SC Construction & Renovation Pte Ltd v Jinzhou Construction Pte Ltd
Jurisdiction | Singapore |
Judge | Tan May Tee |
Judgment Date | 16 May 2019 |
Neutral Citation | [2019] SGDC 98 |
Court | District Court (Singapore) |
Hearing Date | 16 May 2019,18 April 2019,12 April 2019 |
Docket Number | Summons No. 1400 of 2019, District Court Originating Summons No. 42 of 2019, RAS 13/2019 |
Plaintiff Counsel | Mr Ng Hweelon (Veritas Law Corporation) |
Defendant Counsel | Mr Ashok Kumar Rai (Eversheds Harry Elias LLP) |
Subject Matter | Building and Construction Law,Building and Construction Industry Security of Payment Act,Stay of enforcement of adjudication determination |
Published date | 07 August 2019 |
The Plaintiff was engaged by the Defendant pursuant to a Letter of Award dated 8 March 2018 (“LOA”) as its sub-contractor for the works described as “
The LOA provided that the Plaintiff would carry out the Sub-Contract Works in accordance “
On 25 December 2018, the Plaintiff sent a payment claim, Payment Claim No. 16, to the Defendant by email claiming the sum of $193,040.63 (inclusive of 7% GST) for work done up to and including 25 December 2018. The Defendant responded by email on 26 December 2018 stating that the claim was not accepted with the reasons
When no payment was received, the Plaintiff proceeded with an Adjudication Application under the Building and Construction Industry Security of Payment Act (Cap 30B) (“SOPA”) on 28 January 2019. While the Adjudication Application was still being determined, the Defendant commenced action in the High Court in HC/S 218/2019 claiming
The Adjudicator issued his Adjudication Determination dated 5 March 2019 wherein he identified two issues that he had to deal with, namely:
With regard to the first issue, the Adjudicator made the finding that the email sent by the Defendant on 26 December 2018 was not a valid payment response as required by the relevant provisions in SOPA and related regulations. The Defendant’s complaints with regard to the Sub-Contract Works carried out by the Plaintiff’s workers and its counterclaim were therefore not taken into consideration by the Adjudicator. On the second issue, the Adjudicator found that the Plaintiff had established a
As the Adjudication Determination was served on the Defendant on 6 March 2019, the Defendant was obliged to make payment of the adjudicated amount with interest by 13 March 2019. Payment was not made as required which led to the Plaintiff filing an
On 18 March 2019, the Court granted leave for enforcement of the Adjudication Determination as prayed for in the originating summons and entered judgment in the Plaintiff’s favour together with costs of the application fixed at $1,200. The Order of Court was extracted on 19 March 2019.
On 11 April 2019, the Defendant filed a summons (DC/SUM 1400/2019) seeking the following orders:
Although the summons was filed as an
To continue reading
Request your trial