Sim & Associates (sued as a firm) v Tan Alfred

JudgeKarthigesu JA
Judgment Date25 January 1994
Neutral Citation[1994] SGCA 12
Citation[1994] SGCA 12
Defendant CounselCheng Tim Pin (Yap & Yap)
Published date19 September 2003
Plaintiff CounselWoo Bih Li (Bih Li & Lee)
Date25 July 1994
Docket NumberCivil Appeal No 118 of 1993
CourtCourt of Appeal (Singapore)
Subject MatterDefective works in building,Duties and liabilities,Whether breach of contract,Building contract,Whether architect breached duty of supervision,Contract,Architects,Building and Construction Law,Turnkey project for building construction,Breach,Singapore Institute of Architects Form (1982 Ed),Professions,Architects, engineers and surveyors,Whether architects failed to effect proper supervision,Scope of architect's duty of supervision

Cur Adv Vult

This is an appeal against the decision of Justice Warren Khoo in Suit No 9660 of 1985 in which the learned judge awarded the respondent, inter alia, a sum of $193,524 in damages against the appellants for breach of their duties as architects in connection with the construction of a two-storey bungalow and further dismissed the appellants` counterclaim for the balance of their professional fees and disbursements.

In November 1981, the respondent bought a piece of land at No 16 Second Avenue with a view to building a two-storey bungalow thereon.
He engaged the appellants, a firm of architects, planners and engineers to provide various services including architectural services and the services of a quantity surveyor in connection with the construction of the bungalow. There was no formal contract between the appellants and the respondent.

The appellants subsequently called for tenders for the project and on 9 December 1982, on the respondent`s behalf, awarded the contract to Hok Mee Construction (Pte) Ltd (`the main contractor`).
The main contractor had originally submitted a tender for $1,634,853.35. Subsequently however, various items, including the installation of the external marble cladding for the bungalow, were omitted. These omissions resulted in a reduction of the tender sum to $1,228,072.35. The main contractor confirmed these omissions on 10 December 1982 and the formal building contract between the respondent, as `employer`, and the main contractor was signed on 17 January 1983.

The building contract was on the Singapore Institute of architects form of contract (1982 Ed).
Two of the appellants` representatives were appointed `architect` and `quantity surveyor` under the building contract. The commencement and completion dates were stated to be 17 December 1982 and 16 June 1983 respectively. The building contract also provided for a maintenance period of six months from the date of issuance of the completion certificate by the architect. The appendix to the building contract, read with cl 31(1), provided for the architect to issue monthly interim certificates for payment to the main contractor. The respondent, as the `employer` under the building contract, was required to honour these interim certificates for payment within 14 days from the date of certification.

The original specification provided for marble to be affixed to the external walls of the bungalow (the external marble cladding).
The method specified in the original tender documents for securing the marble slabs to the external walls was the use of metal anchorages made of a suitable non-ferrous metal, eg stainless steel or some other approved metal (the mechanical method). However, at the time of the award of the tender on 9 December 1982, the external marble cladding was omitted from the contract because of its high cost, resulting in a reduction of the contract sum. Subsequently, the external marble cladding was reintroduced using a less costly method. This alternative method involved affixing the marble slabs to the external walls using a sand and cement plaster backing with brass wire clamps (the adhesion method). The cheapest quotation for the adhesion method was submitted by Cheah Choon Yin Construction Co Pte Ltd (`Cheah Choon Yin`) on 24 May 1983. This quotation was accepted on 27 June 1983 by the appellants for and on behalf of the respondent. Under the agreement, Cheah Choon Yin was required to commence the external marble works on 29 June 1983 and complete the works within six weeks thereof.

As it often happens in building projects, there were delays to the construction of the bungalow.
No evidence was however led at the trial as to the cause of these delays. Various efforts were made by the appellants as the architect under the building contract to get the main contractor to ensure a prompt completion of the works but without success. The respondent was eager to move into the bungalow as the lease for his rented premises was expiring. Although a temporary occupation licence had not yet been given, the respondent made arrangements with the main contractor to occupy the bungalow and moved in on 28 November 1983. At the time the respondent moved into the bungalow, there were various defective works awaiting rectification and the external marble cladding was not fully completed.

By a letter dated 2 December 1983 from the main contractor to the respondent, various matters relating to the construction of the bungalow were agreed upon between themselves.
Owing to its importance, this letter is reproduced in full:

2 December 1983

Mr Alfred Tan Chor How

No 16 Second Avenue

Singapore 1026

Dear Mr Tan,

2-Storey Bungalow at No 16 Second Avenue

We refer to the recent meeting between yourself and our Mr Kek and are pleased to confirm the following agreement reached between us for the handing over of the building to you for occupation.

(1) The date for the practical completion of the project under the conditions of the building contract has been extended to 30 November 1983, and on taking possession of the premises by you, the works under the building contract has reached a stage of practical completion.

(2) No liquidated damages will be imposed by you. Likewise we agree not to claim for additional costs and expenses incurred due to the extended construction time.

(3) Turfing and planting works under the contract are to be omitted from our contracts.

(4) Due to the shortage of marble slabs supplied by you and at your request we will cease all works on the unfinish external marble wall until the arrival of the marble slabs to be supplied by you. We will remove all scaffolding and equipment from the site as requested by you.

(5) You have agreed to pay us new rates for remobilisation, delivery and re-erection of all scaffold and other preliminary works necessary for the completion of the external marble wall when your material arrives on site.

(6) As per your telex of 24 November 1983, we confirm our agreement that you may engage Allied Initial Services to carry out the clearing of the rubbish and cleaning of the whole site and the building, including polishing of all the floors and wall surfaces for the sum of $2, 500.The said cost shall be for our account on the understanding that we will be relieved of all responsibilities concerning the cleaning up on completion of works as required under the conditions of the building contract.

Yours faithfully

Hok Mee Construction Pte Ltd

(signed)

Kek Kim Hok

Managing Director

cc: Sim & Associates - Attention: Mr Sim Hong Boon



The main contractor left the site on 17 January 1984, subject to the agreement to return later to complete the external marble cladding when the respondent supplied the marble slabs and after new rates for remobilisation were agreed to pursuant to the above agreement.


At the trial, the respondent did not dispute the correctness of the above agreement.
In cross-examination, the respondent indicated that the letter was a correct record of what was agreed to and that he did not eventually come to any agreement with the main contractor as to the new rates to be charged for remobilising the marble works.

On 18 January 1984, the appellants in their capacity as the architect under the building contract wrote to the respondent proposing to issue the 11th interim certificate to the main contractor.
The interim certificate set out the respective amounts proposed for payment to the main contractor and the nominated sub-contractors. No objection was received from the respondent and on 25 January 1984, the appellants issued the 11th interim certificate for progress payment in the sum of $183,866.84 to be paid by the respondent to the main contractor. Under the contract, this payment from the respondent was due in 14 days, ie on or around 8 February 1984. The respondent failed to make this payment and persistently refused to make this payment when called upon to do so. As a result of this failure to pay the 11th interim certificate sum, the main contractor and the nominated sub-contractors refused to rectify the defective works.

Various efforts were made by the appellants to end this impasse resulting in a meeting on 30 May 1984 between the respondent, the main contractor and the appellants.
The unsigned minutes of the meeting recorded the following agreement between the respondent and the main contractor:

Notes of meeting held at Shaw House on 30 May 1984 at 6pm

Attendance:

Mr Alfred Tan (the respondent)

Mr Kek (the main contractor`s representative)

Mr Sim Hong Boon (the appellants` representative)

(1) It was agreed that Mr Alfred Tan will make payment to Mr Kek of Hok Mee Construction Co Pte Ltd the sum of $183,866.84 under architect`s certificate no 275/11 by Friday, 1 June 1984.

(2) Mr Kek has agreed that he and his sub-contractors will commence the rectification works by 15 June 1984 after receiving payment from Mr Tan and have the works completed by 27 July 1984. The list of the defective works prepared by Mr Alfred Tan was given to Mr Kek at the meeting.

(3) Mr Tan agreed that he will issue Mr Kek a banker`s guarantee for payment of the balance of approximately $360,000 to ensure payment to Mr Kek after Mr Kek has completed all the rectification works.

(4) It was agreed that the parties, Mr Tan and Mr Kek and, if necessary, the architect will be present and take over/accept defective works completed by Mr Kek and the sub-contractors progressively.

(5) Should Mr Kek fail to complete all the defective works by the date mentioned above under item 2, it was agreed that he will pay Mr Tan the rate of $1,500 per day.

(6) The defect liability under the contract has expired. It was agreed that Mr Kek will extend this defect liability for a further two months from 27 July 1984 and the retention sum of approximately $9,252.97 will be...

To continue reading

Request your trial
11 cases
  • Lim Guan Cheng v JSD Construction Pte Ltd and Another
    • Singapore
    • High Court (Singapore)
    • 26 November 2003
    ...plc v Key Surveyors Nationwide Ltd & Ors [1996] 3 All ER 184. 41 The defendants relied on Sim & Associates (sued as a firm) v Tan Alfred [1994] 3 SLR 169 and Vaynar Suppiah & Sons v KMA Abdul Rahim & Anor [1974] 2 MLJ 183. In both cases, the reports were sought to be admitted to prove the e......
  • Jet Holding Ltd and Others v Cooper Cameron (Singapore) Pte Ltd and Another
    • Singapore
    • High Court (Singapore)
    • 22 August 2005
    ...v Eastern Garment Manufacturing Sdn Bhd [1989] 3 MLJ 360 (refd) Regina v Shepherd [1993] AC 380 (refd) Sim & Associates v Tan Alfred [1994] 1 SLR (R) 146; [1994] 3 SLR 169 (folld) Trollope & Colls Ltd v North West Metropolitan Regional Hospital Board [1973] 1 WLR 601; [1973] 2 All ER 260 (f......
  • Surender Singh s/o Jagdish Singh And Another (administrators of the estate of Narindar Kaur d/o Sarwan Singh) v Li Man Kay and Others
    • Singapore
    • High Court (Singapore)
    • 22 July 2009
    ...conditions in s 32 of the Evidence Act and to warrant the court’s admission of Nurse Lourdes’ AEIC (see Sim & Associates v Tan Alfred [1994] 3 SLR 169 and Central Bank of India v Hemant Govindprasad Bansal [2002] 3 SLR 143 I should point out however that not all the documents the plaintiffs......
  • 15962 Goj 22 478 18Js
    • Malaysia
    • Session Court (Malaysia)
    • 6 January 2023
    ...it will not constitute negligence. [See Hunter v Hanley [1955] SLT 21; [2955] SC 200; Sim & Associates (sue as a firm) v Alfred Tan [1994] 3 SLR 169; and PB Malaysia Sdn Bhd v Samudra (M) Sdn Bhd [2009] 7 MLJ 681] I also rely on the authority of Shearn Delamore & Co v Sadacharami a/l Govind......
  • Request a trial to view additional results
1 firm's commentaries
  • Architects' Duties
    • Singapore
    • Mondaq Singapore
    • 9 December 2003
    ...or subsequent contractual relationship between the person suffering the loss and the representor. 5 [1826]2 C&P 378 6 38 BLR 25 7 [1994]3 SLR 169 8 [1911] 75 J.P. 197 9 1974] A.C. 727 (H.L.) 10 SIA Conditions of Appointments, s. 2.2.5 11 [1990] 3 WLR 414 (H.L.) 12 [1996] 1 SLR 113 13 [1......
4 books & journal articles
  • Litigation
    • United Kingdom
    • Construction Law. Volume III - Third Edition
    • 13 April 2020
    ...the court or the opposing party to do so), that written evidence may be excluded as hearsay evidence: see Sim & Associates v Tan Alfred [1994] 3 SLR 169 at [63]–[65]. 595 However, there is no legal requirement that evidence be adduced in this way. It may be possible for experts to give evid......
  • Contract administration
    • United Kingdom
    • Construction Law. Volume I - Third Edition
    • 13 April 2020
    ...QC, where it was held that there was no real distinction between “supervision” and “inspection”. See also Sim & Associates v Tan Alfred [1994] 3 SLr 169 at [39]. 169 See SAIT Inc v Grieve [1998] SaSC 6705 at page 18, per Williams J. ContraCt aDMiniStration the applicable contract, that the ......
  • Building and Construction Law
    • Singapore
    • Singapore Academy of Law Annual Review No. 2021, December 2021
    • 1 December 2021
    ...2207 at [116]. 75 [2015] UKSC 67. 76 [2021] 1 SLR 661. 77 [2020] EWHC 2373 (Comm) at [55(ii)] and [59(iii)]. 78 See para 7.5 above. 79 [1994] 1 SLR(R) 146. 80 Sim & Associates v Tan Alfred [1994] 1 SLR(R) 146 at [40] and [43]. 81 [2019] 4 SLR 628. 82 [1966] AC 406. The judgment noted that t......
  • BUILDING CONSULTANTS’ EXPOSURE AND LIABILITY UNDER SINGAPORE LAW — FROM OCEAN FRONT TO HONG HUAT
    • Singapore
    • Singapore Academy of Law Journal No. 2001, December 2001
    • 1 December 2001
    ...1211. 61 [2000] 1 SLR 166, 62 Ibid, at page 181. 63 Cotton v Wallis [1955] 1 WLR 1168. 64 Sim & Associates (sued as a firm) v Tan Alfred [1994] 3 SLR 169. 65 Setron, supra note 61 at page 181, paragraph 36. 66 (1971) 18 BLR 149. 67 Ibid, at page 64. 68 Ibid, at page 162. 69 Eastern Lagoon, ......

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT