Golden Pacific International & Holdings (S) Pte Ltd v JL Marine & Engineering Pte Ltd
Jurisdiction | Singapore |
Judge | Lim Mei Yee Elaine |
Judgment Date | 31 January 2023 |
Neutral Citation | [2023] SGDC 32 |
Court | District Court (Singapore) |
Docket Number | District Court Suit No 767 of 2021 |
Hearing Date | 04 October 2022,06 October 2022,12 January 2023 |
Citation | [2023] SGDC 32 |
Year | 2023 |
Plaintiff Counsel | Lim Zhi Ming, Max (Rajah & Tann Singapore LLP) |
Defendant Counsel | Twang Kern Zern, Simone Bamapriya Chettiar (Central Chambers Law) |
Subject Matter | Contract,Breach,Remedies,Damages,The broad ground 'exception',Cost of cure,Loss of amenity,Evidence,Admissibility of evidence,Hearsay,Weight of evidence |
Published date | 22 November 2023 |
The present proceedings arise from two agreements between the parties for the design, supply and installation of two shipsets of Heating, Ventilation and Air Conditioning (“HVAC”) systems (each an “Agreement” and collectively, the “Agreements”), one for the vessel TK 343 (also known as “Go Koi”) and the other for the vessel TK 344 (also known as “Golden Honour”) (collectively, the “Vessels”).
The plaintiff claimed against the defendant for failing to supply and install HVAC systems for the Vessels in accordance with the contractual specifications. By the time of this decision, the only live claims are the “Temperature Claim”, and the “Mist Eliminators Claim”, as defined below. The defendant counterclaimed for the balance unpaid contract price of $26,800 under the Agreement for TK 344.
After considering the pleadings, evidence and submissions of the parties, I allow the Temperature Claim but award only nominal damages to the plaintiff, and allow the Mist Eliminators Claim and the counterclaim their entirety. The reasons for my decision are set out below.
The undisputed factsThe plaintiff is a Singapore company in the business of ship-owning and chartering. The defendant is a Singapore company in the business of engineering design, supply, installation, servicing, testing and commissioning of HVAC and refrigeration provision systems for the marine and offshore industries.1
On or about 28 January 2014, the parties entered into the Agreements, under which the defendant agreed to sell, design, supply and install, among other things, two shipsets of HVAC systems (one for each Vessel) for the contract price of $268,000 per Vessel.2 The Agreements were contained in the defendant’s quotations dated 11 January 2014, which were accepted and confirmed by the plaintiff on or about 28 January 2014.3 The terms of the Agreements were identical save that they pertained to different Vessels.
For the purposes of this Suit, the material terms in each of the Agreements are as follows:
| | |
| ||
| | |
| | |
| ||
| | |
| |
Two (2) Units of ‘JLM’ SM-6012 ‘Marine Type’ sea water-cooled condenser of 90/10 Cu/Ni tubes and bronze cover material construction material construction suitable for seawater application, inclusive of receiver, safety valve and purge valve.
Mist Eliminators, Weather-Tight Louvers and Ventilators: One (1) Complete Set
One (1) complete set of Mist Eliminators, Weather-tight louvers, Mushroom and Gooseneck Ventilators shall be provided including Engine Room Fan Louvers. The Mist Eliminators for AHU and Engine Room Fans Fresh Air Intake shall be of stainless steel S/S 316L material construction.
20% Payment Upon Order Confirmation
40% Payment Upon Delivery of Equipment
30% Payment Upon Delivery of Site Installation Material
20% Progressive (Pending Site Installation)
10% Upon Commissioning of Systems
On or about 27 February 2015, the parties agreed to vary the Agreements to upgrade the cooling capacity of the HVAC systems of the Vessels from 150 Kw to 200 Kw, in exchange for the plaintiff’s payment to the defendant of an additional $20,000 per shipset.8 This variation was contained in the defendant’s quotations dated 18 December 2014, which were accepted and confirmed by the plaintiff on or about 27 February 2015.9 The terms of the variation of the Agreements were identical save that they pertained to different Vessels.
At the time the Agreements were concluded and subsequently varied, the plaintiff was the owner of the Vessels.10
The Vessels were constructed at a yard in Batam, Indonesia (“the yard”). Sometime in the second half of 2015, the defendant delivered its purported mist eliminators for the Vessels to the yard. In June 2016, the defendant installed the HVAC systems of the Vessels.11 The installation was completed by no later than 24 June 2016.12 The HVAC systems of the Vessels are identical.13
In early December 2017, the defendant conducted commissioning testing for the HVAC system of TK 343, during which it measured the temperatures produced by the system during the testing. These temperatures were recorded in a commissioning report dated 10 December 2017 (the “Commissioning Report”).
Since early 2018, TK 343 has been chartered to GO Marine and deployed in Broome, Australia.
In or around May 2021 and March 2022, the plaintiff sold TK 344 and TK 343 respectively. The plaintiff did not carry out any repairs to the HVAC systems of the Vessels before the Vessels were sold.
The parties’ cases The plaintiff’s case The plaintiff pleaded three heads of claim against the defendant.
In its Statement of Claim, the plaintiff identified the following losses arising from these heads of claim:
The plaintiff claimed $250,000 in damages, or alternatively, damages to be assessed.20
In its Defence to Counterclaim, the plaintiff denied that the balance contract price of $26,800 under the Agreement for TK 344 is payable to the defendant.21 The plaintiff also pleaded that even if it is liable for the balance contract price of $26,800:
In its closing submissions, the plaintiff no longer pursued the Condenser Claim, or the Survey and Testing Costs in relation to the Temperature Claim. However, the plaintiff sought the following additional remedies for the Temperature Claim:23
The plaintiff also submitted, as its sole defence to the counterclaim, that the defendant’s non-compliance with the Temperature Requirement afforded it a complete defence pursuant to section 53(1) of the SGA. This was because the diminution in value of the HVAC systems on account of the defendant’s breaches is the entire contract price under the Agreements.24
The defendant’s case The defendant denied the plaintiff’s claims and pleaded the following defences:25
To continue reading
Request your trial