Vertex Far East Pte Ltd v S A C (PTE) LTD
Jurisdiction | Singapore |
Judge | Loo Ngan Chor |
Judgment Date | 28 June 2010 |
Neutral Citation | [2010] SGDC 272 |
Court | District Court (Singapore) |
Hearing Date | 12 February 2010,06 November 2009,09 October 2009,23 November 2009,12 July 2010,22 December 2009,28 June 2010 |
Docket Number | District Court No 4057 / 2008 / N, District Court Appeal No 34 of 2010 |
Plaintiff Counsel | Melvin Chan (TSMP Law Corporation) |
Defendant Counsel | Selvaraj (Myinstoe & Selvaraj) |
Published date | 15 February 2011 |
By a letter of acceptance1 dated 2nd November 2007, the Housing and Development Board appointed the plaintiff as main contractor for site clearance and infrastructure works for a site at Lorong Halus C1 (“the project”) to be used for the stockpiling of sand and granite. The main contract was dated 18th April 20082. The consideration for the main contract was $1,166,000.00.
The defendant quoted to the plaintiff in their letter3 dated 2nd January 2008 to provide some works within the project. The parties signed a sub-contract agreement4 dated 5th March 2008 (“the sub-contract”), which the plaintiff confirmed on 6th March 2008. In so confirming, the plaintiff made a hand-written note on page 3 of the sub-contract which read “letter of award to be issued. Works to comply in all respects to HDB contract specifications.” No letter of award was issued but this does not matter for this case. The terms of the main contract were not incorporated, except for the specifications, so far as relevant. There are none.
The sub-contract provided that the defendant would supply and install two units of weighbridges, supply a new office cabin and a new security post. The sub-contract also required the supply of a variety of peripheral items. The value of the sub-contract works (“the works”) was $79,500.00.
The sub-contract provided that the defendant would deliver the weighbridges, the new office cabin and security post within ten weeks from the plaintiff’s “firm order” and that the defendant would have an “installation time includ(ing) testing, calibration, and commissioning” of approximately 10 to 12 days.
The plaintiff’s case is that the defendant had an extended completion time for the works to 31st July 20085. The defendant agrees6. (Quite parenthetically, I should mention that there was some argument over when the contracted dates for delivery and completion of the works were, owing to a factual dispute over when the plaintiff paid a “30% deposit on confirmation of the order”.7 The plaintiff’s position was that there was a firm order from the date when the plaintiff confirmed the sub-contract on 6th March 2008, so that delivery of items was due by 15th May 2008 and the works were to be completed by 27th May 2008. The defendant’s position was that time ran from 3rd April 2008 (which was when they said the plaintiff paid the deposit, a date which was the source of yet more dispute), so that their delivery of items fell on 12th June 2008 and the works were to be completed by 24th June 2008.) It is quite clear that the agreed extended completion date of 31st July 2008 rendered the dispute over the time-lines irrelevant.
The HDB’s consultant for the project was Surbana International Consultants Pte Ltd (“Surbana”). Surbana eventually issued their certificate of substantial completion on 26th November 20088, which stated that the date of substantial completion of the project was 16th October 2008. An interim final account9 for the project, signed by Surbana, did reflect a sum of $52,000.00 by way of “actual liquidated damages”.
It is common ground that the security post and the cabin office were delivered on 19th June 2008. As for the two weighbridges, the defendant’s position is that these were delivered on 18th June 2008 because that was the date of their invoice. The plaintiff says that the weighbridges in fact comprised a number of constituents and that the defendant only completed delivery in October 2008.
The pleadings: In this action, the plaintiff’s claim is that the defendant failed to complete the works by 31st July 2008 and or that the works were deficient in a number of ways10, owing to which they suffered damage. The plaintiff’s particulars of defects were these:
The plaintiff thus claims:
The Defence and Counter-claim (Amendment No. 1) states that the delays (if any) were in fact caused by the plaintiff. The following particulars of delays were set out:
In respect of the alleged deficiencies (
The defendant counter-claims for the payment of the sum of $17,013.00, which is 20% of the value of the sub-contract, including GST, these being for amounts they invoiced the plaintiff on 11th July 2008 and 25th July 2008.19 I should mention that the plaintiff had paid 30% of the value of the sub-contract as a deposit and 50% of the value of the sub-contract, which was contractually due upon delivery of the items, pursuant to the defendant’s invoice dated 18th June 2008 (referred to at
The plaintiff’s responses to the defence and counter-claim were these:
It would be useful to outline the scope of the parties’ disagreement. In respect of the issues of delay, these concerned really the two weighbridges and one cabin office. The plaintiff saw the weighbridges and the cabin office as a single composite item, so that lateness the completion of either meant that there was lateness overall. The defendant’s position is that the delays were caused by the plaintiff’s failure to provide timely instructions or changing their instructions. In respect of the alleged defects, these mainly concerned the security office and the cabling of the cabin office.
Purpose of the weighbridges:The project involved a stockpiling site. Loaded trucks moving in and out of the site were expected to be weighed on either of the two weighbridges so that, nett of their unladen weight, the weight of their load would be known. Hence, as might be envisaged, each weighbridge comprised a steel platform mounted over load cells for weights to be taken, and both were linked to one computer system with a printer (to be housed in the cabin office) and a display monitor so that the weights read by the weighbridges would be known, recorded and receipted.
The evidence and my findings: Defects: For the defects, the plaintiff says that they incurred $7000 to put right the defects, as follows24:
To continue reading
Request your trial