Anti-Corrosion Pte Ltd v Berger Paints Singapore Pte Ltd and another appeal
Jurisdiction | Singapore |
Judge | Chao Hick Tin JA |
Judgment Date | 02 November 2011 |
Neutral Citation | [2011] SGCA 57 |
Court | Court of Appeal (Singapore) |
Docket Number | Civil Appeal Nos 224 and 240 of 2010 (Suit No 989 of 2009) |
Published date | 10 November 2011 |
Year | 2011 |
Hearing Date | 28 April 2011 |
Plaintiff Counsel | Philip Fong Yeng Fatt, Jonathan Yuen Djia Chiang and Joana Teo Swee Ling (Harry Elias Partnership LLP) |
Defendant Counsel | Ang Cheng Hock SC, Sathiaseelan s/o Jagateesan, Kenneth Lim Tao Chung and Ramesh Kumar Ramasamy (Allen & Gledhill LLP) |
Subject Matter | Contract,Breach,Commercial Transactions,Sale of Goods |
Citation | [2011] SGCA 57 |
This appeal and cross-appeal concern a dispute between a paint manufacturer and a painting subcontractor on whether latent defects in the supplied paint led to the serious discolouration of the internal surfaces at various parts of a building project. The subcontractor sued for losses,
A High Court judge (“the Judge”) dismissed the subcontractor’s claim and allowed the manufacturer’s counterclaim for the sum of $72,676.62; see
Both parties now appeal against different aspects of the judgment below. The subcontractor contends that the Judge had erred on the issue of causation while the manufacturer is appealing against the above-mentioned… that if I had to decide on the issue of the warranty, I would have found that [the Respondent]] had warranted all its products used in any of the plaintiff’s projects for a period of 5 years provided that the use was based on a proposed paint system by the defendant.
The subcontractor is Anti-Corrosion Pte Ltd (“the Appellant”). It provides construction and renovation services, which include paint application works. Its managing director is Lim Choon Lin Vincent (“Vincent Lim”). Among the Appellant’s personnel, he was the one who liaised most often with the Respondent’s representatives.
Berger Paints Singapore Pte Ltd (“the Respondent”) is the paint manufacturer and supplier. Its sales representative, Joseph Yong, conducted the sale negotiations with Vincent Lim. Rajeev Goel is the Respondent’s regional technology manager who was in charge of the Respondent’s investigations after the paint discolouration occurred. Its superior was Jaideep Nandi, the chief executive officer of the Respondent.
FactsThe Respondent supplied the Appellant with paint on three separate occasions prior to the project in question. The first time it did so was in 2005 for the painting of the external surfaces of a Toh Guan dormitory. The project was completed without any complaints.
Subsequently, in January 2006, the Respondent proposed to the Appellant and supplied a paint system for the Toh Guan Road East Capital One project (“the Toh Guan project”). Unlike the earlier project, the painting works were for external and internal surfaces. The Respondent’s Decora Emulsion paint (“the paint”) was used for the internal surfaces. The Respondent’s product data sheet stated,
This was not all that Joseph Yong did to prevail upon the Appellant to accept the Respondent’s proposal. He again directly addressed the Appellant’s concerns in a subsequent letter (“13 January letter”):4
With reference to the above subject and our discussion regarding the coating for the internal concrete surfaces including ceiling. :Proposed Paint System for Toh Guan Road East Capital One We are pleased to forward out letter for your submission to your client that it
is not a [sic] necessary to apply a sealer coat before applying Berger Decora Emulsion even though it was stated in our product datasheet. [emphasis added]
With reference to the above subject, we will be providing you with Subject: Warranty five (5) years warranty on our products used in any of your up coming project as long as is based on our proposed paint system [sic].[emphasis added]
The Toh Guan project was completed uneventfully. After this, the Respondent supplied paint to the Appellant for a third project at No 2 Toh Tuck Link (“the Toh Tuck Link project”). For this, it did not submit a proposal for a paint system.
The Respondent then supplied the Appellant with the same Decora Emulsion paint for a project at Bukit Batok Street 23 (“the Bukit Batok project”)
The Appellant’s account was that, having learnt about the Appellant’s intended bid for the Bukit Batok project, Joseph Yong approached Vincent Lim in July 2007 with a proposal to use the Respondent’s paint. The Appellant asserts that it had relied on the Respondent’s assurances on the suitability of the paint in submitting its winning bid for the project. Joseph Yong, it maintains, gave similar verbal assurances about the suitability of using the paint without the prior application of a sealer coat to Vincent Lim. Vincent Lim testified that this was the reason why he did not seek written confirmation from the Respondent that a sealer coat was unnecessary. He was also led to believe the warranty, as stated in the 13 January letter, would continue to apply to this project.
The Respondent disputed the Appellant’s claim that Joseph Yong actively sought the latter’s business support or that he advised the Appellant on the paint system. The Respondent claimed that it supplied paint to the Appellant on a “supply-only” basis6 and that the Appellant purchased the paint not because of Joseph Yong’s advice but because it was cheap. Regrettably, we note that the Respondent did not take steps to ensure that Joseph Yong testified in Court. All the Respondent could baldly state was that its advice on the appropriate paint system for the Bukit Batok Project was not given. We therefore accept Vincent Lim’s evidence on these issues.
The requisite painting works were carried out between September 2007 and April 2008. During this period, the Respondent delivered the paint to the Appellant as and when the latter required it. According to the Respondent, the paint came from several different production batches. The Judge at
Sometime in April 2008, it was observed that there was serious pinkish discolouration of the paint on the internal surfaces of the Bukit Batok Project. The Judge found, in the judgment at
To continue reading
Request your trial-
Anti-Corrosion Pte Ltd v Berger Paints Singapore Pte Ltd
...Pte Ltd Plaintiff and Berger Paints Singapore Pte Ltd and another appeal Defendant [2011] SGCA 57 Chao Hick Tin JA , Andrew Phang Boon Leong JA and VK Rajah JA Civil Appeals Nos 224 and 240 of 2010 (Suit No 989 of 2009) Court of Appeal Commercial Transactions—Sale of goods—Breach of contrac......
-
Security for performance
...Council v Ryarsh Brick Co Ltd (1985) 4 Con LR 85 at 89, per Judge Newey QC; Anti-Corrosion Pte Ltd v Berger Paints Singapore Pte Ltd [2011] SGCA 57 at [26]–[27]. Compare Fuji Seal Europe Ltd v Catalytic Combustion Corp (2005) 102 Con LR 47 at 74 [149]–76 [158], per Jackson J. If a warranty,......
-
Litigation
...114 CLR 164; Stewart v Dillingham Constructions Pty Ltd [1974] VR 24 at 28. 980 Anti-Corrosion Pte Ltd v Berger Paints Singapore Pte Ltd [2011] SGCA 57 at [37]; Paciic Marine & Shipbuilding Pte Ltd v Xin Ming Hua Pte Ltd [2014] SGHC 102 at [64]–[67], per Quentin Loh J; Kalzip Asia Pte Ltd v......
-
Defects
...BHP Billiton Petroleum Ltd v Dalmine SpA [2003] BLR 271 at 277 [25], per Rix LJ; Anti-Corrosion Pte Ltd v Berger Paints Singapore Pte Ltd [2011] SGCA 57 at [37]. 450 BHP Billiton Petroleum Ltd v Dalmine SpA [2003] BLR 271 at 279 [36], per Rix LJ. 451 See, by way of illustration, Brit Inns L......