Eltron Electrical Engineering Pte Ltd v Right Engineering Pte Ltd
Jurisdiction | Singapore |
Judge | Loo Ngan Chor |
Judgment Date | 15 September 2017 |
Neutral Citation | [2017] SGDC 256 |
Court | District Court (Singapore) |
Hearing Date | 16 March 2017,09 March 2017,19 May 2017,08 August 2017,26 January 2017,07 April 2017 |
Docket Number | DC/DC Suit No. 2202 of 2015, District Court Appeal No. HC/DCA 13 of 2017 |
Plaintiff Counsel | Mr Tang King Kai (M/s TANG & PARTNERS) - |
Defendant Counsel | Mr Nandwani Manoj Prakash (M/s GABRIEL LAW CORPORATION) - |
Subject Matter | Liquidated damages,additional damages,adjudication determination,temporary finality,declaration |
Published date | 18 January 2018 |
I allowed the plaintiff’s claim following a trial. I now set out the reasons for my decision for the purpose of the defendant’s appeal. I do this essentially by enlarging a little on, and adapting from, the brief reasons that I gave parties for my decision.
The defendant was the plaintiff’s labour sub-contractor for certain electrical works connected to the so-called revitalisation of the shops and concourses at Boon Lay Shopping Centre. Materials were provided by the plaintiff. The written sub-contract of the parties was dated 4
The contract:
Clause 1 of the contract stated that the value of the “lump sum contract” was $68,700, excluding GST. By clause 2, the duration of the contract was to be from 1
In essence, the contract required the defendant to install, among other things, the public announcement (“PA”) and fire alarm systems. Clause 3 of the contract read:
The scope of works shall be, but not limited to:
- PA system installation works
- Installation of ceiling speakers, horn speakers, box speakers c/w testing and commissioning and installation of speaker point.
- Fire alarm system installation works
- Installation of heat detector, smoke detector c/w testing commissioning and installation of heater and smoke detector points.
- Electrical installation of works
…
According to a tabular summary accompanying the contract, the total value of the contract was arrived at by toting up the total number of units of the devices, ie, speakers, heat or smoke detectors, and device points, ie, speaker points, heater points or smoke detector points, multiplied by their unit rates. The unit rate per device was $10 and per device point was $30. Testing and commissioning of each lot was priced at $350.ii It was not disputed that the installation of functional device points entailed, not only the putting in place of the device points, but also the laying of conduits, trunkings or cables ending at the device points.
Clause 6 spoke of the defendant having to “comply to our standard terms and conditions as per attached.”
Several of the standard terms may be set out:
The dispute:
In all, the defendant rendered seven progress claims starting from 3
| |||||||
| | | | | | | |
| | | | | | | |
| | | | | | | |
| | | | | | | |
| | | | | | | |
| | | | | | | |
| | | | | | | |
| | | | | | | |
| | | | | | | |
I should note, for completeness, that the total amount with GST paid based on the plaintiff’s certification as stated in the table should have read $30,086.98 (this being the sum of its three component figures) ($7,616.53 + $12,987.93 + $9,482.52) rather than $28,118.67. The sum of $30,086.98 works out to $28,118.67 plus 7% GST. For this purpose, the balance unpaid on the contract, without factoring in GST, was $40,581.33 ($68,700 - $28,118.67).iv I mention this last figure as it was germane to the calculation of certain additional damages which I allowed. (See [42] below.)
The defendant did not wish to accept the plaintiff’s cheque dated 16
The cheque that I just mentioned was the outcome of a joint inspection by parties on 13
The defendant stopped work completely on 14
The plaintiff thereafter took over the works and incurred a sum of $60,967.50 for the labour costs of completing the works, which it did on 27
The plaintiff also claimed liquidated damages from 16
The defendant had taken out an adjudication application under the Building and Construction Industry Security of Payment Act (Cap 30B) (“the Act”) in SOP/AA 115 of 2015 on 24
The plaintiff thus wanted a declaration that it was not liable to pay the adjudicated sum of $27,593.54. The plaintiff relied on s21(3) of the Act and
The defence comprised several points, which I shall deal with when I state my findings below.
The reason for the parties’ different ideas of how much the defendant should be paid for its work turned on whether the defendant should be paid for work it had done towards completing the device points, even though the corresponding conduits, trunkings or cables may not have been, or been fully, laid. The defendant took the view that even where it had not strictly speaking completed a device point, it should have been paid a proportionate amount based on the work it had completed, ie, the laying of conduits or trunkings or cables ending at the corresponding device points. The plaintiff did not agree to this way of looking at it in that it says that it needs to pay only when a device point had been finally completed by connection with the relevant conduits, trunkings and cables.
At the trial, the plaintiff’s director, Mr Tan Meng Choon, and site supervisor, Mr Sivanesan Narainasamy, testified for the plaintiff.
The defendant had three witnesses: Mr Chua Siong Gee, its director, Mr Santiago Domingo Jr Aganan, its assistant project manager, and Mr Chin Loon Choon, its site supervisor.
Owing to the way in which my findings were arrived at, by reference to the objective indicia arising out of relevant documents in the record, I would not be recounting the witnesses’ testimony (although footnote ix below contains a brief reference for the purpose of [11] above).
No apportionment:
I deviate briefly. In my way of looking at it, it is clear that if a device point was completed, the unit rate of $30 became payable. Where it was not completed, the defendant’s claim, if such it was, would really have been one in
To continue reading
Request your trial