Diamond Glass Enterprise Pte Ltd v Zhong Kai Construction Co Pte Ltd and another appeal
Jurisdiction | Singapore |
Judge | Woo Bih Li JAD |
Judgment Date | 31 May 2023 |
Neutral Citation | [2023] SGHC(A) 20 |
Court | High Court Appellate Division (Singapore) |
Docket Number | Civil Appeal Nos 125 and 129 of 2021 |
Hearing Date | 06 January 2023 |
Citation | [2023] SGHC(A) 20 |
Year | 2023 |
Plaintiff Counsel | Chan Kah Keen Melvin and Yong Wei Jie Timothy (TSMP Law Corporation) |
Defendant Counsel | Kris Chew Yee Fong and Isabel Su Hongling (Zenith Law Corporation) |
Subject Matter | Building and Construction Law,Damages,Liquidated damages,Scope of works,Variations,Costs |
Published date | 08 June 2023 |
This is a supplementary judgment for the cross-appeals in AD/CA 125/2021 (“CA 125”) and AD/CA 129/2021 (“CA 129”). They arise out of the decision of the High Court judge (the “Trial Judge”) in HC/S 1282/2019 (“S 1282”), published as
The background facts have been comprehensively set out in the Trial Judgment at [1]–[3] and [6]–[27]. We will therefore only highlight the pertinent facts.
Zhong Kai Construction Co Pte Ltd (“ZK”) engaged Diamond Glass Enterprise Pte Ltd (“DG”) as a subcontractor for the supply of materials, equipment and tools to carry out and complete the aluminium cladding of an external facade, blast/ballistic doors and windows, aluminium doors, and window works by a Letter of Award dated 7 November 2016 (the “Subcontract”). These works were for a project for the construction of equipment buildings and facilities at the Singapore Changi Airport.
In S 1282, ZK claimed against DG for liquidated damages arising from DG’s delays. ZK also claimed the sum of $340,233.10 against DG for replacement works arising from DG’s abandonment of the worksite around 6 June 2018 and for rectification works done. ZK further sought to overturn the adjudicated amount that was awarded to DG in Adjudication Determination No 339 of 2019 (“AA 339”) under the Building and Construction Industry Security of Payment Act (Cap 30B, 2006 Rev Ed) issued on 15 November 2019 (the “AD”). DG counterclaimed for,
The Trial Judge allowed ZK’s claims for liquidated damages and the costs of replacement and rectification works in part. The itemised claims were set out in the Trial Judgment at [220] and the Appeal Judgment at [93]. As for DG’s counterclaims, the Judge allowed DG’s counterclaim for payment due under VO 18 in the amount of $5,070 and disallowed DG’s counterclaims for payments in respect of VO 6, VO 8 and VO 19 (see Trial Judgment at [232] and [241] and Appeal Judgment at [6]).
We allowed DG’s appeal in CA 125 in part and ZK’s appeal in CA 129 in part and made,
In this Supplementary Judgment, we address:
Following the release of the Appeal Judgment, the parties sent in various letters in relation to the Appeal Judgment. We set out the background and content of the various letters here.
Background TSMP’s 29 December 2022 Letter On 29 December 2022, DG’s counsel, TSMP, sent a letter to court querying two aspects of the Appeal Judgment (“TSMP’s 29 December 2022 Letter”):
In relation to the Remaining Sums Issue, DG states that it had quantified the remaining sums which ZK would have had to pay DG if the Subcontract was fully performed, amounting to the sum of $90,417.05 in their Appellant’s Case (“AC”) in CA 125, Respondent’s Case in CA 129 and Combined Skeletal Arguments for CA 125 and CA 129. This comprises the following items that ZK would have had to pay DG under the Subcontract:
DG further highlights that these remaining sums accorded with claims which, as
DG points out that this court had addressed the deduction of the Retention Sum (Appeal Judgment at [255]–[261]). However, the Appeal Judgment did not address the remaining works at [10(a)]–[10(c)] above, which amount to $62,514.30. DG thus requests clarification from this court on whether the remaining works in the sum of $62,514.30 are to be accounted for and/or deducted from the costs of the replacement and rectification works awarded to ZK.
Separately, DG highlights an apparent calculation error in the Appeal Judgment (at [279]–[280]). The Appeal Judgment (at [279]) states:
DG was entitled to only $146,647.33 ($197,522.83 less $50,875.5) out of the claimed amount of $264,789.08 (Judgment at [250]).
The figure of $50,875.50 was derived from the total sum for VO 6, VO 8 and VO 18, which the Trial Judge had set aside. However, the accurate total sum for VO 6, VO 8 and VO 18 is $50,857.50, and not $50,875.50. As such, DG suggests that paragraphs [279]–[280] of the Appeal Judgment should be corrected as follows (proposed corrections made in underline):
DG also further highlights that the Judge had allowed VO 18 (which was not challenged by ZK) and therefore, DG is properly entitled to $197,552.83 (and not $192,452.83) out of the claimed amount of $264,789.08, which amounts to 74.6% of the claims made in AA 339. Accordingly, DG submits that [280] of the Appeal Judgment should be corrected accordingly (proposed corrections made in underlined):
On 11 January 2023, ZK’s counsel, Zenith Law Corporation (“Zenith Law”) sent a letter to court responding to TSMP’s 29 December 2022 Letter (“Zenith Law’s 11 January 2023 Letter”). ZK’s position is that:
On 1 March 2023, the court directed that TSMP was to respond in writing to the following queries:
To continue reading
Request your trial