Drydocks World-Singapore Pte Ltd (formerly known as Pan-United Shipyard Pte Ltd) v Jurong Port Pte Ltd
Jurisdiction | Singapore |
Judge | Nathaniel Khng AR |
Judgment Date | 30 June 2010 |
Neutral Citation | [2010] SGHC 185 |
Court | High Court (Singapore) |
Docket Number | Suit No 757 of 2009 (Summons No 1811 of 2010) |
Year | 2010 |
Published date | 01 July 2010 |
Hearing Date | 31 May 2010 |
Plaintiff Counsel | Lai Yew Fai, Melissa Marie Tan Shu Ling and Teo Guan Kee (Rajah & Tann LLP) |
Defendant Counsel | Jude Philomen Benny and Grace Lin Li'En (Joseph Tan Jude Benny LLP) |
Subject Matter | Arbitration |
Citation | [2010] SGHC 185 |
This is an application (“the Application”) by the defendant, Drydocks World-Singapore Pte Ltd (“Drydocks”) (formerly known as Pan-United Shipyard Pte Ltd), for,
This judgment contains my decision, as well as brief reasons for my decision. In this judgment, for convenience, the term/condition that the limitation defence be waived in arbitration proceedings will hereafter be referred to as “the Condition” and the term/condition that Jurong Port seeks (see
Jurong Port and Drydocks entered into three separate contracts on 30 June 2000, 14 March 2001 and 29 January 2003. For ease of reference, the three contracts will hereafter be referred to, respectively, as “the 2000 Contract”, “the 2001 Contract” and “the 2003 Contract”, and, collectively, as “the Contracts”. Pursuant to the Contracts, Drydocks was to design, supply, install and commission nine quay cranes (“the Cranes”). The 2000 Contract and 2001 Contract incorporated,
The Contracts each contained a number of clauses that dealt with dispute resolution. The pertinent clauses for present purposes (“the Clauses”), which are identical in each of the Contracts, are as follows:
34.1 Reference to the Superintending Officer - If a dispute or difference of whatsoever kind shall arise between the Employer [
ie , Jurong Port] or the Superintending Officer or the Superintending Officer’s Representative and the Contractor [ie , Drydocks] in connection with or arising out of the Contract or the execution of the Works, whether during the execution of the Works or after their completion and whether before or after any termination of the Contract or the Contractor’s employment, including any dispute or difference as to any opinion, instruction, determination, decision, certificate or valuation of the Superintending Officer or the Superintending Officer’s Representative, it shall in the first place be referred by either party in writing to the Superintending Officer for his decision. Such reference shall state that it is made pursuant to this Clause and a copy shall be sent to the other party to the Contract.- No later than the expiry of 30 days after the date upon which the Superintending Officer received such reference, the Superintending Officer shall give notice of his decision in writing to the Employer and to the Contractor and shall for information state therein that it is given pursuant to this Clause. Such decision shall identify the reference pursuant to which it is made and shall be final and binding on the parties to this Contract unless, as hereinafter provided, either party shall require that the decision should be referred to arbitration.
…
34.2 Reference to Arbitration If either the Employer or Contractor is dissatisfied with the decision of the Superintending Officer made pursuant to Clause 34.1 hereof, or if the Superintending Officer fails to give notice of his decision on or before the expiry of the 30 day period following the date on which the Superintending Officer received the reference, then the Employer or the Contractor may, within 90 days from the date of receipt of the aforesaid decision of the Superintending Officer, or within 90 days from the date of expiry of the aforesaid 30 day period (as the case may be) give notice to the other party with a copy for information to the Superintending Officer of his intention to refer the decision or the dispute or difference that had not been decided to an arbitrator. … Any such reference shall be deemed to be a submission to arbitration within the meaning of the Arbitration Act or any re-enactment or modification thereof.
By about 2004, the Cranes were delivered and put into operation by Jurong Port. In 2007, Jurong Port discovered certain defects in the Cranes, and entered into negotiations with Drydocks for the rectification of the defects. As Drydocks took no steps to rectify the defects, Jurong Port engaged third-party contractors in August 2007 to carry out repair work on the Cranes. Following the completion of the repairs in or around April 2009, Jurong Port entered into negotiations with Drydocks for compensation for the costs of the repairs. Further defects in the Cranes were subsequently discovered. On 4 September 2009, Jurong Port commenced the Action in order to “ensure that it did not fall foul of any limitation periods that may be applicable to its claim”.2 The writ was served on 3 March 2010. Drydocks filed its memorandum of appearance on 10 March 2010. In the statement of claim, which was filed on 19 April 2010, Jurong Port pleaded that defects had been discovered in the Cranes in 2007, 2008 and 2009, and claimed damages from Drydocks on the basis of negligence, breach of contract, breach of warranty, as well as misrepresentation.
On 7 December 2009, Jurong Port referred the matter to the respective Superintending Officers under the Contracts – Ms Mao Whey Ying (“Ms Mao”) for the 2000 Contract (Drydocks seemed to question her status in its letter to her dated 8 April 2010 (see, also,
Ms Mao, on her part, advised the parties, in a letter dated 5 January 2010 that was addressed to Jurong Port and copied to Drydocks, to jointly appoint an independent assessor for the establishment of the material facts and evidence. The parties subsequently entered into discussions on a joint appointment of an independent assessor. On 8 April 2010, Drydocks wrote to Ms Mao to inform her that the parties could not reach an agreement
It was not denied that arbitration proceedings had been commenced with respect to the entire dispute between the parties following the issuance of the two notices of arbitration (“the Notices of Arbitration”) by Drydocks. On each of the two different occasions that Drydocks issued the Notices of Arbitration to Jurong Port, Drydocks concomitantly invited Jurong Port to discontinue the Action. In a letter dated 11 March 2010, Jurong Port offered to discontinue the Action, provided that Drydocks gave its agreement to the Condition. In another letter dated 19 March 2010, Jurong Port offered to discontinue the Action, provided that Drydocks gave its agreement to the Modified Condition. However, Drydocks did not agree to either the Condition or the Modified Condition.
The main submissions of the partiesDrydocks submitted that the Action should be stayed pursuant to s 6 of the Arbitration Act. In support of this submission, Drydocks pointed out that the dispute is subject to valid arbitration agreements between the parties, pleadings had not been delivered and no other step in the proceedings had been taken, it was and still remains ready and willing to proceed with arbitration, and no sufficient reasons exist to show that the dispute should not be referred to arbitration. Drydocks submitted, in the alternative, that the court should exercise its inherent jurisdiction to stay the Action or should stay the Action on the basis of the pending arbitration proceedings on the dispute. Drydocks also submitted that the court should not grant a...
To continue reading
Request your trial