Samsung Corp v Chinese Chamber Realty Pte Ltd and Others
Jurisdiction | Singapore |
Judge | Chao Hick Tin JA |
Judgment Date | 29 December 2003 |
Neutral Citation | [2003] SGCA 50 |
Date | 29 December 2003 |
Subject Matter | Whether application could be made pending application for stay of proceedings,Whether court could invoke inherent powers to vary O 14 r 1,Order 92 r 4 Rules of Court (Cap 322, R 5, 1997 Rev Ed),Summary judgment,Application for summary judgment under new O 14 r 1,Order 14 r 1 Rules of Court (Cap 322, R 5, 1997 Rev Ed),Defence not filed,Civil Procedure,Inherent powers |
Docket Number | Civil Appeal No 81 of 2003 |
Published date | 10 January 2004 |
Defendant Counsel | Latiff Ibrahim, Yeo Khung Chye (Harry Elias Partnership) |
Court | Court of Appeal (Singapore) |
Plaintiff Counsel | C R Rajah SC (instructed), Koh Kok Wah, Gerald Ng and Daniel Chia (Wong and Leow LLC) |
Chao Hick Tin JA
1 This appeal raises the question as to whether it is proper, in the light of the current O 14 r 1, for the court to compel a defendant to file his defence to an action, with the aim of enabling the plaintiff to file an O 14 application for summary judgment, when the defendant has already filed an application for a stay of the proceeding.
2 The present O 14 r 1 reads:-
“Where a statement of claim has been served on a defendant and that defendant has served a defence to the statement of claim, the plaintiff may, on the ground that that defendant has no defence to a claim included in the writ, or to a particular part of such a claim, or has no defence to such a claim or part except as to the amount of any damages claimed, apply to the Court for judgment against that defendant.”
3 The words which we have italicized above, namely, “served a defence to the statement of claim” have replaced the previous words “entered an appearance in the action.”. Under the previous rule, even though the defendant had already applied for a stay of the proceeding, there was nothing to stop a plaintiff from applying for summary judgment. This was because it was then not a requirement that the defence must be filed before the O 14 application could be made. It was also then the practice, in the interest of avoiding delay, that both the stay and the O 14 applications would be heard at the same time. While the tests that would be applied in determining the two applications were not the same, there would usually be considerable overlap in the arguments presented. Thus, in a sense, there was some expedience in this approach. An example where such an approach was taken is the case of Aoki Corp v Lippoland (S) Pte Ltd
4 In Yeoh Poh San & anor v Won Siok Wan
5 Relying on the principles enunciated by this Court in The Jarguh Sawit
“The point is that while a defendant is seeking to stay the proceeding, whether by way of original application or an appeal, the defendant should not be required to meet the plaintiff’s claim on the merits. A defendant is entitled to focus his attention on the appeal for a stay and not be distracted by running two contradictory courses of action at the same time.”
6 At this juncture it would be appropriate for us to look at the case of The Jarguh Sawit which Woo JC relied upon. There, the defendants unsuccessfully applied to set aside the writ under O 12 r 7 of the Rules of Court on the ground that the court had no jurisdiction in the admiralty action instituted by the plaintiffs. In their defence and counterclaim filed, the defendants reiterated the jurisdictional point. The plaintiffs applied for summary judgment and also to strike out the jurisdiction point pleaded in the defence on the ground that the latter issue had already been determined. The Assistant Registrar struck out the jurisdictional issue pleaded in the defence and this decision was upheld by the High Court. As regards the action proper, the defendants were given conditional leave to defend. The defendants were dissatisfied and appealed to the Court of Appeal. This Court upheld the decision below that the defendants were not entitled to raise the jurisdictional issue again, the point having been previously decided. It was res judicata. What were considered germane by Woo JC were the views expressed by this Court when dealing with the jurisdictional point:-
“30. Firstly, whether or not a court has jurisdiction is, of necessity, a question logically prior to the substantive dispute of the parties. Unless and until a court is properly seized, it cannot adjudicate on the matter …
34. The Rules of Court also contemplate that the matter of jurisdiction should be determined once and for all at the interlocutory stage. The Rules clearly suggest that jurisdiction is finally determined at the stage where an application is made under O 12 r 7 ….
35. A party to an action brought in Singapore may dispute jurisdiction after having first entered an appearance by an application made by summons under O 12 r 7. This does not amount to a submission to jurisdiction: O 12 r 7(5). Order 12 r 7(2) then prescribes that a defendant may dispute jurisdiction by making an interlocutory application by a summons in chambers. …”
7 It seems to us that as a matter of logic, it makes absolute sense that when the question of stay is put in issue that should first be determined before any further step is taken by either party in the action. In the context of an arbitration clause, it is all the more so as under s 6(1) of the Arbitration Act it is expressly provided that the party who wants a stay of the court proceeding should apply “after appearance and before delivering any pleading or taking any other step in the proceeding.” Once the stay question is finally determined, then everything else will follow from that.
The facts
8 We now set out in brief the facts of the present case. The three respondents, the plaintiffs in the action, were the developers of a 30-storey office building right in the heart of town. The appellants, Samsung, were the main contractors of the project. There were apparently delays in the completion of the project as a result of which the Architect of the project (“the Architect”) issued a delay certificate in favour of the respondents. The respondents sought payment under the certificate, relying on the temporary finality provisions in clause 31(11) of the Singapore Institute of Architects conditions of contract (“SIA contract”). Because of the appellants’ refusal to honour the certificate, the respondents instituted the present action to compel payment. The appellants entered appearance and applied for a stay on the ground that there was an arbitration clause in the SIA contract.
9 Due to the requirement in the current O 14 r 1, the respondents could not apply for summary judgment because no defence had yet been filed. At the hearing of the stay application before the Assistant Registrar, the appellants orally applied for an extension of time to file their defence until after the stay application had been finally decided (including any appeals therefrom). At the same time, the respondents also applied orally for leave to file the O 14 application without waiting for the defence to be filed by the appellants in order to ensure that both the stay application as well as the O 14 application could be heard together, as was the practice under the previous rule.
10 Invoking the inherent powers of the court spelt out in O 92 r 4, the Assistant Registrar granted leave to the respondents to file their O 14 application without the defence having been filed by the appellants. To safeguard the position of the appellants, she also ordered that whatever affidavits filed by the appellants to resist the O 14 application would not be viewed as steps taken in the proceeding. She further granted the appellants’ application that they need not file the defence until the stay application had been finally disposed of. She lastly ordered that both the stay application and the O 14 application should be heard together. Pursuant to...
To continue reading
Request your trial-
Australian Timber Products Pte Ltd v Koh Brothers Building & Civil Engineering Contractor (Pte) Ltd
...with the stay application on 18 February 2004. The defendant relied on the decision in Samsung Corp v Chinese Chamber Realty Pte Ltd [2004] 1 SLR 382 (“Samsung”) for the proposition that once a stay application has been served, and until it has been finally disposed of, it is not proper for......
-
Q & M Enterprises Sdn Bhd v Poh Kiat
...has then to file its Defence. Indeed, in the Singapore Court of Appeal decision of Samsung Corp v Chinese Chamber Realty Pte Ltd [2004] 1 SLR 382 (“the Samsung Corp case”), it was emphatically confirmed that while a stay application is pending, no application under O 14 should be made. This......
-
Go Go Delicacy Pte Ltd v Carona Holdings Pte Ltd and Others
...Roussel-Uclaf v G D Searle & Co Ltd and G D Searle & Co [1978] 1 Lloyd's Rep 225 (refd) Samsung Corp v Chinese Chamber Realty Pte Ltd [2004] 1 SLR (R) 382; [2004] 1 SLR 382 (folld) Sanwell Corp v Trans Resources Corp Sdn Bhd [2002] 2 MLJ 625 (refd) Skopos Design Group Ltd v Homelife Nursing......
-
Go Go Delicacy Pte Ltd v Carona Holdings Pte Ltd and Others
...10, 2002 Rev Ed) (“the Act”) - directly contradicted the Court of Appeal's decision in Samsung Corp v Chinese Chamber Realty Pte Ltd [2004] 1 SLR (R) 382 (“Samsung”), they should have been more proactive and explored other options: at [22] and [36]. (4) The options available to the defendan......
-
Contract administration
...certiicates. 534 See Macdonald v Malcolm (1855) 17 D 1033 at 1037, per Lord Deas. 535 Samsung Corp v Chinese Chamber Realty Pte Ltd [2004] 1 SLR(R) 382 at 391 [25], per Chao Hick Tin JA (considering of an SIA form). 536 GTMS Construction Pte Ltd v Ser Kim Koi [2014] SGHC 232 at [57], per Ta......
-
Arbitration
...V K Rajah JA took the opportunity to reconcile the decisions of the Court of Appeal in Samsung Corp v Chinese Chamber Realty Pte Ltd[2004] 1 SLR 382 (‘Samsung Corp’) and Australian Timber Products Pte Ltd v Koh Brothers Building & Civil Engineering Contractor (Pte) Ltd[2005] 1 SLR 168 (‘Aus......
-
Arbitration
...evidence of fraud, and mere allegations are insufficient, as set out by the court in Samsung Corp v Chinese Chamber Realty Pte Ltd[2004] 1 SLR(R) 382 (Samsung Corp): H P Construction at [42], citing Samsung Corp at [25]. 4.13 The court, however, observed that in the case before it, the frau......
-
Building and Construction Law
...evidence of fraud and mere allegations are insufficient: H P Construction at [42], citing Samsung Corp v Chinese Chamber Realty Pte Ltd[2004] 1 SLR(R) 382 (Samsung Corp) at [25]. The learned Judicial Commissioner said in his judgment (H P Construction at [49]): All I have to do is decide wh......