Tech-System Design & Contract (S) Pte Ltd v WYWY Investments Pte Ltd
Jurisdiction | Singapore |
Judge | Edmund Leow JC |
Judgment Date | 31 March 2014 |
Neutral Citation | [2014] SGHC 57 |
Court | High Court (Singapore) |
Docket Number | Originating Summons No 785 of 2013 |
Year | 2014 |
Published date | 11 April 2014 |
Hearing Date | 01 November 2013,20 January 2014 |
Plaintiff Counsel | Lee Chay Pin Victor (Chambers Law LLP) |
Defendant Counsel | Tay Wei Heng Terence (Terence Tay) |
Subject Matter | Banking,Performance Bonds |
Citation | [2014] SGHC 57 |
The defendant is a property developer. On 29 October 2009 it engaged the plaintiff as its main contractor for the development of three blocks of apartments at Oei Tiong Ham Park. Under the main contract, the plaintiff was required to and did provide two performance bonds for the sum of $988,888.80 (10% of the total contract price) in lieu of a deposit as security for performance of its obligations.
A dispute arose between the parties, which was subsequently referred to arbitration. Arbitration had not yet begun when on 14 August 2013 the defendant issued demands to the insurer for the total amount of the performance bonds. The plaintiff claimed the calls were unconscionable and filed this application for an injunction to restrain the defendant from calling on the performance bonds “until the determination or outcome of the arbitration hereto”.
I heard the application on 1 November 2013 and dismissed it the same day with costs of $10,000 to the defendant. On 5 November 2013 the plaintiff wrote in to request for further arguments to be made. I agreed and heard the plaintiff’s further arguments on 20 January 2014 but saw no reason to disturb my earlier decision.
I thereupon dismissed the application and awarded costs of the hearing of $4,000 to the defendant. The plaintiff has now appealed and these are the grounds for my decision.
Background to the disputeUnder cl 41 of the main contract, the plaintiff was required to pay 10% of the contract price to the defendant as security deposit for the due performance and observation of its obligations under the contract. In lieu of the security deposit, the plaintiff procured two performance bonds from EQ Insurance Company (“the insurer”): the first, for the sum of $542,128.80 was dated 16 November 2009; and the second dated 4 February 2010 was for the remaining sum of $446,760, for a total of $988,888.80.
The plaintiff commenced work under the main contract in November 2009. The original completion date was set for 3 July 2011. However, in the course of excavation works, there was an incident of soil slippage which resulted in the Building and Construction Authority (“the BCA”) issuing a stop work order on 15 January 2010. On 14 September 2010, the stop work order was lifted and work was recommenced and completed in January 2012.
Following two inspections by the BCA, a temporary occupation permit was finally issued on 13 August 2012.
There were two main areas of dispute between the parties.
The first involved the defendant’s entitlement to liquidated damages under the main contract. This was stated to run at a rate of $6,000 a day beyond the original completion date unless an extension of time was granted. The plaintiff made a first application for extension of time on 8 May 2011 and continued to make further applications as work progressed.
In the event, on 10 July 2013, the architect informed the plaintiff that he was unable to assess several of the plaintiff’s applications for extension of time. An extension of only 56 days was granted in the end. This meant a total of 351 days of delay not covered by extensions of time and according to the defendant, this rendered the plaintiff liable to about $2.1m in liquidated damages. The plaintiff claimed that the architect had wrongly failed to consider its applications for extensions of time.
The second source of dispute was the plaintiff’s obligations under the main contract to remedy defects that arose during the one-year defects liability period. This period expired on 13 August 2013. The architect arranged for a site inspection on 2 August 2013 for the purpose of ascertaining the defects that had to be rectified.
The plaintiff claimed that on that day no inspection was carried out and it was presented with a
These two disputes were to be referred to arbitration pursuant to cl 37(1) of the main contract. However the defendant said it was still entitled to call on the performance bonds because it was claiming from the plaintiff more than the sum secured by the bonds. The relevant clauses (cll 5) in the terms of the two performance bonds were materially the same and stated that the insurer was:
… obliged to effect the payment in full forthwith or the direction within 30 business days of our receipt thereof [of a demand on the bond], without requiring any proof that your entitlement to such sum or sums under the Contract or that the Contractor has failed to execute the Contract or is otherwise in breach of the Contract, and notwithstanding the existence of any differences or disputes between yourself and the Contractor arising under or out of or in connection with the Contract or the carrying out of work thereunder or as to any amount or amounts payable thereunder and notwithstanding that such differences or disputes have been referred to arbitration or are the subject of proceedings in Court or is in the midst of any other means of dispute resolution or any request or instruction which may have been given to us by the Contractor not to effect the payment.
It was not disputed that pursuant to cl 5 the defendant was entitled to call on the bonds and the insurer had the corresponding obligation to pay on them “without requiring any proof” as to the defendant’s entitlement to such sums.
Issues before the court and parties’ arguments The sole issue in this case was whether the defendant’s call on the performance bonds was unconscionable. Unconscionability has been held to include the elements of abuse, unfairness and dishonesty and the applicant for equitable relief has to establish this to the high threshold of a strong
The plaintiff said the call was unconscionable for the following three broad reasons:
The defendant said the call could not be unconscionable because:
To continue reading
Request your trial-
Tech-System Design & Contract (S) Pte Ltd v WYWY Investments Pte Ltd
...Design & Contract (S) Pte Ltd Plaintiff and WYWY Investments Pte Ltd Defendant [2014] SGHC 57 Edmund Leow JC Originating Summons No 785 of 2013 High Court Banking—Performance bonds—Unconscionability—Contract for construction works—Disputes arising sent for arbitration—Whether defendant empl......
-
Security for performance
...Mount Sophia Pte Ltd v Join-Aim Pte Ltd [2012] SGCA 28 at [18]–[19]; Tech-System Design & Contract (S) Pte Ltd v WYWY Investments Pte Ltd [2014] SGHC 57 at [15], per Edmund Leow JC; JK Integrated (Pte Ltd) v 50 Robinson Pte Ltd [2015] SGHC 57 at [23]–[27], per Hoo Sheau Peng JC; Arab Bankin......