Ang Cheng Guan Construction Pte Ltd v Corporate Residence Pte Ltd
Jurisdiction | Singapore |
Judge | Lee Seiu Kin J |
Judgment Date | 24 January 2017 |
Neutral Citation | [2017] SGHC 9 |
Plaintiff Counsel | Edwin Lee, Yong Boon On, Jasmine Chan and Amanda Koh (Eldan Law LLP) |
Date | 24 January 2017 |
Docket Number | Originating Summons No 774 of 2016 |
Hearing Date | 28 October 2016,20 September 2016 |
Subject Matter | Adjudication,Building and construction law,Dispute resolution |
Year | 2017 |
Defendant Counsel | Chuah Chee Kian Christopher, Tan Li Hsiang Pamela, Chen Hong Lynn and Jin Shan (WongPartnership LLP) |
Court | High Court (Singapore) |
Citation | [2017] SGHC 9 |
Published date | 19 April 2017 |
In this originating summons, the applicant, Ang Cheng Guan Construction Pte Ltd (“ACG”), seeks to set aside the adjudication review determination dated 13 July 2016 (“the Adjudication Review Determination”) in adjudication review application no SOP/ARA 03 of 2016 (“the Adjudication Review Application”). After hearing submissions from counsel for the parties on 20 September and 28 October 2016, I reserved judgment. I now give my decision.
Background The respondent, Corporate Residence Pte Ltd (“CR”), had engaged ACG to carry out works in a construction project. On 18 March 2016, ACG took out adjudication application no SOP/AA 102 of 2016 (“the Adjudication Application”) in relation to a payment claim dated 22 February 2016 (“the Payment Claim”). Five issues (“the AA Issues”) were determined by the adjudicator (“the Adjudicator”) in the resulting adjudication (“the Adjudication”):
In relation to the 1st AA Issue, the Adjudicator found in favour of ACG and determined that the Payment Claim was not served out of time. With respect to the 2nd AA Issue, the Adjudicator found that the Payment Responses were valid. On the 3rd AA Issue, ACG had claimed that it was entitled to EOT for four delay events characterised as: (a) “Piles Removal Delay”; (b) “Piles Re-Casting Delay”; (c) “Drawings Delay”; and (d) “ERSS Delay”. The Adjudicator determined that ACG was entitled to an additional EOT of 133 days beyond what was granted by the architect for the first delay event (
The net result was that CR was found liable to pay ACG the sum of $467,428.69 (“the Adjudicated Amount”). The Adjudicator also awarded interest and ordered that CR bear 70% of the costs of the Adjudication.
On 19 May 2016, CR lodged the Adjudication Review Application pursuant to s 18(2) of the Building and Construction Industry Security of Payment Act (Cap 30B, 2006 Rev Ed) (“the Act”). In compliance with s 18(3) of the Act, CR paid the Adjudicated Amount to ACG prior to the lodgement. A review adjudicator (“the RA”) was appointed by the Singapore Mediation Centre.
At the adjudication review (“the Adjudication Review”), CR sought a review of two of the Adjudicator’s determinations:
In connection with the review of these two determinations, CR framed the following issues for determination by the RA (“CR’s Issues”):
In respect of CR’s 1st Issue, the RA found that the “Contract Variation Notice” did not constitute a valid and/or proper notice which complied with cl 23(2) of the Conditions of Contract. On CR’s 2nd Issue, the RA found that the Adjudicator was wrong to have found that ACG was entitled to an additional EOT of 133 days. In consequence of this finding, the RA held that CR had validly imposed liquidated damages on ACG for delayed completion.
At the same time, ACG was
However, the RA formed the view that his jurisdiction was limited to the determination of the issues raised by CR in the Adjudication Review (
This is the first time that the question of the scope of an adjudication review has come up before the High Court. As noted in
At the heart of the matter is the question: what is the scope of an adjudication review? ACG submitted that a review adjudicator is entitled to review the entire adjudication determination (“the Broad Interpretation”). On the other hand, CR submitted that an adjudication review is restricted to only the issues raised by the respondent (“the Narrow Interpretation”) because of the following factors:
It is convenient at this point to dispose of the second factor submitted by CR. The adjudication regime is a creature of the Act, which establishes an entirely new regime for the purpose of providing a fast but interim means for resolving payment disputes in the construction industry. It is therefore incorrect to draw an analogy to appeals in court proceedings which are not only governed by different legislation but, more importantly, provide for a final decision arrived at after a comprehensive process that ensures that all relevant facts and legal arguments are fully ventilated. These are two entirely different processes. The correct approach to resolving the question in the present case is to consider the provisions in the Act and the Building and Construction Industry Security of Payment Regulations (Cap 30B, Rg 1, 2006 Rev Ed) (“the Regulations”), secondary materials such as Parliamentary debates, as well as the policy behind the Act.
With this in mind, I turn to consider the provisions in the Act and the Regulations which relate to adjudication review. They are found in ss 18 and 19 of the Act and reg 10 of the Regulations.
Sections 18 and 19 of the Act provide as follows:
Adjudication review applications
18. —(1) This section shall apply to a respondent who is a party to an adjudication if the adjudicated amount exceeds the relevant response amount by the prescribed amount or more.(2) Subject to subsection (3), where a respondent to whom this section applies is aggrieved by the determination of the adjudicator, the respondent may, within 7 days after being served the adjudication determination, lodge an application for the review of the determination with the authorised nominating body with which the application for the adjudication had been lodged under section 13.
(3) Where the respondent is required in consequence of the adjudication determination to pay an adjudicated amount to the claimant, the respondent shall not lodge any application for the review of the determination unless he has paid the adjudicated amount to the claimant.
(4) An adjudication review application —
... - shall be made in writing addressed to the authorised nominating body requesting it to appoint one or more review adjudicators to determine the application;
To continue reading
Request your trial-
CMC Ravenna Singapore Branch v CGW Construction & Engineering (S) Pte Ltd
...that have been issued in the High Court are the recent decisions of Ang Cheng Guan Construction Pte Ltd v Corporate Residence Pte Ltd [2017] 3 SLR 988 (“Ang Cheng Guan”) and Mataban Development Pte Ltd v Black Knight Warrior Pte Ltd [2017] SGHCR 12 (“Mataban Development”). Also, the adjudic......
-
Mataban Development Pte Ltd v Black Knight Warrior Pte Ltd
...on the other hand, raises a fairly recent High Court decision in Ang Cheng Guan Construction Pte Ltd v Corporate Residence Pte Ltd [2017] 3 SLR 988 (“Ang Cheng Guan Construction Pte Ltd”) which, at first blush, appears to be at some variance in approach with that advocated in SEF Constructi......
-
Building and Construction Law
...Ltd v JH Projects Pte Ltd [2017] SGHC 238 at [33]. 113 Strategic Construction Pte Ltd v JH Projects Pte Ltd [2017] SGHC 238 at [57]. 114 [2017] 3 SLR 988. 115 Ang Cheng Guan Construction Pte Ltd v Corporate Residence Pte Ltd [2017] 3 SLR 988 at [19]. 116 Ang Cheng Guan Construction Pte Ltd ......