Audi Construction Pte Ltd v Kian Hiap Construction Pte Ltd
Jurisdiction | Singapore |
Judge | Sundaresh Menon CJ,Tay Yong Kwang JA,Steven Chong JA |
Judgment Date | 22 January 2018 |
Neutral Citation | [2018] SGCA 4 |
Plaintiff Counsel | Tan Jia Wei, Justin (Trident Law Corporation) |
Date | 22 January 2018 |
Hearing Date | 13 November 2017 |
Docket Number | Civil Appeal No 136 of 2017 |
Published date | 27 January 2018 |
Defendant Counsel | Lee Peng Khoon Edwin, Poonaam Bai d/o Ramakrishnan Gnanasekaran, Amanda Koh Jia Yi and Chow Jia Yao (Eldan Law LLP) |
Court | Court of Appeal (Singapore) |
Citation | [2018] SGCA 4 |
Year | 2018 |
The Building and Construction Industry Security of Payment Act (Cap 30B, 2006 Rev Ed) (the “Act”) was passed to establish “a fast and low cost adjudication system to resolve payment disputes”:
A number of disputes over the interpretation of the Act have reached this court for final determination. On one level, this may suggest that the Act is not achieving its intended purpose. Nonetheless, it would be fair to say that the decisions of this court have helped to resolve a number of issues. This has, in turn, facilitated the adjudication process. Thus, leading commentators in the field have opined that this court’s decision in
This appeal concerned yet another dispute over the interpretation of the Act. Under s 10(2)(
The payment claim thus proceeded for adjudication. There, the respondent for the first time challenged its validity on the basis that it had not been served “on” 20 November 2016, as the parties’ contract had required. The adjudicator rejected this argument and issued the adjudication determination (the “AD”) in the appellant’s favour. The respondent then applied to the High Court to set aside the AD, and the Judge set it aside. He ruled that the Act required the payment claim to be served
The appeal raised a number of interesting issues which we will address here to provide greater clarity and certainty to the adjudication process under the Act. In particular, we will explain how the Interpretation Act (Cap 1, 2002 Rev Ed) (the “IA”) resolves the issue of how parties can perform their obligations when they fall due on a Sunday or a public holiday. We will also explain whether an omission or failure to file a payment response can constitute a waiver of a party’s right to raise an objection to the adjudicator’s jurisdiction or on a breach of a mandatory provision, or estop him from later exercising that right.
FactsThe facts of the case were straightforward and not in dispute. In October 2015, the respondent engaged the appellant as a subcontractor. Under their contract, the appellant was to carry out structural works in the construction of a nursing home.2 By cl 59 of their contract, the appellant was entitled to serve a payment claim on the date for submission of progress claims as set out in Appendix 1 of the contract.3 Appendix 1 of the contract, in turn, stipulated the “[t]imes for submitting progress claims” as the “20th day of each calendar month”.4
The 20th day of November 2016, however, fell on a Sunday. The appellant thought that it would not be feasible to serve a payment claim that day, not least because the payment claim was voluminous and because the respondent’s office was closed. Sensibly, the appellant decided to serve a payment claim two days earlier on the Friday of that week,
Before the adjudicator, the respondent challenged the validity of the payment claim on the basis that it had not been filed on the 20th of the month as the contract required.6 The adjudicator rejected this argument and issued the AD in favour of the appellant in January 2017.7 In February 2017, the appellant applied for and was granted leave to enforce the AD. In the same month, the respondent applied to the High Court to set aside both the AD and the order granting leave to enforce. The Judge heard the respondent’s application in April 2017 and gave judgment for the respondent in July 2017 in
The Judge identified four issues for decision: (a) whether the service of the payment claim was invalid because it had not been served on 20 November 2016; (b) whether the payment claim was invalid because it did not state in its header that it was a payment claim under the Act; (c) whether the respondent had waived its right to object under issue (a); and (d) whether the respondent had waived its right to object under issue (b).8 As the present appeal concerned only issues (a) and (c), we will focus on the Judge’s decision on these issues.
The Judge thought that issue (a) essentially came down to whether, on a true construction of cl 59 read with Appendix 1 of the parties’ contract, the appellant was entitled to serve a payment claim only
The appellant argued that the respondent would suffer no prejudice if a payment claim were to be validly served before the 20th of the month because that allowed the respondent more time to consider the payment claim. The Judge rejected this argument because by s 11(1) of the Act, early service may result in a claimant being entitled to payment on a date earlier than would have been the case if the payment claim had been served on the date specified, given that time for serving a payment response runs from the date a payment claim is served.11 The Judge found arguments based on prejudice unhelpful in any event because the parties had specified the time for submission of payment claims in their contract, and it had to be presumed that there was a reason for this.12 The Judge was also not persuaded by the appellant’s contention that it was impossible to serve a payment claim on a Sunday.13 So the Judge concluded that service of the payment claim had to be done on the 20th day of the month, “neither sooner nor later”.14
On issue (c), the Judge found that the respondent had not waived its right to object to the premature service of the payment claim.15 The Judge did not find it necessary to resolve the apparent conflict between four decisions of the High Court cited by the respondent (
The Judge then considered that even if it were possible to waive an available objection to the invalid service of a payment claim, the respondent had not done so on the facts.16 The Judge thought that it would generally be the case that filing a payment response without raising the objection to service would be inconsistent with any subsequent position that the service was invalid. But the Judge also considered that this did not necessarily extend to the situation where a respondent elects not to file a payment response at all because it has taken the view that the payment claim was invalid for not having been filed in accordance with the provisions of the contract. The Judge saw no reason that a respondent should not be entitled to take such a position and, consistently with it, take no action until he is served with an adjudication application.17 On the facts, the Judge found that the objection was not waived since there was no unequivocal representation that was sufficient to sustain either a waiver by estoppel or a waiver by election.18
As for the remaining issues, the Judge found in favour of the appellant in respect of issue (b)19 and there was therefore no need to consider issue (d).20 However, the Judge observed that if there had been such a need, he would have found that the respondent had indeed waived the objection relating to the payment claim header.21 In the premises, the Judge set aside the AD on the ground that the payment claim had not been served on time in contravention of the mandatory provision in s 10(2)(
To continue reading
Request your trial-
Benlen Pte Ltd v Authentic Builder Pte Ltd
...Grouteam at [49]–[50] and [53], cited with approval by the Court of Appeal in Audi Construction Pte Ltd v Kian Hiap Construction Pte Ltd [2018] 1 SLR 317 (“Audi Construction (CA)”) at [21] and [42]. But all of this only takes us to the point where the parties begin to diverge from the commo......
-
Larpin, Christian Alfred v Kaikhushru Shiavax Nargolwala
...of action for fraudulent misrepresentation: at [216].] Case(s) referred to Audi Construction Pte Ltd v Kian Hiap Construction Pte Ltd [2018] 1 SLR 317 (refd) Broadley Construction Pte Ltd v Alacran Design Pte Ltd [2018] 2 SLR 110 (refd) Chai Cher Watt v SDL Technologies Pte Ltd [2012] 1 SLR......
-
Beyonics Asia Pacific Ltd v Goh Chan Peng
...Pte Ltd v Longstroff AG [2015] 1 SLR 521 at [53]–[54], waiver of rights (see Audi Construction Pte Ltd v Kian Hiap Construction Pte Ltd [2018] 1 SLR 317 (“Audi Construction”) at [58]–[61] and squarely in cases of misrepresentation by silence (see Wee Chiaw Sek Anna v Ng Li-Ann Genevieve [20......
-
Salaya Kalairani (legal representative of the estate of Tey Siew Choon, deceased) and another v Appangam Govindhasamy (legal representative of the estate of T Govindasamy, deceased) and others and another appeal
...waiver or an abandonment of rights, we considered some cases on the same. In Audi Construction Pte Ltd v Kian Hiap Construction Pte Ltd [2018] 1 SLR 317, the Court of Appeal laid down instructive principles on the doctrine of waiver. First, the Court of Appeal defined the term, and held at ......
-
Can Enforcement Of An Adjudication Determination Be Stayed If The Enforcement Respondent Would Be Pushed Into Liquidation?
...in order to disentangle the knot of disputed claims and cross-claims." In Audi Construction Pte Ltd v Kian Hiap Construction Pte Ltd [2018] 1 SLR 317 ("Audi Construction"), the CA explained at [1] that the aim of SOPA was to establish "a fast and low cost adjudication system to resolve paym......
-
Can You Submit A Payment Claim After The Issuance Of A Final Certificate?
...objection pursuant to s 15(3) of the SOPA, following the CA's decision in in Audi Construction Pte Ltd v Kian Hiap Construction Pte Ltd [2018] 1 SLR 317 ("Audi The developer then applied to the HC for the adjudication determination to be set aside. Relying on Audi Construction, the HC expre......
-
Building and Construction Law
...Construction Pte Ltd v Ser Kim Koi [2021] SGHC 9 at [340]–[341], following Audi Construction Pte Ltd v Kian Hiap Construction Pte Ltd [2018] 1 SLR 317 at [57], [58] and [61]. 41 GTMS Construction Pte Ltd v Ser Kim Koi [2021] SGHC 9 at [343]. 42 GTMS Construction Pte Ltd v Ser Kim Koi [2021]......
-
Contract Law
...[1991] 1 QB 1. 26 For completeness, the High Court in this case held that there was no duress which led to the June 2011 Agreement. 27 [2018] 1 SLR 317. 28 See para 12.24 above. 29 [2014] 2 SLR 156. 30 See para 12.1 above. 31 [2019] SGHC 275. 32 [2019] SGHC 59. 33 See para 12.14 above. 34 T......
-
Contract Law
...Yi Peter [2021] SGHC 109 at [194]. 66 Prudential Assurance Co Singapore (Pte) Ltd v Tan Shou Yi Peter [2021] SGHC 109 at [196]–[197]. 67 [2018] 1 SLR 317 at [58]. 68 Audi Construction Pte Ltd v Kian Hap Construction Pte Ltd [2018] 1 SLR 317 at [61]. 69 Prudential Assurance Co Singapore (Pte......
-
Building and Construction Law
...Maxwell, 10th Ed, 2016) at para 3–078. 59 Millenia Pte Ltd v Dragages Singapore Pte Ltd [2018] SGHC 193 at [415]. 60 Act 47 of 2018. 61 [2018] 1 SLR 317. 62 (2017) 18 SAL Ann Rev 131. 63 Audi Construction Pte Ltd v Kian Hiap Construction Pte Ltd [2018] 1 SLR 317 at [23]. 64 Audi Constructio......