China Railway No 5 Engineering Group Co Ltd Singapore Branch v Zhao Yang Geotechnic Pte Ltd
Jurisdiction | Singapore |
Judge | Chan Seng Onn J |
Judgment Date | 22 May 2019 |
Neutral Citation | [2019] SGHC 130 |
Court | High Court (Singapore) |
Docket Number | Originating Summons No 443 of 2019 |
Published date | 25 May 2019 |
Year | 2019 |
Hearing Date | 13 May 2019,07 May 2019 |
Plaintiff Counsel | Tan Jin Yong (Lee & Lee) |
Defendant Counsel | Choa Sn-Yien Brendon and Zachariah Chow Jie Rui (ACIES Law Corporation) |
Subject Matter | Building and Construction Law,Statutes and regulations,Building and Construction Industry Security of Payment Act,Payment claim,Performance bond proceeds |
Citation | [2019] SGHC 130 |
The present originating summons involves one key issue, namely, whether adjudication under the Building and Construction Security of Payments Act (Cap 30B, 2006 Rev Ed) (“SOPA”) is the appropriate forum to canvass construction disputes that arise purely in relation to performance bond proceeds.
At first blush, the issue appears to have been conclusively decided by Tan Siong Thye J (“Tan J”) in the earlier decision of
On closer inspection, however, it will be seen that the decision in
The plaintiff, China Railway No 5 Engineering Group Co Ltd Singapore Branch (“the main contractor”) engaged the defendant, Zhao Yang Geotechnic Pte Ltd (“the sub-contractor”) to carry out works in relation to the “design and construction of Lentor station and construction of tunnels for Thomson line”.1
The first adjudicationOn 25 September 2018, the sub-contractor issued Payment Claim 35 (“PC35”), claiming from the main contractor a total sum of $848,584.93 (inclusive of Goods and Services Tax (“GST”)).2 The total sum related to works completed from 20 October 2015 to 25 September 2015.3 Following a dispute in relation to PC35, the parties referred the matter to adjudication.
By his AD dated 13 December 2018, the adjudicator determined that $692,051.21 (inclusive of GST) was payable by the main contractor to the sub-contractor (“1AD”).4 It is not disputed that the adjudicated sum was paid in full by the main contractor to the sub-contractor.5
The second adjudicationNot long after 1AD was issued, on 20 December 2018, the main contractor called on an on-demand performance bond issued by the United Overseas Bank Ltd (“UOB”) in favour of the main contractor for the sum of $281,441.95.6 The performance bond had been procured by the sub-contractor to serve as “a deposit or security for the due performance and observance by the Sub-Contractor of all stipulations, terms and conditions contained in the Sub-Contract.”7
As a result of the call on the performance bond, on 25 December 2018, the sub-contractor served Payment Claim 36 (“PC36”) on the main contractor for the sum of $301,142.89, being the value of the performance bond which had been called and 7% GST.8
In response to PC36, the main contractor issued its payment response, disputing the validity of PC36 as there was “no claim for any new works under PC 36 which is a repeat claim”.9 Further, the main contractor explained that PC36 was “not even a claim for construction work under the [SOPA] but rather an attempt by [the sub-contractor] to recover the sum of $281,441.95 paid to [the main contractor] under the unconditional performance bond”.10
Given the dispute between the parties, the matter was referred to adjudication. At the adjudication, the adjudicator held that he had the jurisdiction to adjudicate on PC36 which relatedly
Having found that he had jurisdiction to determine the matter, the adjudicator determined that the main contractor was to pay the sum of $281,441.95 (excluding GST) to the sub-contractor (“2AD”).14 By mirroring the sum called under the performance bond, 2AD reversed the call on the performance bond entirely.
Dissatisfied with the adjudicator’s determination, the main contractor applied to set aside 2AD.
The two issuesTwo interrelated issues arise for my consideration.
The first issue is whether s 10(1) SOPA, which delineates the scope of a payment claim under SOPA, is a mandatory provision, breach of which would mandate the adjudication determination arising from the underlying payment claim to be set aside.
If s 10(1) SOPA is deemed to be a mandatory provision, the second issue is whether a payment claim for performance bond proceeds only is a valid payment claim for the purposes of s 10(1) SOPA.
The first issue: Whether s 10(1) SOPA is a mandatory provision The court’s role in setting aside applications As the Court of Appeal cautioned in
In determining whether the adjudicator has acted in excess of his jurisdiction, the question is whether the SOPA provision alleged to have been breached is a mandatory provision (
In this case, the main contractor relies on the sub-contractor’s alleged breach of s 10(1) SOPA as its primary basis for setting aside 2AD.
Hence, the preliminary question is whether s 10(1) SOPA is a mandatory provision, breach of which enables the main contractor to succeed in its setting aside application.
Section 10(1) SOPA is a mandatory provision In determining whether s 10(1) SOPA is a mandatory provision, the query is whether it is “so important that it is the legislative purpose that an act done in breach of that provision should be invalid” (
In this regard, section 10(1) SOPA provides as follows:
Payment claims
[emphasis added]
By stipulating that the payment claim must be “in respect of a progress payment”, s 10(1) SOPA seeks to limit the scope of any payment claim to claims for progress payments
Furthermore, s 10(1) SOPA limits the persons on whom the payment claim may be served to (a) persons who may be liable to make the payment under the construction contract, or (b) any other persons identified in the construction contract. Payment claims against any other persons would breach s 10(1) SOPA.
Section 10(1) SOPA therefore ensures that only
The importance of ensuring that payment claims remain within the scope of s 10(1) SOPA cannot be understated. As Lee Seiu Kin J highlighted in
To continue reading
Request your trial