CZT v CZU
Jurisdiction | Singapore |
Judge | Chua Lee Ming J |
Judgment Date | 27 November 2023 |
Neutral Citation | [2023] SGHC(I) 22 |
Court | International Commercial Court (Singapore) |
Docket Number | Originating Summons No 1 of 2023 |
Hearing Date | 04 September 2023 |
Citation | [2023] SGHC(I) 22 |
Year | 2023 |
Plaintiff Counsel | Nair Suresh Sukumaran, Tan Tse Hsien, Bryan (Chen Shixian) and Joel Wang Pinwen (PK Wong & Nair LLC) |
Defendant Counsel | Koh Swee Yen SC, Claire Lim, Pang Yi Ching, Alessa and Teo Wei Kiat Samuel (WongPartnership LLP) |
Subject Matter | Arbitration,Award,Recourse against award,Setting aside |
Published date | 28 November 2023 |
This is an application by the plaintiff to set aside an arbitral award issued by an arbitral tribunal in arbitration proceedings seated in Singapore and conducted in accordance with the Rules of Arbitration of the International Chamber of Commerce 2017 (“ICC Rules 2017”).
Background factsThe plaintiff entered into a contract with the defendant (the “Provisional Contract”) under which the plaintiff contracted to deliver certain component packages that included materials, machinery and equipment (the “Material Packages”) as well as other documentation, designs and services.1 A third party to be appointed by the defendant (the “Contractor”) was to use the Material Packages to construct certain products for the defendant.
Article 1.1 of the Provisional Contract set out the “main obligations” of the plaintiff and the defendant, which included the following:
Subsequently, the defendant appointed the Contractor. The plaintiff, the defendant and the Contractor then entered into an agreement for the transfer of the defendant’s rights and obligations under the Provisional Contract to the Contractor (the “Transfer Agreement”).2
Article 1 of the Transfer Agreement provided that all rights and obligations of the defendant in the Provisional Contract were unconditionally and irrevocably transferred to the Contractor except those “identified” in an attachment to the agreement (the “Attachment”). Article 2 of the Transfer Agreement provided that the defendant was “completely released from all the contractual obligations and waive[d] all contractual rights stipulated in the Provisional Contract except for those as identified in the Attachment”.
The Attachment set out a table containing two columns. The left-hand column was titled “Article” and the right-hand column was titled “Comments”. The table included the following references to and comments on Art 1.1 of the Provisional Contract:
| |
| |
| |
Article 6 of the Transfer Agreement provided that the Transfer Agreement and the Attachment were incorporated and made part of the Provisional Contract.
Two other contracts were entered into:
The defendant alleged that it subsequently discovered that certain components of the Material Packages were defective. The defendant filed an action in the defendant’s home jurisdiction (“Country D”) against the Contractor and the plaintiff (the “Litigation”). The court found the Contractor liable for 30% of the damages suffered by the defendant. The claim against the plaintiff was dismissed due to lack of jurisdiction because of an arbitration agreement in the Provisional Contract.
The arbitration agreement in the Provisional Contract provided for disputes to be settled by arbitration in Singapore by three arbitrators “in accordance with the Rules of Conciliation and Arbitration of the International Chamber of Commerce”.5
The arbitration proceedingsOn 25 April 2019, the defendant commenced arbitration proceedings against the plaintiff (the “Arbitration”).6 In due course, the arbitration tribunal (the “Tribunal”) was constituted, comprising Professor Douglas Jones AO (“Prof Jones”), Professor Keechang Kim (“Prof Kim”) and Dr Philipp Habegger (“Dr Habegger”). Prof Kim was the defendant’s nominee while Dr Habegger was the plaintiff’s nominee. Prof Jones was appointed by the International Court of Arbitration of the International Chamber of Commerce as President of the Tribunal pursuant to Art 12(2) of the ICC Rules 2017.
In brief, the defendant claimed against the plaintiff for damages suffered by the defendant as a result of the plaintiff’s failure to perform its obligations, including its obligation to deliver the Material Packages free from any defect.
The Provisional Contract was governed by the laws of Country D. Under Art X of the relevant Code (the “Code”) in Country D, the defendant was entitled to claim damages against the plaintiff in respect of the defective Material Packages. However, the defendant could rely on Art X only if it had the right to delivery of the Material Packages and this right remained with the defendant after the Transfer Agreement was executed.
The issues in the Arbitration that are relevant to the present proceedings were whether:
The defendant argued in the Arbitration that:
On the other hand, the plaintiff argued that:
No claims were made in the Arbitration with respect to the Domestic Contract. The Contractor’s entitlement (if any) under the Supply Contract or any other contract was also not in issue in the Arbitration.
The Final Award and DissentOn 20 September 2021, the ICC sent the final award (the “Final Award”)15 dated 14 September 2021 to the parties.16 The Final Award was a majority award by Prof Jones and Prof Kim (the “Majority”). The Majority concluded that the defendant had a valid claim against the plaintiff for breach of contract under the Provisional Contract with respect to the plaintiff’s delivery of defective Material Packages, which constituted incomplete performance under Art X of the Code.17 The Majority ordered the plaintiff to pay the defendant damages, interests and costs.18
In brief, the Majority found that:
The Majority’s reasons for its interpretation of the Transfer Agreement included the following:
To continue reading
Request your trial-
CVV V CWB: The Nature Of Set-Aside Applications And Adequacy Of The Tribunal's Reasons
...9. 2 In keeping with convention, the Court anonymized the parties. 3 CVV and others v CWB, [2023] SGCA(I) 9 at para 25. 4 CZT v CZU, [2023] SGHC(I) 22. 5 CVV and others v CWB, [2023] SGCA(I) 9 at para 29, citing Soh Beng Tee & Co Pte Ltd v Fairmount Development Pte Ltd, 2007 SGCA 28. 6 CVV ......