Icon Studio Pte Ltd v Kingsley Khoo Hoi Leng
Jurisdiction | Singapore |
Judge | Loo Ngan Chor |
Judgment Date | 18 March 2020 |
Neutral Citation | [2020] SGDC 60 |
Citation | [2020] SGDC 60 |
Court | District Court (Singapore) |
Published date | 01 April 2020 |
Docket Number | DC Suit No. 1811 of 2015 |
Plaintiff Counsel | Mr Mervyn Foo Yeung Chern, Ms Elyssa Tan Jing Ting and Ms Yik Shu Ying (Yi Shu Ying) (M/s Lee & Lee) |
Defendant Counsel | Ms Emily Su and Mr Kenneth Tan (M/s Donaldson & Burkinshaw LLP) |
Subject Matter | Building and Construction Law,Damages for defects,Delay in completion,Incomplete work,Quantum Meruit,Contract,Mitigation of damage,Civil Procedure,Pleadings,Experts |
Hearing Date | 18 March 2020 |
These grounds set out the decision which I make and my reasons therefor in a renovation dispute between the parties, heard by me.
Having carefully read the parties’ closing and reply submissions and examined the record, my decision is to substantially allow the Plaintiff’s claim and to allow a limited portion of the Defendant’s counter-claim.
This dispute concerns renovation works done by the Plaintiff for the Defendant at a condominium unit at “XX-XX Horizon Tower Condominium” (“the flat”).
The Plaintiff’s claim is for outstanding payment of $121,257.69 for the renovation works. The Defendant says that the Plaintiff failed to do the renovations with due care and competence so that they were not reasonably free from defects and fit for their purposes.1 The Defendant says that owing to the alleged defects, whatever sum that may be due to the Plaintiff would be neutralised by the Plaintiff’s counter-claim and result in the Plaintiff having to pay the Defendant $32,019.15 “as rectification costs” and $21,000 “as compensation amount” for loss of use of the flat.2
The Defendant had bought the flat in early 2014. The flat was for the Defendant’s and his family’s occupation.3
In August 2014, the Defendant employed Kloud LLP to draw up a design for the flat.4
The Plaintiff’s claim for the outstanding payment is based on there being three agreements, one for the sum of $110,000 for original works first agreed (“original works”), a second in the sum of $150,000 for variation works (“variation works”) and a sum of $16,257.69 for additional items which the Plaintiff bought and installed at the flat based on several requests made by the Defendant (“additional variation works”). Including a payment of $50,000 which the Defendant made on 9
The Defendant had initially disputed any agreement between the parties, at any rate, for the variation and additional variation works; the Plaintiff having pleaded that the parties agreed on each of the three components of the works6, the Defendant denied this but then pleaded that there was an agreement in respect of the original works7. This position was reiterated in the Defendant’s opening statement.8 In his AEIC, the Defendant admitted that he agreed to the variation works.9 However, he maintained that when the Plaintiff sought a second payment on 3
The Defendant’s case is that there was a firm date for completion of the renovation works in that “the Plaintiff’s Roy represented to the Defendant that the renovation works would be completed by Christmas
The trial occupied three days. The first day was concerned with my hearing and ruling on a preliminary objection of the Defendant. The testimonial part of the trial took place during a later tranche of two days.
Each party called three witnesses.
The Plaintiff called Mr Teo Khoon Ling Roy (“Roy”), the Plaintiff’s director involved in the contractual negotiations with the Defendant12, Mr Johnny Shang Chia Hui, the Plaintiff’s director who supervised the works13 and Mr See Choo Lip, a quantity surveyor who had featured as the parties’ single joint expert14 but whose report and addendum were disowned by the Defendant.
The Defendant himself testified.15 He also called two witnesses. Mr Neo Thiam Soon, a technical officer of Inspect First Singapore Pte Ltd (“Inspect First”), who provided evidence of fact concerning defects he observed at the flat during his site visit on 31
This case has had a troubled procedural history. As parties perhaps realised, the resolution of this dispute would turn much on expert evidence. As I shall explain, this has been so and my decision is informed by my assessment of the merits of the parties’ respective experts’ evidence. In particular, I accept Mr See’s evidence.
I need to first advert to the procedural history because it has an impact on the quality of the experts’ evidence, directly in respect of Mr See’s, and indirectly in respect of Mr Lem’s.
In his preliminary objection, the Defendant claimed that Mr See’s evidence should be inadmissible because of without prejudice privilege.18 Parties had attended mediation sessions at the State Courts Centre for Dispute Resolution from 19
In the letter dated 28
[The Plaintiff] and [the Defendant] have agreed to jointly engage Mr See Choo Lip of PMC World Pte Ltd (“the Expert”) to investigate and provide his impartial findings on the following issues in dispute,
such findings to be regarded as binding on both [the Plaintiff] and [the Defendant]:…20
(emphasis added)
In Part B of the Annex, it was stated that “[The Defendant] says that there were defects in the renovation works – please see Annex A to [the Defendant’s] Defence and Counterclaim dated 15 July 2015.” The “issue” for Mr See’s “determination” was to “determine which of the defects alleged by [the Defendant] are made out and which are not.” and “Insofar as any of the alleged defects are made out, to provide an estimate of the reasonable cost to make good these defects.”
It is noteworthy that the list of defects set out by the Defendant at Annex A of his pleading is taken from an inspection report dated 31
I heard submissions of counsel for the preliminary objection and rendered my oral decision in the afternoon of the first tranche of the trial on 26
It would be apparent that had the Defendant abided by his agreement, Mr See’s views concerning the defects listed in Annex A of his pleading, and rectification costs, would have been the end of the matter and it would have been amicably resolved. In the result, this did not happen.
Indeed, after the trial concluded, the Defendant filed an application to amend his Defence and Counterclaim to include supposedly “incomplete works”. Based on the record, the Defendant’s allegation of incomplete works is derived from Mr Lem’s report (although one cannot be sure about its provenance). The Plaintiff had duly objected to Mr Lem’s evidence including the allegations concerning allegedly incomplete works. Mr Lem had made references to such allegedly incomplete works. Two consequences arose out of these allegations.
On the basis of these allegations, Mr Lem derived “an assessment of the value of the renovation work performed by [the Plaintiff]. He arrived at an estimate of S$183,055.37…”22 (as opposed to the agreed price for the original works and the variation works). Using the alleged value of the work, deducting $68,120 (being the quotation of an entity that did not testify, Heavenly Homestead), adding GST to the difference, and last deducting sums paid to account by the Defendant,
Owing to the position that works remained “incomplete”, Mr Lem opined that the “contract completion date” was 1
In turn, this led to the Defendant saying in opening, the following:
I pause to say that in closing the Defendant has implicitly resiled from that humongous claim for so-called loss of use and fallen back on his pleaded position of 89 days x $7,000,
The Defendant did not make any application to amend his Defence and Counterclaim at any time before or during the trial to...
To continue reading
Request your trial