Doshion Ltd v
Jurisdiction | Singapore |
Judge | Choo Han Teck J |
Judgment Date | 28 February 2011 |
Neutral Citation | [2011] SGHC 46 |
Published date | 28 February 2011 |
Date | 28 February 2011 |
Year | 2011 |
Hearing Date | 24 February 2011 |
Plaintiff Counsel | A Verghis and Sandra Tan (Drew & Napier LLC) |
Citation | [2011] SGHC 46 |
Defendant Counsel | Mohan Pillay and Yeo Boon Tat (MPillay) |
Court | High Court (Singapore) |
Docket Number | Originating Summons No 132 of 2011 |
Doshion Limited (“the plaintiff”) is an Indian Company and Sembawang Engineers and Constructors Pte Ltd (“the defendant”) is a Singaporean Company. The plaintiff was the defendant’s sub-contractor. A dispute arose from two sub-contracts (“the Sub-Contracts”) between them. The parties commenced arbitration proceedings (“the Arbitration”) under the arbitration clause in the Sub-Contracts. The Arbitration was scheduled for ten days and was to start on Monday, 28 February 2011. On Thursday, 24 February 2011 the plaintiff applied in this Originating Summons to stop the arbitration, and prayed for:
Counsel for the plaintiff submitted that all disputes in the Arbitration were settled on 15 February 2011 because the plaintiff had accepted the defendant’s proposal in the Settlement Agreement (which counsel conceded was an oral agreement reached between the solicitors for the parties). As such, counsel argued, the Arbitration should have been terminated as of that date.
The defendant disputed the existence of the Settlement Agreement. Further, the defendant contended that the right and power to decide whether there was a Settlement Agreement lay within the jurisdiction of the arbitral tribunal. The defendant interpreted the plaintiff’s argument to be a claim that the arbitral tribunal had become
If there is no dispute between the parties, naturally the arbitration clause cannot be invoked. However, once a dispute arises, including a dispute as to whether there is a dispute at all, the matter falls into the hands of the...
To continue reading
Request your trial-
Bdg v Bdh
...dispute between the parties as it covered whether a settlement agreement was reached: Doshion Ltd v Sembawang Engineers and Constructors [2011] 3 SLR 118 (“Doshion”). On the facts, the Plaintiff had complied with the requirements of the dispute resolution clause. A dispute did arise on the ......
-
Arbitration
...arbitral proceedings by way of a court declaration to that effect was made in Doshion v Sembawang Engineering and Constructors Pte Ltd[2011] 3 SLR 118. In this case, there were disputes between Doshion Limited an Indian company which was a sub-contractor to Sembawang Engineers and Construct......