Reliance Infrastructure Ltd v Shanghai Electric Group Co Ltd
Jurisdiction | Singapore |
Judge | Philip Jeyaretnam J |
Judgment Date | 31 January 2024 |
Neutral Citation | [2024] SGHC(I) 3 |
Court | International Commercial Court (Singapore) |
Docket Number | Originating Application No 1 of 2023 |
Hearing Date | 11 January 2024,12 January 2024 |
Citation | [2024] SGHC(I) 3 |
Year | 2024 |
Plaintiff Counsel | Vergis S Abraham SC, Asiyah binte Ahmad Arif, Ngo Wei Shing (Wu Weishen) and Liu Enning (Providence Law Asia LLC), Harish Salve KC (Blackstone Chambers) |
Defendant Counsel | Cavinder Bull SC, Foo Yuet Min, Tay Hong Zhi, Gerald, Tan Yi Fan and Tan Pei Han (Drew & Napier LLC), Nicholas Emmet Graham Leslie (Fountain Court Chambers), Ketan Gaur and Aayush Mitruka (Trilegal) |
Published date | 31 January 2024 |
When a company receives a claim on a contract of which it has no record and where its purported signatory has ceased to be its employee, does it waive any jurisdictional objection to the arbitration based on forgery of the arbitration agreement if it unsuccessfully defends the arbitration without alleging forgery? If it contests the claim on its merits with the defence that the contract was entered into by its employee without authority, but without specifically alleging that the arbitration agreement contained in the contract was itself made without authority, can it after the award is given against it raise a jurisdictional challenge that the arbitration agreement was made without authority? These were the principal questions that arose in this challenge to an arbitration award.
The claimant in this application seeks to set aside an award of an arbitral tribunal (“the Tribunal”) dated 8 December 2022 (“the Award”), which awarded damages in favour of the defendant. The Tribunal’s putative jurisdiction was based upon an alleged arbitration agreement between the Parties contained in a letter dated 26 June 2008 (“the Guarantee Letter”) within which the claimant had purportedly guaranteed the sums owed to the defendant in another related contract. The claimant had disputed the legal validity of the Guarantee Letter during the arbitration, but the Tribunal was unconvinced by that submission.
Upon challenge of that Award before this court, our task is to determine whether the claimant has waived its rights to adduce the following challenges before us – (1) that the defendant had forged the signatures of its former officer, Mr Rajesh Agrawal, on the Guarantee Letter; and (2) in the alternative, if he did sign it, that Mr Agrawal had no authority to bind the claimant to an agreement to arbitrate with the defendant.
Background Factual background of the dispute The partiesThe claimant seeking to set aside the Award is Reliance Infrastructure Limited (“Reliance Infrastructure”), a company incorporated in the Republic of India, and the defendant, Shanghai Electric Group Co Ltd (“Shanghai Electric”), was incorporated in the People’s Republic of China.1
Both Parties had been involved in a major construction project for an electricity generating power plant in Sasan Village, India (“the Sasan Project”),2 and it is from the Sasan Project that this dispute between the Parties arose.
The Supply Contract between Reliance (UK) and Shanghai ElectricOn 24 June 2008, the owner of the Sasan Project, an Indian company known as Sasan Power Limited (“Sasan Power”), entered into a contract with an English company, Reliance Infra Projects (UK) Limited (“Reliance (UK)”), that is related to Reliance Infrastructure (“the Sasan Project Contract”). Under the Sasan Project Contract, Reliance (UK) was to procure for Sasan Power the supply of equipment and services needed for the Sasan Project.3
On 26 June 2008, Reliance (UK) and Shanghai Electric then entered into a contract that provided for Shanghai Electric to supply the requisite equipment and services for the Sasan Project (“the Supply Contract”).4 It was Mr Agrawal, Reliance Infrastructure’s Additional Vice–President at the material time,5 who signed the Supply Contract on behalf of Reliance (UK).6
Although Reliance (UK)’s board of directors had provided express authorisation for Mr Agrawal to execute the Supply Contract with Shanghai Electric by passing a board resolution to that effect,7 there is no evidence in the record indicating that that board resolution had ever been furnished to Shanghai Electric as the grounds of Mr Agrawal’s authority to do so.8 The validity of the Supply Contract is not a matter of dispute between the Parties.
The final version of the Supply Contract did not contain any ‘parent company guarantee’ clause,9 owing to a request from Mr Agrawal to Shanghai Electric on 25 May 2008 seeking the deletion of such a clause.10
It is undisputed that Mr Agrawal had been involved in the negotiations over the Supply Contract, although the nature of his involvement is disputed. While Reliance Infrastructure characterises his role as a purely facilitative one of coordinating the negotiations between the Parties’ senior managements,11 Shanghai Electric argues instead that he led the negotiations between them and all entities within the wider Reliance Group (including Reliance Infrastructure) in relation to multiple power plant projects they were both involved in, inclusive of the Sasan Project.12
The events surrounding the disputed Guarantee Letter between Reliance Infrastructure and Shanghai Electric Unlike with the Supply Contract, the validity of the Guarantee Letter
On 9 February 2007, Reliance Infrastructure, under its previous name: Reliance Energy Limited,13 agreed to indemnify Shanghai Electric in relation to claims that the owner of another power plant project in Hisar, India may institute against Shanghai Electric for any matters relating to that project (“the Hisar Indemnity”).14
Paragraph 6(b) of the Hisar Indemnity contained an agreement to arbitrate disputes between the Parties,15 and it was Mr Agrawal who signed the Hisar Indemnity on behalf of Reliance Infrastructure (as Reliance Energy Limited).16
On 20 May 2008, the Parties entered into a Framework Agreement that established that “[t]he Purchaser shall provide suitable guarantee letter from its parent company acceptable to the Contractor”.17
While Mr Agrawal did not sign the Framework Agreement for Reliance Infrastructure, he did initial at the bottom of every page thereof.19 Paragraph 3.7 also contained an agreement to arbitrate disputes between the Parties.20
On 23 June 2008, another officer of Reliance Infrastructure sent an email to Shanghai Electric, copying Mr Agrawal, with an attached draft of a guarantee letter dated 25 June 2008.21 Under that draft guarantee, Reliance Infrastructure would have guaranteed the performance of Reliance (UK)’s obligations owed to Shanghai Electric under another contract,22 which related to a different power plant project in India that was owned by the Damodar Valley Corporation (“the DVC Draft Guarantee”).23
Paragraph 10 of the DVC Draft Guarantee contained an agreement to arbitrate disputes between the Parties,24 but the draft was never executed by the Parties.25
On 26 June 2008, the Guarantee Letter was allegedly signed by Mr Agrawal on behalf of Reliance Infrastructure at a signing ceremony in Shanghai, China. According to Ms Yu Liwen, who was Shanghai Electric’s sales and business development manager at the time,26 she printed out the Guarantee Letter, delivered it to Mr Agrawal, and then witnessed him sign it.27
According to Ms Yu, Mr Agrawal attended that ceremony on behalf of the senior management of the Reliance Group,28 as said to be demonstrated by the contents of Mr Agrawal’s speech which he delivered thereat.29
In the Guarantee Letter, Reliance Infrastructure guaranteed (or is alleged to have guaranteed) the performance of Reliance (UK)’s obligations owed to Shanghai Electric in the Supply Contract.30 Paragraph 10 contained a putative agreement to submit all disputes between the Parties to arbitration, seated in Singapore, and administered by the Singapore International Arbitration Centre (“SIAC”).31
On 4 July 2008, Mr Agrawal sent an email to Shanghai Electric’s Vice–President, with an enclosed letter relaying various requests made by the Damodar Valley Corporation and proposing a contractual assignment for Shanghai Electric’s acceptance. That letter was signed by Mr Agrawal, who was described therein as an “Authorized Signatory” for Reliance Infrastructure.32
On 26 August 2008, Mr Agrawal sent an email to Shanghai Electric, in which he discussed two other power plant projects in India,
The underlying SIAC–administered arbitration arose out of outstanding payments alleged by Shanghai Electric to be owed to it by Reliance (UK), that went unpaid and in alleged breach of the Supply Contract.34 Shanghai Electric invoked the arbitration agreement in Paragraph 10 of the Guarantee Letter and sought enforcement of Reliance Infrastructure’s guarantee of Reliance (UK)’s liabilities under the Supply Contract.35
In response, Reliance Infrastructure pleaded that the Guarantee Letter was invalid, because it was not aware of its existence,36 and Mr Agrawal had no authority to execute it.37 However, Reliance Infrastructure did not expressly put in issue that Mr Agrawal’s signature on the Guarantee Letter was a forgery, nor did it expressly plead that the Tribunal lacked jurisdiction over the dispute.
In opening submissions to the Tribunal on 6 September 2021, Reliance Infrastructure made clear that it was
Then, on the last...
To continue reading
Request your trial