Ho Pak Kim Realty Co Pte Ltd v Revitech Pte Ltd
Jurisdiction | Singapore |
Judge | Lai Siu Chiu J |
Judgment Date | 19 February 2013 |
Neutral Citation | [2013] SGHC 41 |
Court | High Court (Singapore) |
Hearing Date | 25 June 2012,26 April 2012 |
Docket Number | Suit No 36 of 2006 (Registrar’s Appeals Nos 69 and 70 of 2012) |
Plaintiff Counsel | See Chern Yang (Premier Law LLC) |
Defendant Counsel | Tito Isaac, Justin Chan and Denyse Yeo (Tito Isaac & Co LLP) |
Subject Matter | Contract |
Published date | 27 February 2013 |
This was yet another chapter in the long-running battle between Ho Pak Kim Realty Co Pte Ltd (“the plaintiff”) and Revitech Pte Ltd (“the defendant”) over the construction by the plaintiff of the defendant’s condominium located at No 89 Kovan Road (“the project”) called Kovan Primera. Previous disputes between the parties are encapsulated in my judgments in
The 2007 judgment determined the scope of works of the plaintiff for the project. The plaintiff appealed against the 2007 judgment (in Civil Appeal No 149 of 2007), but did not file the record of appeal/the appellant’s case within the timelines stipulated under Order 57 rule 9 of the Rules of Court (Cap 322, R 5, 2006 Rev Ed). The appeal was deemed to be withdrawn as a result. The 2010 judgment dealt with the merits of the plaintiff’s claim and the defendant’s counterclaim. There, I made the following orders in my judgment (at [135]) delivered on 8 April 2010:
The plaintiff appealed (in Civil Appeal No 74 of 2010) against the 2010 judgment. On 30 September 2010, the plaintiff’s appeal was dismissed, but the Court of Appeal made one variation to the order at [135(g)(ii)] of the 2010 judgment. The variation (as underlined below) reads as follows:
The defendant was awarded interlocutory judgment against the plaintiff for defective construction
limited to (1) the roof and parapet wall; (2) the basement car park; (3) windows, sliding doors, glass balustrades and aluminium trellis; (4) defective marble flooring; (5) external walls; (6) staircases; (7) outdoor shower and (8) exit signagesand in respect of all these items, only if the defendant established that it was subject to any legal obligation to complete the said rectifications. [underlining added]
The defendant filed its notice of assessment, and the assessment of damages for the items set out in [2(f)(i) to 2(f)(iv)] above was conducted by an Assistant Registrar (“the AR”) on 12 October 2011. Four witnesses testified for the defendant, including a quantity surveyor, Martin Anthony Riddett (“Riddett”), who had also testified at the main trial. The plaintiff called no witnesses, although it filed an affidavit of evidence-in-chief (“AEIC”) by its director, Benson Ho Soo Fong (“Ho”). On 10 February 2012, the AR delivered his judgment and awarded the following sums to the defendant:
The AR adjourned to a later date the assessment for the 8 items of defective construction by the plaintiff set out in [2(f)(ii)] above (“the 8 defective items”), directing that it should be undertaken in two stages,
On 21 February 2012, the AR awarded the defendant the costs of the assessment fixed at $35,000, and $9,000 for disbursements.
The plaintiff was dissatisfied with the AR’s decision and filed Registrar’s Appeal No 69 of 2012 (“the plaintiff’s appeal”) against the following orders:
The defendant on its part appealed in Registrar’s Appeal No 70 of 2012 (“the defendant’s appeal”) against the awards for all four items set out in [4] above. It prayed that the sums awarded by the AR for these four items be increased to:
Both appeals came up for hearing before this court.
Counsel for the plaintiff was Mr See Chern Yang (“Mr See”). I should point out that neither Mr See nor his present or previous law firm acted for the plaintiff in the 2007 judgment. Indeed, for the 2010 judgment, the plaintiff changed counsel mid-stream when the case was part-heard. Mr See argued that based on the Court of Appeal’s ruling at [3] above, the defendant had not proved there was a legal obligation on the plaintiff’s part to carry out the rectification works, contrary to the AR’s ruling. Consequently, there should not be a second tranche of hearing to assess the damages for the 8 defective items. He submitted that the defendant’s contention that there was such a legal obligation was misconceived as it was based on the following premise:
As the defendant had not discharged the burden to prove it was legally obliged to rectify the 8 defective items, Mr See argued, the defendant was only entitled to nominal damages at law (see
Consequently, Mr See submitted, there was no basis for the AR to order a second tranche of hearing to assess damages relating to the 8 defective items. Mr See alleged that the defendant had in fact claimed damages beyond the compensatory principle.
As for premise (b) in [8] above, the defendant had relied on the expert opinion of Hoe Ai Sien Mary (“HASM”) of Hoe-Tan (Co) Pte Ltd, who stated that a duty to rectify defects existed. Mr See contended that HASM’s expert testimony should, however, be disregarded as it did not come within the ambit of s 47 of the Evidence Act (Cap 97, 1997 Rev Ed) (“the Evidence Act”), which states:
Opinions of experts
47. —(1) Subject to subsection (4), when the court is likely to derive assistance from an opinion upon a point of scientific, technical or other specialised knowledge, the opinions of experts upon that point are relevant facts.
To continue reading
Request your trial-
Wong Kwee Cheong trading as Hedar Engineering Works v Lim Chye Lim trading as AD-Engineers
...on Contracts volume 1 General Principles 28th edition, 1999. Mr Hanam also referred to Ho Pak Kim Realty Co Pte Ltd v Revitech Pte Ltd [2013] SGHC 41 in which Lai Siu Chiu J, he submitted, appeared to have awarded damages for the plaintiff’s failure to maintain a maintenance crew during the......
-
Ho Pak Kim Realty Co Pte Ltd v Attorney-General
...that it was subject to any legal obligation to complete the said rectifications. Ho Pak Kim Realty Co Pte Ltd v Revitech Pte Ltd [[2013] SGHC 41: This was a cross-appeal by both HPK and Revitech against an Registrar’s assessment of damages for part of the interlocutory judgment ordered agai......
-
Building and Construction Law
...by the buyer. Damages Costs of rectification 7.11 The subject of damages was considered in Ho Pak Kim Realty Co Pte Ltd v Revitech Pte Ltd[2013] SGHC 41, the latest in a trilogy of cases between the same parties which had come before the High Court over the construction of a condominium cal......