Join-Aim Pte Ltd v BS Mount Sophia Pte Ltd and another
Jurisdiction | Singapore |
Judge | Tay Yong Kwang J |
Judgment Date | 09 January 2012 |
Neutral Citation | [2012] SGHC 3 |
Court | High Court (Singapore) |
Docket Number | OS 643 of 2011 |
Published date | 17 May 2012 |
Year | 2012 |
Hearing Date | 11 October 2011 |
Plaintiff Counsel | Tan Chee Meng, SC and Quek Kian Teck (WongPartnership LLP) |
Defendant Counsel | Teh Kee Wee Lawrence and Melvin See Hsien Huei (Rodyk & Davidson LLP),The second defendant unrepresented. |
Subject Matter | Banking,Performance Bonds,Unconscionability |
Citation | [2012] SGHC 3 |
The plaintiff (the main contractor in a building project) sought an injunction to restrain the 1
Having heard arguments by both parties, I decided that the interim injunction granted earlier by Andrew Ang J should stand, pending arbitration between the plaintiff and the 1
The plaintiff is a Singapore incorporated company, having its address at Block 201E Tampines Street 23 #04-94, Singapore 527201.3 It is the main contractor under the Contract (see
The 1
The 2
The plaintiff, as main contractor, entered into a contract with the 1
The architect under the Contract was M/s Ronny Chin & Associates of 147B Selegie Road, Singapore 188313 (“
On 4 March 2011, the Architect issued the Completion Certificate which certified that works under the Contract were completed on 27 August 2010.15 Goh Tong Chuan (“
The director of the Architect, Chin Hong Onn, also known as Ronny Chin (“
On 30 March 2011, the Architect sent the Completion Certificate to the parties by fax. The following day, the Architect informed the parties by letter of the Completion Date of 27 August 2010.18
On 24 May 2011, the plaintiff submitted its request for an extension of time of 298 days. The granting of this extension would bring the plaintiff’s work in line with the Completion Date of 27 August 2010.19
On 22 June 2011, the Architect recommended that an extension of time of 24 days be granted to the plaintiff and this brought the total extension of time to 93 days.20
In an email dated 24 June 2011, the Architect sent the plaintiff a Delay Certificate dated 4 March 2011 which confirmed that:
Goh, in his affidavit, stressed the point that the Delay Certificate was issued only on 4 March 2011, some 6 months after the certified completion of 27 August 2010.22
On 15 July 2011, and pursuant to Clause 37(1) of the Conditions of Contract, the plaintiff commenced arbitration proceedings against the 1
On 20 July 2011, the plaintiff sent the 1
On 27 July 2011, the 1
On 2 August 2011, the plaintiff obtained an interim injunction restraining the 1
In the light of Clause 2 of the Performance Bond and the 1
On 16 May 2011, the plaintiff submitted Progress Claim No. 30 (Revision 4) pursuant to clause 31(2) (a) of the Conditions of Contract for the amount of S$1,197,669.68, in respect of (i) variation works carried out by the plaintiff after completion of the Contract works under Architect’s Instructions No. 38-56, and (ii) variation works carried out by the Plaintiff under several Variation Orders issued by the Architect. In Goh’s affidavit, it stated that the 1st defendant and the Architect did not dispute Progress Claim No. 30 (Revision 4) but they also did not provide any payment response. On 14 June 2011, Progress Claim No. 30 (Revision 4) was resubmitted by the plaintiff to the Architect and the 1st defendant. According to Goh, this amount remains due and outstanding from the 1st defendant to the plaintiff.
Summary of PleadingsThe plaintiff submitted that the injunction ought to be continued on the ground on unconscionability.30
The 1
The plaintiff, in support of its case, essentially stated that31:
In Goh’s affidavit, he stated that it would be “patently unfair” for the 1
The 1
The 1
To continue reading
Request your trial-
BS Mount Sophia Pte Ltd v Join-Aim Pte Ltd
...call on the bond was unconscionable. The Judge’s decision can be found in Join-Aim Pte Ltd v BS Mount Sophia Pte Ltd and another [2012] SGHC 3 (“the GD”). After hearing the parties on 7 February 2012, we dismissed the appeal and allowed the injunction to remain. However, our reasons for so ......
-
BS Mount Sophia Pte Ltd v Join-Aim Pte Ltd
...call on the bond was unconscionable. The Judge’s decision can be found in Join-Aim Pte Ltd v BS Mount Sophia Pte Ltd and another [2012] SGHC 3 (“the GD”). After hearing the parties on 7 February 2012, we dismissed the appeal and allowed the injunction to remain. However, our reasons for so ......
-
Case Note
...or cash-flow to the beneficiary who is entitled to “pay first — argue later” on the guarantee. 1Join-Aim Pte Ltd v BS Mount Sophia Pte Ltd[2012] SGHC 3 at [37], per Tay Yong Kwang J. 2 See discussion at paras 6–10 below of the meaning of unconscionability in the context of performance guara......