UES Holdings Pte Ltd v Grouteam Pte Ltd
Jurisdiction | Singapore |
Judge | Quentin Loh J |
Judgment Date | 26 October 2015 |
Neutral Citation | [2015] SGHC 275 |
Year | 2015 |
Date | 26 October 2015 |
Published date | 04 November 2016 |
Hearing Date | 21 August 2015 |
Plaintiff Counsel | Ian de Vaz and Melanie Chew (WongPartnership LLP) |
Citation | [2015] SGHC 275 |
Defendant Counsel | Radika Mariapan (IRB Law LLP) |
Court | High Court (Singapore) |
Docket Number | Originating Summons No 649 of 2015 |
By this originating summons, UES Holdings Pte Ltd (“the Plaintiff”) seeks to set aside an adjudication determination under the Building and Construction Industry Security of Payment Act (Cap 30B, 2006 Rev Ed) (“the Act”).
The Plaintiff was engaged as a main contractor by Changi Airport Group (Singapore) Pte Ltd (“CAG”) for a project entitled “Relocation of Pumphouse and Substation at Singapore Changi Airport”1 (“the Main Contract”). The Plaintiff then entered into a domestic sub-contract (“the Sub-contract”) with Grouteam Pte Ltd (“the Defendant”) to carry out,
On 20 April 2015, the Defendant served Payment Claim No. 18 (“the Payment Claim”) on the Plaintiff.3 Not having received a payment response from the Plaintiff, on 20 May 2015, the Defendant proceeded to serve a notice of intention to apply for adjudication (“the Notice of Intention”) and lodged an adjudication application (“the Adjudication Application”) with the Singapore Mediation Centre (“SMC”).4 Upon receipt of the Notice of Intention, the Plaintiff then issued Payment Response No. 18 (“the Payment Response”) on 20 May 2015.5 The SMC served a copy of the Adjudication Application on the Plaintiff on 21 May 2015.6 An adjudicator was appointed and on 19 June 2015, the adjudicator rendered his determination (“the Adjudication Determination”) ordering,
The Plaintiff is applying to set aside the Adjudication Determination on three alternative grounds:8
It is necessary to make some comments on the Sub-contract. It is exhibited in the 1st Affidavit of Chua Kok Liang, filed on 9 July 2015 (“1st CKL Affidavit”), and it runs for some 507 pages, from pp 85–592. The phrase “cobbled together” is an apt description, so are the words “enigmatic” and “confusing”. There were quite a number of documents that were bundled together; some parts of which sat ill with another and the language used was at times wanting and difficult to comprehend. This is unfortunately not all that unusual in some of the construction contracts that end up in arbitration or the courts.
The affidavits give little or no information on the negotiations leading up to the Sub-contract or how some important documents came to be included in the Sub-contract. The context is thus largely missing. The more relevant parts of the Sub-contract, dated 30 August 2013, are as follows:
I should mention at this juncture that Section 6 of the First Schedule to the Sub-contract Agreement contains a ‘priority’ or ‘precedence’ clause which provides for inconsistencies between the attachments which form the Sub-contract:14
Notwithstanding anything stated in this Sub-Contract, in the event and to the extent of any inconsistency between two or more attachments which form part of this Sub-Contract, those attachments will be interpreted in the following order of priority:
[emphasis in original]
Section 6 of the First Schedule will play a crucial role as some parts of the Sub-contract appear,
The Plaintiff’s First Ground of Challenge (
Preliminaries E appears at Sect1.1/16 of the Preliminaries under the heading “INTERIM PAYMENTS”. Item D appears under that heading as well and precedes Preliminaries E; item D is headed “The Reference Schedule” and caters for valuation of progress claims by reference to items within a “Reference Schedule” based on the percentage completion of each item therein. It reads:
For the purposes of clause 32 of the [PSSCOC] , the Contractor shall allow in his price for progress payments to be valued by reference to the items set out in the Reference Schedule for the Valuation of Progress Payments (“the Reference Schedule”). The valuation for each progress payment shall be based on the percentage completed of each of the items set out in the Reference Schedule in a reference month and multiplying the said percentage by the value of the item.[emphasis added]
Within 7 days from the end of each calendar month (hereinafter “the reference month”),the Contractor shall deliver to the Employer (with copies to the Superintending Officer),a payment claim in a form which shows a breakdown of the amount claimed by reference to the items as set out in the Reference Schedule. In addition to the requirements set out in clause 32.1(1) of the [PSSCOC], the payment claim shall also state:(1) Amounts paid previously under the Contract; and
(2) The balance arising out of the Contract in respect of the reference month which is due to the Contractor or the Employer, as the case may be.
[emphasis added]
In contrast, the Defendant disagrees and contends instead that clause E of the SOCN (“Negotiations E”) is the applicable provision that governs the submission of payment claims.16 As noted above, the SOCN is set out in Annex 1 of the Sub-contract. Clause D of the SOCN sets out a Payment Schedule which breaks down the payment of the contract price into stages by percentage. Under this Schedule, 5% is payable upon receiving the Performance Bond, 5% upon submission of shop drawings, 75% “[u]pon monthly...
To continue reading
Request your trial-
Rong Shun Engineering & Construction Pte Ltd v CP Ong Construction Pte Ltd
...supported by any Singapore authority. Indeed, as the respondent points out, the proposition is positively contradicted by Loh J’s approach in UES Holdings Pte Ltd v Grouteam Pte Ltd [2016] 1 SLR 312 (“UES”).39 The respondent in UES alleged that a payment claim had not been served “at such t......
-
UES Holdings Pte Ltd v KH Foges Pte Ltd
...(S) Pte Ltd v Balanced Engineering & Construction Pte Ltd [2014] SGHC 142 at [43]-[49] and UES Holdings Pte Ltd v Grouteam Pte Ltd [2016] 1 SLR 312 (“Grouteam (HC)”) at [51]. In relation to a construction contract, the deadline for filing an adjudication application hinges on the deadline f......
-
Trustee of the estate of Tay Choon Huat, deceased v Soon Kiat Construction & Maintenance Pte Ltd
...(S) Pte Ltd v Balanced Engineering & Construction Pte Ltd [2014] SGHC 142 at [43]–[49], UES Holdings Pte Ltd v Grouteam Pte Ltd [2016] 1 SLR 312 at [51], UES Holdings Pte Ltd v KH Foges Pte Ltd [2018] 3 SLR 648 (“Foges”) at [83]. “Day” in the SIA Article 9 of the SIA Conditions defines “pay......
-
Linkforce Pte Ltd v Kajima Overseas Asia Pte Ltd
...This also assured me of the propriety of examining the merits of the Adjudicator’s decision: see UES Holdings Pte Ltd v Grouteam Pte Ltd [2016] 1 SLR 312 (“Grouteam (HC)”) at [40]. A fortiori when there could be a breach of natural justice caused by the wrongful exclusion of Kajima’s paymen......
-
Building and Construction Law
...the importance of strict compliance with the timelines prescribed for the payment process. In UES Holdings Pte Ltd v Grouteam Pte Ltd[2016] 1 SLR 312 (‘UES Holdings’), the payment claim related to a subcontract for certain civil and architectural works. A payment claim was served by the sub......