BVU v BVX
Jurisdiction | Singapore |
Judge | Ang Cheng Hock JC |
Judgment Date | 13 March 2019 |
Neutral Citation | [2019] SGHC 69 |
Court | High Court (Singapore) |
Docket Number | Originating Summons No 249 of 2016, Originating Summons No 249 of 2016 (Summons No 1731 of 2018) |
Published date | 19 March 2019 |
Year | 2019 |
Hearing Date | 23 November 2018,31 May 2018,22 November 2018 |
Plaintiff Counsel | Jainil Bhandari, Tng Sheng Rong and Stella Ng (Rajah & Tann Singapore LLP) |
Defendant Counsel | Lin Weiqi Wendy, Jill Ann Koh Ying and Wong Yan Yee (WongPartnership LLP) |
Subject Matter | Arbitration,Award,Recourse against award,Setting aside |
Citation | [2019] SGHC 69 |
The originating summons before me is an application to set aside an international arbitral award on grounds of fraud and public policy. The accompanying summons (Summons No 1731 of 2018 ("SUM 1731”)) is an application to set aside a subpoena to produce documents issued against [E], an employee of the respondent, which was the party who succeeded in the arbitration. The issue at the heart of these proceedings is this – after the conclusion of arbitration and the issuance of the final award, did the successful party’s decision not to call certain witnesses to give evidence and disclose certain internal documents, which it did not view as being relevant to its case in the arbitration, render the award that was issued by the tribunal liable to be set aside on grounds of fraud or public policy?
Facts The lead-up to the arbitrationIn January 2011, in response to spiralling food prices and growing concerns about scarcity, the South Korean government embarked on a project (the “Project”) to secure long-term stable lines of food supply from international sources and supplement the domestic food supply. The defendant, BVX (“the Purchaser”), a state-owned company, was appointed to spearhead the Project.
The Purchaser was put in touch with the plaintiff, BVU (“the Supplier”), which recommended that the Purchaser procure food (“the Products”) from South America. The Supplier and the Purchaser began negotiations in mid-2011. On 14 June 2012, after governmental approval was obtained, the Purchaser and the Supplier formally entered into an agreement (“the Agreement”).
The material terms of the Agreement are as follows:
Following the execution of the Agreement, the Purchaser did not submit a rolling forecast. In a letter to the Supplier on 26 December 2012, the Purchaser confirmed a rumour that it had entered into a Memorandum of Understanding (“MOU”) with one of the Supplier’s competitors, [Y Co]. Subsequently, a series of meetings between the parties took place.
On 19 April 2013, the Purchaser forecasted a purchase of 170,000 tons of the Products. This was considerably less than what was stated in the Forecast Range. The Purchaser, however, refused to place any orders under the Agreement. Instead, it began a public tender process. On 25 April 2013, it sent a letter inviting the Supplier to take part in the public tender for the amount of the Products earlier forecasted. Up to the time of the arbitration hearing, the Purchaser had not placed any orders with the Supplier.
The arbitrationOn 25 July 2013, the Supplier commenced ICC Arbitration No 19630/CYK (“the arbitration”) against the Purchaser claiming US$2.25m in damages plus interest for breach of the Agreement, among other requests for relief. According to the Supplier, this figure represented its loss of approximately 3 months of profit from October to December 2012.
The parties’ positions in the arbitration The Supplier alleged that the Purchaser had breached the Agreement by:
The Purchaser’s position was that its obligations under the Agreement were not absolute or binding, but was to instead use its “best commercially reasonable effort” to order and purchase the Products as per the Forecast Range. According to the Purchaser, this was supported by the plain words used in the Agreement. Recourse to extrinsic evidence to interpret the Agreement was therefore unnecessary. It was pointed out that an earlier draft of Clause 6.1 originally provided in mandatory terms that the Purchaser “
The Purchaser argued that the Agreement was “a type of framework agreement”. This was supported by the fact that the Agreement left out key commercial terms such as quantity, quality, supply method, supply date and, in particular, price. The parties had therefore contemplated that separate sale and purchase agreements would have to be concluded between the parties subsequently. Further, there could not have been a binding obligation to order a million tons of the Products annually over a 20-year period given that there was no guarantee that food production, distribution or price would remain stable over the entire period.
The Purchaser added that it was subject to certain laws and regulations in Korea that required it to call for a public tender as it was a state-owned enterprise. This should have been known to the Supplier given that it had knowledge of the Project, and should have aware that the Purchaser, as a state-owned corporation, would be under a statutory obligation to supply goods through a public or competitive tendering process. The standard of “best commercially reasonable effort” did not require the Purchaser to flout Korean public procurement laws by entering into a specially negotiated contract with the Supplier.
On Korean procurement law, the Purchaser took the position that Article 6.1 of the Contractual Affairs Regulations of Public Corporations and Quasi-government Entities (“the Contract Regulations”) required it to conclude contracts by way of a competitive bidding process, which meant, in short, that it had to call a public tender. The Contract Regulations are enacted under the State Act on Contracts to which the State is a Party (“the State Contracts Act”). In addition, the Purchaser contended that none of the exceptions, which would permit a specially negotiated contract (without the need for a public tender) under Article 8 of the Contract Regulations or Article 26 of the Enforcement Decree of the State Contracts Act applied to the situation at hand. The Purchaser disagreed with the Supplier’s reading of Article 4 of the Contract Regulations (see [15] below) as it contended that “international tendering procedures” were different from “public competitive tendering”. As a general rule, even if the Purchaser was exempt from international tendering procedures, it would still have to comply with Article 6 of the Contract Regulations and conduct a public tender.
The Supplier disagreed with the Purchaser’s interpretation of the phrase “best commercially reasonable effort”. The Supplier also argued that the invitation to hold a public tender and the entering of the MOU with [Y Co] were breaches of the Purchaser’s obligation to treat the Supplier as the “most preferred Supplier”.
On Korean procurement law, the Supplier relied on Article 7.1 of the State Contracts Act read with Article 26(1)(
In addition, and alternatively, the Supplier relied on a Note to Annex 3 of the World Trade Organisation Agreement on Government Procurement, as well as Article 4(1)(
Article 4
…
To continue reading
Request your trial-
Bloomberry Resorts and Hotels Inc. v Global Gaming Philippines LLC
...Investment Co Ltd v Goldenray Consortium (Singapore) Pte Ltd [2014] 1 SLR 814 (folld) Boardman v DPP [1975] AC 421 (refd) BVU v BVX [2019] SGHC 69 (folld) BXS v BXT [2019] 4 SLR 390 (refd) BXY v BXX [2019] 4 SLR 413 (refd) Ching Chew Weng Paul, deceased v Ching Pui Sim [2011] 3 SLR 869 (ref......
-
Bloomberry Resorts and Hotels Inc and another v Global Gaming Philippines LLC and another
...Swiss Singapore Overseas Enterprises Pte Ltd v Exim Rajathi India Pvt Ltd [2010] 1 SLR 573 (“Swiss Singapore”) at [64] cited in BVU v BVX [2019] SGHC 69 (“BVU v BVX”) at [46]. In this regard, the court in Beijing Sinozonto considered whether the grounds under s 31(4)(b) of IAA have been mad......
-
Bloomberry Resorts and Hotels Inc and another v Global Gaming Philippines LLC and another
...conceals material information and/or suppresses evidence that would have substantial effect on the making of the award: see BVU v BVX [2019] SGHC 69 at [47] (“BVU”). We further note, however, that in the same paragraph, BVU states that there must be a causative link between any concealment ......
-
Aw And Others v Py And Another
...any claim of alleged misrepresentation. 33. In the passage of the judgment relied upon by Counsel for AW Group, in BVU v BVX [2019] SGHC 69, the Court emphasized (in paragraph 47) that apart from deliberate concealment of “… there must be a causative link between the deliberate concealment ......