CAJ and another v CAI and another appeal
Court | Court of Appeal (Singapore) |
Judge | Andrew Phang Boon Leong JCA |
Judgment Date | 11 November 2021 |
Neutral Citation | [2021] SGCA 102 |
Citation | [2021] SGCA 102 |
Docket Number | Civil Appeals Nos 11 and 43 of 2021 |
Hearing Date | 22 September 2021 |
Plaintiff Counsel | Thio Shen Yi SC, Neo Zhi Wei Eugene and Uday Duggal (TSMP Law Corporation) |
Defendant Counsel | Cavinder Bull SC, Lin Shumin and Amadeus Huang Zhen (Drew & Napier LLC) (instructed), Nicholas Jeyaraj s/o Narayanan (Nicholas & Tan Partnership LLP) |
Subject Matter | Arbitration,Award,Recourse against award |
Published date | 16 November 2021 |
Under Singapore law, the scope for judicial intervention in arbitration proceedings is narrowly circumscribed. In the context of applications to set aside arbitral awards, this is borne out by the fact that a party seeking to challenge an award may only do so on limited statutorily-prescribed grounds. Even then, the court will exercise its power with restraint, setting aside awards
A perusal of the published decisions of the Singapore court would show that, over the past 20 years, approximately only 20% of applications to set aside arbitral awards have been allowed. This attests to the fact that it is not common in Singapore for awards to be set aside, and the courts have only done so in
The heart of these appeals concerns the tribunal’s decision to allow an extension of time to the appellants in respect of a construction project, which had the effect of cutting down the quantum of the liquidated damages for the delay which were otherwise payable to the respondent in full. However, it was undisputed that the issue of an extension of time was not raised in the parties’ pleadings and consequently it did not feature in the Terms of Reference for the arbitration or in the parties’ respective List of Issues. We heard and dismissed the appeals on 22 September 2021. In our view, the Judge was eminently right in holding that the tribunal’s decision to allow the extension of time was in excess of its jurisdiction and in breach of natural justice. We now furnish the full grounds of our decision.
The facts The material facts are comprehensively set out in the Judge’s decision in
The parties’ dispute arose from two contracts (“the Agreements”) for the construction of a polycrystalline silicon plant (“the Plant”). The respondent’s subsidiary was the owner of the Plant and the appellants were the contractors responsible for the construction of the Plant. During the construction of the Plant, issues arose in connection with excessive vibrations in the compressors which were located in the hydrogen unit of the Plant, which remained unresolved as at the contractual date of mechanical completion. Rectification works were eventually carried out in a piecemeal fashion pursuant to the instructions of the respondent’s subsidiary (“the Admitted Instruction”).
Subsequently, the respondent’s subsidiary commenced an arbitration (“the Arbitration”) against the appellants. The Arbitration was seated and conducted in Singapore under the auspices of the International Chamber of Commerce (“ICC”), pursuant to the 2012 ICC Rules (“ICC Rules”). It was heard by a three-member arbitral tribunal consisting of Professor Colin Ong QC (the presiding arbitrator), Professor Doug Jones AO and Dr Reinhard Neumann (collectively, “the Tribunal”). The respondent was subsequently joined to the Arbitration, as the assignee of its subsidiary’s claim against the appellants.
In the Arbitration, the respondent sought liquidated damages from the appellants, alleging that the appellants had caused a 144-day delay in the mechanical completion of the Plant due to the excessive vibrations in the compressors within the hydrogen unit. The appellants’ defence in the Arbitration was two-fold. First, the appellants argued that mechanical completion had been achieved on time, as the vibrations did not materially affect the operation or safety of the Plant. Second, the appellants also contended that any delay was a result of the Admitted Instruction, such that the respondent had waived its right to claim liquidated damages or, alternatively, was estopped from doing so (“the Estoppel Defence”).
It bears emphasis that the appellants’ pleadings
In the respondent’s written closing submissions in the Arbitration, the respondent objected to the appellants’ raising of the EOT Defence, in the following terms:
…
…
[emphasis in original]
In its final award and the addendum to the final award (collectively, “the Award”), the Tribunal found that the appellants had failed to achieve mechanical completion on time. The Tribunal also rejected the Estoppel Defence. However, the Tribunal accepted the EOT Defence, finding that the EOT Defence was “perfectly capable of consideration by the Tribunal” because the respondent had been given the opportunity to make submissions in response to the appellants’ arguments in its written closing submissions. The Tribunal further observed that the appellants were entitled to make use of the existing evidence in the Arbitration to make good the EOT Defence. The Tribunal thus went on to consider the substance of the EOT Defence and eventually decided to extend the time for mechanical completion by a period of 25 days, such that the respondent was only entitled to receive liquidated damages for 74 days instead of 99 days.
Subsequently, the respondent applied to the High Court to partially set aside the Award on the basis that (a) by ruling upon and allowing the EOT Defence, the Tribunal had exceeded the scope of the parties’ submission to arbitration; and/or (b) the Award had been made in breach of natural justice.
The decision belowIn the proceedings below, the Judge allowed the respondent’s setting aside application. As the Judgment itself is quite comprehensive, we highlight only those findings which are relevant to the present appeals.
First, the Judge found that the respondent did not have a fair and reasonable opportunity to respond to the EOT Defence. This was referred to by the Judge as the “Primary NJ Breach”. In the Judge’s view, the EOT Defence was a completely new defence, which was factually and conceptually distinct from the Estoppel Defence. Although the appellants had raised some facts, evidence and arguments as to the time that rectification works would have taken but for the Admitted Instruction, the respondent’s decision not to engage with these points could not be faulted as it did not have to do so in the context of the Estoppel Defence (see the Judgment at [90]–[100]).
Second, the Judge found that the Tribunal had relied substantially on its professed experience in reaching its decision on the EOT Defence (see the Judgment at [167]–[168]). However, the Tribunal did not explain what its experience entailed or what it encompassed, and the parties were not given any opportunity to address the Tribunal on the same. This affected the Award and occasioned prejudice to the respondent, constituting what the Judge termed as the “Secondary NJ Breach” (see the...
To continue reading
Request your trial