Anti-Corrosion Pte Ltd v Berger Paints Singapore Pte Ltd
Jurisdiction | Singapore |
Judge | Philip Pillai J |
Judgment Date | 08 May 2012 |
Neutral Citation | [2012] SGHC 101 |
Court | High Court (Singapore) |
Docket Number | Suit No 989 of 2009 |
Published date | 14 May 2012 |
Year | 2012 |
Hearing Date | 06 July 2010,28 June 2010,05 July 2010,02 July 2010 |
Plaintiff Counsel | Jonathan Yuen and Joana Teo (Harry Elias Partnership LLP) |
Defendant Counsel | Sathiaseelan s/o Jagateesan, Kenneth Lim and Ramesh Kumar (Allen & Gledhill LLP |
Subject Matter | Contract |
Citation | [2012] SGHC 101 |
The plaintiff is a painting contractor and the defendant is a manufacturer and supplier of paint. The full account of the background to the dispute arising between the parties is set out in
For the purpose of this judgment, which deals solely with the assessment of damages, it suffices to set out the following salient facts. The plaintiff was subcontracted to paint the surfaces of a building project at Bukit Batok Street 23 (‘the Bukit Batok project”) which included:
In
The Court of Appeal dismissed the defendant’s cross-appeal on the warranty at
... Joseph Yong made his statements to Vincent Lim intending the latter to rely on them. We therefore find the following assurances given by Joseph Yong were express terms of the contract:
- the Respondent's Decora Emulsion paint would be fit for application on the internal surfaces of the Bukit Batok project, without the need for a sealer coat; and
- the provision of a five-year warranty for the paints used in the Bukit Batok project, provided the use of paint was based on a proposed paint system by the Respondent: see [9] and [10] above as well as [42]-[45] below.
The Court of Appeal allowed the plaintiff’s appeal and made the following findings:
This assessment of damages follows the Court of Appeal’s findings.
My decisionThe plaintiff’s claim of $1,185,545.60 for special damages is as follows:1
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
The general rule is that special damages have to be strictly proven and are otherwise not recoverable (
The plaintiff claims that the entire area that required repainting were as follows:
The plaintiff claims $52,242.75 for its purchase of 43,400 litres of replacement paint from Haruna (S) Pte Ltd.
In its closing statement, the defendant acknowledged that:2
… the Plaintiff is entitled to recover this head of claim should the Defendant be found liable for the discoloration and if the Defendant is permitted to recover damages beyond what the parties had contractually agreed.
The defendant has since been found by the Court of Appeal to be liable for the discolouration and damages. Accordingly, the plaintiff is entitled to claim for $52,242.75 under this head.
Sub-Contractor for repainting works by Swiss Plan Construction Pte LtdThe plaintiff claims the sum of $224,000.00 as the cost of hiring Swiss Plan Construction Pte Ltd (“Swiss Plan”) to carry out the repainting works of the 2nd storey to the 19th storey of the 30-storey building (Building B), comprising the units’ ceiling and wall and basement-corridor ceiling. This was completed by March 2009. As this is fully documented in Swiss Plan’s statement of final account dated 23 March 2009, and is not disputed, I allow this head of claim.
Other heads of claims What remain to be assessed are the plaintiff’s other heads of claim arising out of the plaintiff’s repainting works for 6 of the 9 storeys of Building A, comprising 176,882 m
I note that the number of workers originally deployed in the paintworks was a monthly average of about 20 whilst it was claimed that a monthly average of 23 workers for the repainting. From the invoice submitted by the subcontractor, Building B was completed by the sub-contractor by March 2009. Taking into account that the repainting of Building B had been subcontracted out, and that the plaintiff only repainted 6 storeys of Building A, it would be safer to adopt a measure of the work done by reference to the 7.5 months taken to repaint both Building A and Building B which was 7.5 months and to take into account the respective paint surfaces.
Based on the constant of the surface area, Building A comprised around 63.7% of the total surface area originally painted (
The bulk of the plaintiff’s damage claim is for $631,685.09 allegedly being the cost of paying its workers to carry out its repainting works. To support its claim, the plaintiff produced monthly payslips acknowledged by its workers. Based on the payslips, the plaintiff allegedly took 16,142 man days, or 16 months, to repaint the affected area.3
As the plaintiff had already sub-contracted the repainting works of Building B to Swiss Plan, the plaintiff is only entitled to recover the workers’ salary for repainting 6 storeys of Building A.
The additional time required for repaintingHowever, I was mindful that the...
To continue reading
Request your trial