Hyundai Engineering & Construction Co Ltd v International Elements Pte Ltd
Jurisdiction | Singapore |
Judge | Kannan Ramesh JC |
Judgment Date | 08 July 2016 |
Neutral Citation | [2016] SGHC 132 |
Plaintiff Counsel | Christopher Wong and Chew Wei Jie (cLegal LLC) |
Docket Number | Originating Summons No 204 of 2016 |
Date | 08 July 2016 |
Hearing Date | 25 May 2016,14 April 2016,05 April 2016 |
Subject Matter | Statutes and regulations,Building and Construction Law |
Year | 2016 |
Citation | [2016] SGHC 132 |
Defendant Counsel | Raymond Chan (Chan Neo LLP) |
Court | High Court (Singapore) |
Published date | 14 July 2016 |
Modelled after similar legislation in other Commonwealth jurisdictions, the Building and Construction Industry Security of Payment Act (Cap 30B, 2006 Rev Ed) (“the Act”) came into effect in 2005 with the primary purpose of maintaining liquidity in the construction industry, facilitated by a “fast and low cost adjudication system to resolve payment disputes” (see
The plaintiff, a Singapore-registered foreign company in the business of building construction, was engaged as the main contractor for a project known as “Proposed Conservation & Additions and Alterations to Existing Blocks 1, 9, 14 and NCO Club, and New Erection of 2 Tower Blocks of 34 & 45 Storey, 4 Podium Blocks and 3 Basement Levels, Comprising of Hotels, Offices, Retail Units and Residential Dwelling Units (Total 190 Units) on Lot 858K TS11 at Beach Road (Downtown Core Planning Area)” (“the Project”).
The defendant was a Singapore-incorporated company in the business of the manufacture, production and fabrication of building materials. By a Letter of Award dated 7 August 2013 (“the Letter of Award”) and a Letter of Acceptance dated 11 October 2013 (“the Letter of Acceptance”), the defendant was engaged by the plaintiff as a subcontractor for the “supply, delivery and unloading of stone” to the Project. It was common ground that the agreement evidenced by the Letter of Award and the Letter of Acceptance (“the Subcontract”) fell within the definition of a “supply contract” in s 2 of the Act.
Clause 18 of the terms and conditions in the Letter of Acceptance (“Clause 18”) established a mechanism for the making of periodic payments to the defendant under the Subcontract. It read:
The payment claim that was the subject of the dispute was Progress Claim No 24 (“PC24”), which was served by the defendant on the plaintiff on 20 November 2015. The sum of $1,188,087.59 was claimed under PC24, and it was said to be the cumulative value of the unpaid amounts under the preceding 23 payment claims (“PC1 to 23”) served pursuant to the Subcontract. No new claims were thus made in PC24.
The defendant received no payment or any response providing reasons for non-payment from the plaintiff as regards PC24. As a result, on 22 January 2016, 63 days after the service of PC24, the defendant served a Notice of Intention to Apply for Adjudication of PC24 on the plaintiff and thereafter lodged Adjudication Application No 30 of 2015 (“AA30”) with the Singapore Mediation Centre on the same day. The plaintiff filed its adjudication response on 1 February 2016 relying on reasons that had allegedly been given in the past in relation to PC1 to 23.
The adjudicator found in the defendant’s favour, determining that the defendant was entitled to its revised claim of $974,823.95 and the costs of the adjudication (“the Determination”). The plaintiff, dissatisfied with the Determination, filed OS 204, seeking that it be set aside. There were two grounds which formed the basis for OS 204. The first was that the Determination was made in breach of natural justice as a result of the adjudicator’s refusal to consider reasons for withholding payment that had been provided by the plaintiff
I dismissed OS 204, and the plaintiff has appealed my decision. I set out the grounds of my decision below.
There was no breach of natural justice Section 16(3)(
What constitutes a “relevant due date” in s 15(3)(
The plaintiff adopted a literal approach to the interpretation of s 15(3)(
To continue reading
Request your trial-
AES Façade Pte Ltd v WYSE Pte Ltd
...and rejected, by Kannan Ramesh JC (as he then was) in Hyundai Engineering & Construction Co Ltd v International Elements Pte Ltd [2016] 4 SLR 626. In the course of a comprehensive analysis of the issue, Ramesh JC observed (at [40]) that “the term ‘final determination of those proceedings’ h......
-
Kingsford Construction Pte Ltd v A Deli Construction Pte Ltd
...proceedings against Deli. This is similar to the situation in Hyundai Engineering & Construction Co Ltd v International Elements Pte Ltd [2016] 4 SLR 626, where the court ordered that the money paid into court be released to the defendant even though the matter was pending appeal (at [45]).......
-
Building and Construction Law
...3 SLR 1061 at [41]. 58 [2013] QSC 269. 59 Asplenium Land Pte Ltd v CKR Contract Services Pte Ltd [2016] 3 SLR 1061 at [47]–[48]. 60 [2016] 4 SLR 626. 61 Hyundai Engineering & Construction Co Ltd v International Elements Pte Ltd [2016] 4 SLR 626 at [13]. 62 Hyundai Engineering & Construction......