Shanghai Electric Group Co Ltd v PT Merak Energi Indonesia and another
Judge | Lee Seiu Kin J |
Judgment Date | 06 January 2010 |
Neutral Citation | [2010] SGHC 2 |
Citation | [2010] SGHC 2 |
Docket Number | Originating Summons No 273 of 2009 |
Published date | 14 January 2010 |
Hearing Date | 31 March 2009,09 March 2009,26 May 2009,13 August 2009 |
Plaintiff Counsel | Christopher Chuah, Cindy Lim and Joanna He (WongPartnership LLP) |
Date | 06 January 2010 |
Defendant Counsel | Hri Kumar Nair SC, Tham Feei Sy and Kristine Ang Li Shan (Drew & Napier LLC) |
Court | High Court (Singapore) |
Subject Matter | Conflict of Laws |
This is an application by the first defendant (“PT Merak”) to set aside an
This case involves an interesting point of law that has not arisen in previous decisions of the courts pertaining to on-demand bonds: whether Singapore law is the applicable law in an application to restrain a call on an on-demand bond which provides that English law is the governing law.
Background Shanghai Electric is a company incorporated in China and is in the business of designing, manufacturing, sale and supply of,
By a contract dated 10 August 2007 (“the Contract”), Shanghai Electric was engaged by PT Merak for the design, engineering, manufacturing, procurement, construction, start-up, testing, commissioning and completion of a 2 x 60 MW coal fired electricity and steam generating power plant (“the Power Plant”) located in West Java, Indonesia, for the sum of US$108m (“the Contract Price”). On 22 January 2008, PT Merak and Shanghai Electric (referred to collectively as “the Parties”) entered into an addendum to the Contract (“the Addendum”) which amended several clauses of the Contract.
The Contract provided for PT Merak to pay Shanghai Electric an advance payment of 10% of the Contract Price (“the Advance Payment”) amounting to US$10.8m. The Advance Payment was a condition precedent for the issuance of the notice to proceed. In turn, s 7.7(a) of the Contract required Shanghai Electric to procure the Bond for the sum of US$10.8m in favour of PT Merak. This was performed on 20 November 2007 with the issue of the Bond for the sum of US$10.8m by the Singapore branch of the Bank. On 1 April 2008, PT Merak effected payment of the sum of US$10.8m to Shanghai Electric. With this, Shanghai Electric commenced work under the Contract.
Under the Bond, the Bank undertook to pay to PT Merak the sum of up to US$10.8m (which is the amount of the Advance Payment) upon receipt of:
the Owners’ first written demand stating
On 2 February 2009, PT Merak issued to Shanghai Electric a “Notice of Contractor Default” pursuant to s 19.2.2(b) of the Contract. PT Merak alleged that since 10 August 2007 (the date of the Contract), “very little progress was made on the construction of the Power Plant. Apart from the temporary site office, temporary warehouse, temporary site roads, test pilings, excavation and some lean concrete (levelling concrete) for the foundations of the Boiler and Turbine Buildings, there is nothing else on site. Significantly, [Shanghai Electric] failed to complete the work in respect of Payment Milestones 1 to 5. Further, [PT Merak] also encountered numerous difficulties with [Shanghai Electric]. Although [PT Merak] tried to resolve these difficulties through meetings and correspondence, this proved futile”.
On 11 February 2009, Shanghai Electric sent a letter (“the first Letter”) to PT Merak stating that:
This was followed by a second letter from Shanghai Electric dated 13 February 2009 (“the second Letter”) setting out its response to various items of alleged “Contractor Defaults” contained in the notice of contractor default. On 16 February 2009, PT Merak replied – acknowledging receipt of the “Contractor Remedial Plan” attached to the letter of 11 February 2009 and stating that it was “currently reviewing the Contractor Remedial Plan and will revert with [its] response in accordance with s 19.2.2(b) of the Contract”.
On 19 February 2009, PT Merak sent a second letter to Shanghai Electric, stating, amongst other things, that “until such time as [PT Merak has had] the opportunity to evaluate [Shanghai Electric’s] Contractor Remedial Plan, [Shanghai Electric’s] request for a meeting is unnecessary”. By a letter dated 27 February 2009 (“the third Letter”), Shanghai Electric furnished further details of the Contractor Remedial Plan to PT Merak.
On 6 March 2009, three events occurred: first, PT Merak delivered a notice of termination to Shanghai Electric to terminate its appointment under the Contract (“the Notice of Termination”); second, Shanghai Electric wrote to PT Merak, accepting the termination and alleging that such termination amounted to a repudiation of the Contract by PT Merak; third, after delivery of the notice of termination to Shanghai Electric, PT Merak delivered a letter of demand to the Bank calling for payment under the Bond (“the Demand”).
On 9 March 2009, Shanghai Electric filed the Injunction application on an
As alluded to at the outset of this judgment, there is an issue as to the applicable law governing the restraint on the calling of an on-demand bond. The Contract itself is governed by English law, it being an express provision in s 26.8 thereof. Section 25.1 provides for disputes to first be attempted to be resolved by good faith negotiations. Failing this, s 25.2.1 provides such dispute to be submitted to arbitration at the Singapore International Arbitration Centre (“SIAC”) to be conducted in accordance with the ICC Rules. It is also expressly provided in the Bond that the governing law is English law. Although the Bond is an agreement between the Bank and PT Merak, it was given pursuant to s 7.7(b) of the Contract which required Shanghai Electric to procure an advance payment security in the form annexed in exhibit N-2 of the Contract. The terms of the Bond essentially mirrored the form in exhibit N-2. The governing law clause in the Bond – which also provides that Singapore courts have non-exclusive jurisdiction over any proceedings arising out of it – states as follows:
This [Bond] shall be governed by and construed in accordance with the laws of England. We hereby irrevocably submit to the non-exclusive jurisdiction of the courts of [Singapore] for the purposes of any … proceedings arising out of this [Bond].
PT Merak submitted that, as the Contract and, especially, the Bond expressly provide that English law is the governing law, this court should apply English law in relation to the decision whether to restrain PT Merak from making a demand under the Bond. Shanghai Electric, on the other hand, submitted that notwithstanding that English law is the governing law of the Bond, this application was governed by the procedural law of the forum and therefore Singapore law would apply. This is an important point as Singapore law and English law diverge on whether fraud is the only basis upon which the court would restrain a call on an on-demand bond.
This divergence was brought about by the decision of the Court of Appeal in
To continue reading
Request your trial- Kejuruteraan Bintai Kindenko Sdn Bhd v Nam Fatt Construction Sdn Bhd
-
Goj 22 851 2018 Signed 1
...of HRH Sheikh Sultan bin Khadifa bin Zayed AlNahyan [2000] 1 SLR (R) 117; and Shanghai Electric Group Co Ltd v PT Merak Energi Indonesia [2010] 2 SLR 329)…” [Emphasis Based on the ratio of Sumatec Engineering (supra), with all due respect to the Plaintiff’s counsel, I do not find that any s......
-
Macquarie Bank Ltd v Graceland Industry Pte Ltd
...As to those submissions, Graceland relied, in particular, on Shanghai Electric Group Co Ltd v PT Merak Energi Indonesia and another [2010] 2 SLR 329 at [20]; Halsbury’s Laws of Singapore vol 6(2) (LexisNexis, 2017) at para 75.256; Dicey, Morris & Collins, The Conflict of Laws (Sweet & Maxwe......
-
Labroy Offshore Ltd v Master Marine AS and others
...Pte Ltd v Tridex Technologies Pte Ltd [2011] 1 SLR 449 (“Astrata”); Shanghai Electric Group Co Ltd v PT Merak Energi Indonesia [2010] 2 SLR 329 at [47]; and, finally, Eltraco International Pte Ltd v CGH Development Pte Ltd [2000] 3 SLR(R) 198 at [32]. Third, it denied Labroy’s allegation of......
-
Security for performance
...the procedural law of the jurisdiction in which the injunction is sought: see Shanghai Electric Group Co Ltd v PT Merak Energi Indonesia [2010] 2 SLr 329. 236 Power Curber International Ltd v National Bank of Kuwait SAK [1981] 3 all Er 607 at 614, per Griiths LJ; United City Merchants (Inve......
-
Case Note
... DEMAND GUARANTEES IN INTERNATIONAL COMMERCE Conflicts and Confusion Shanghai Electric Group Co Ltd v PT Merak Energi Indonesia [2010] 2 SLR 329 This note considers the implications of the Singapore High Court‘s decision in Shanghai Electric Group Co Ltd v PT Merak Energi Indonesi......
-
Building and Construction Law
...traditional position in England. In the second decision, the High Court in Shanghai Electric Group Co Ltd v PT Merak Energi Indonesia [2010] 2 SLR 329 (‘Shanghai Electric Group Co Ltd’) had to consider, inter alia, whether the nature of the relief granted to restrain a call on the bond is a......
-
Conflict of Laws
...The line between matters of substance and procedure are not always clear. Shanghai Electric Group Co Ltd v PT Merak Energi Indonesia [2010] 2 SLR 329 explored this distinction vis-�-vis an injunction restraining the defendant from receiving money pursuant to a call on an advance payment o......