutual International Insurance Co Ltd [1988] 2 Lloyd's Rep 63 (distd) Taylor v Wa......
  • Mae Engineering Ltd v Dragages Singapore Pte Ltd (fka Dragages et Travaux Publics (S) Pte Ltd)
    • Singapore
    • High Court (Singapore)
    • 25 April 2002
    ... ... Group Ltd & Anor v Balfour Beatty Construction Ltd ... & Ors [1993] 1 All ER 664 (refd) ... Kwan Im Tong Chinese Temple v Fong Choon Hung ... 29.    There is another and more fundamental reason to arrive at the ... ...
  • Four Pillars Enterprises Co Ltd v Beiersdorf Aktiengesellschaft
    • Singapore
    • Court of Appeal (Singapore)
    • 6 February 1999
    ...should not be referred to arbitration lay with the respondents: Kwan Im Tong Chinese Temple v Fong Choon Heng Construction Pte Ltd [1998] 2 SLR 137 at [para ] 14 and JDC Corporation & Anor v Lightweight Concrete Ltd [1999] 1 SLR 615 at [para ] 10. 23.In our opinion, in this case there was a......
  • Request a trial to view additional results
4 books & journal articles
  • Arbitration
    • Singapore
    • Singapore Academy of Law Annual Review No. 2005, December 2005
    • 1 December 2005
    ...45; JDC Corporation v Lightweight Concrete Pte Ltd[1999] 1 SLR 615; Kwan Im Tong Chinese Temple v Fong Choon Hung Construction Pte Ltd[1998] 2 SLR 137; Batshita International (Pte) Ltd v Lim Eng Hock Peter[1997] 1 SLR 241; Aurum Building Services (Pte) Ltd v Greatearth Construction Pte Ltd[......
  • Civil Procedure
    • Singapore
    • Singapore Academy of Law Annual Review No. 2002, December 2002
    • 1 December 2002
    ...6.21 The court referred to the Court of Appeal”s decision in Kwan Im Tong Chinese Temple v Fong Choon Hung Construction Pte Ltd[1998] 2 SLR 137 where it was stated that it was inappropriate for the court to use summary judgment principles to determine whether a stay of summary judgment proc......
  • Arbitration
    • Singapore
    • Singapore Academy of Law Annual Review No. 2004, December 2004
    • 1 December 2004
    ...Arbitration Act (Cap 10, 1985 Rev Ed (‘repealed Act’), namely, Kwan Im Tong Chinese Temple v Fong Choon Hung Construction Pte Ltd[1998] 2 SLR 137 for the proposition that the court could apply principles used in summary judgment proceedings in an application for stay under s 7 of the previo......
  • REFLECTIONS ON THE SINGAPORE INSTITUTE OF ARCHITECTS’ CONDITIONS OF SUB CONTRACT (SECOND EDITION)
    • Singapore
    • Singapore Academy of Law Journal No. 2000, December 2000
    • 1 December 2000
    ...clauses as borne out in two recent Court of Appeal decisions in Kwan Imm Tong Chinese Temple v Fong Choon Hung Construction Pte Ltd(1998) 2 SLR 137 and JDC Corporation v Lightweight Concrete Pte Ltd(1999) 1 SLR 615 is that unless the claim is “undisputed or indisputable”, a stay of proceedi......

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT