Re Mechanised Construction Pte Ltd

JurisdictionSingapore
CourtHigh Court (Singapore)
JudgeChao Hick Tin JC
Judgment Date27 April 1989
Neutral Citation[1989] SGHC 44
Citation[1989] SGHC 44
Published date19 September 2003
Year1989
Docket NumberCompanies Winding Up No 786 of
Date27 April 1989
Subject MatterGrounds for winding-up,Whether debtor's failure to pay disputed sum sufficient ground for winding-up,Winding up,Dispute over amount owing,Companies,s 254(2)(a) Companies Act (Cap 50),Failure to pay statutory demand
Plaintiff CounselDA Mitchell (Donaldson & Burkinshaw)
Defendant CounselKelvin Lim (Tan Lee & Choo)

Cur Adv Vult

These winding-up proceedings were first initiated by Haller (Far East) Pte Ltd on 22 November 1986 on the ground that the debtor company, Mechanised Construction Pte Ltd, owed Haller a sum of $64,297.96. The petition of Haller was based on neglect by the company to pay up the sum demanded within three weeks of the issue of the statutory notice. On 17 November 1987, by an order of court, Haller was given leave to withdraw its petition and in its place, Boustead Services Pte Ltd (Boustead) was granted leave to be substituted as the petitioning creditor. The substituted petition was filed on 22 December 1987. The ground upon which the substituted petitioner sought to rely to wind up the company was that the latter neglected to pay or satisfy a statutory notice of demand dated 20 January 1987 for a sum of $141,036.79.

The sum of $141,036.79 was alleged to be due from the company to Boustead under a sale contract dated 30 June 1985 whereby Boustead agreed to supply, fabricate and install structural steelworks of an estimated total weight of 201 metric tones at the rate of $1,490 per tone, making an estimated total of $299,490.
These materials and services were required in connection with the Katong Convent Secondary School Project, in which the company was a sub-contractor. Under the contract the time for completing the works was to be `four to five months from confirmation of order and on condition that the site is available to (Boustead) within two weeks after confirmation of order`. Payment was to be made by `monthly progressive at 30 days upon invoicing`. On 5 July 1985, in accepting the offer from Boustead, the company stated that it agreed and accepted `the sales contract for a total lump sum price of $299,490 subject to final quantity`. The site was only made available to Boustead on 10 August 1985.

The company alleged that the progress of work undertaken by Boustead `was extremely slow`.
The company asserted that the original completion date should have been 10 January 1986 (five months from 10 August 1985). On 8 November 1985, Boustead submitted a revised programme to the company to complete the works by 7 April 1986. The company indicated that, without prejudice to its rights, it agreed to the revised programme. Thereafter, the progress of the work still appeared to be slow, so much so that on 3 March 1986, the company reminded Boustead that their delay had caused delay to other works relating to `roof tile installation and subsequent windows plastering, screwing and ceiling below the roofs`. In their reply of 5 March 1986, Boustead admitted that `the rate of progress at the site prior to the beginning of this year (was) unfortunately slow` but added that `efforts (had) been made since to speed up the work both at site and in our workshop`. Boustead also said that `this rate of progress will be difficult to maintain if progressive payment due to us is not forthcoming`.

Thereafter works would appear to remain slow as the company alleged that by April 1986, only about 35 tones of trusses had been installed and that by 26 April 1986, the company had paid $60,000 to Boustead, more than what was due to Boustead.
That sum was said to be equivalent to payment for 40 tones of installed trusses. The minutes of a site meeting on 18 April 1986 recorded that `there are presently 40 trusses yet to be laid in order that the entire roofing might be finished on time`. On 19 May 1986, Boustead was warned by the company to complete the works by 15 June 1986, failing which the company would terminate the contract for `breaching the time frame and (would) continue the remaining work on (its) own` so that the school project would not be jeopardized. The company ceased to make any payment to Boustead since May 1986. The entire works were not completed until 26 August 1986, a delay of four months and 20 days counting from the date on which the works should have been completed in accordance with the revised programme.

I would also set out the following events subsequent to the date of completion of the works on 26 August 1986:

27 August 1986:

Boustead wrote to the company to say that it had completed all the works and demanded payment for the sum of $175,832.26.

5 September 1986:

The company replied to say that the claim was not acceptable and said that `since 20 June 1986, we have continued your remaining works with our own men and machineries to complete your contractual work on 26 August 1986 due to the absence of your workforce on site. We are unable to calculate the cost incurred and suffered by us due to your long delay and absence of manpower until the whole project is completed and handed over to the employer`.

16 September 1986:

Boustead wrote to dispute that their workforce was not present to undertake the works except in one instance - `the exception is frames TRC-1 and TRC-5 in drawing R4-1 which you had revised and decided to carry out supply, fabrications and installations yourself.` Boustead suggested a meeting to resolve their dispute.

24 October 1986:

A meeting was held between the parties.

12 November 1986:

Boustead wrote to say that following the meeting and their examination of the claims raised by the company, Boustead would reduce their invoiced claim of $175,832.26 by $30,443.50.

22 November 1986:

Haller filed the original petition to wind up the company.

12 December 1986:

Boustead sent a reminder to the company to pay up the sum of $141,036.79 within seven days failing which Boustead `will...

Get this document and AI-powered insights with a free trial of vLex and Vincent AI

Get Started for Free

Unlock full access with a free 7-day trial

Transform your legal research with vLex

  • Complete access to the largest collection of common law case law on one platform

  • Generate AI case summaries that instantly highlight key legal issues

  • Advanced search capabilities with precise filtering and sorting options

  • Comprehensive legal content with documents across 100+ jurisdictions

  • Trusted by 2 million professionals including top global firms

  • Access AI-Powered Research with Vincent AI: Natural language queries with verified citations

vLex

Unlock full access with a free 7-day trial

Transform your legal research with vLex

  • Complete access to the largest collection of common law case law on one platform

  • Generate AI case summaries that instantly highlight key legal issues

  • Advanced search capabilities with precise filtering and sorting options

  • Comprehensive legal content with documents across 100+ jurisdictions

  • Trusted by 2 million professionals including top global firms

  • Access AI-Powered Research with Vincent AI: Natural language queries with verified citations

vLex

Unlock full access with a free 7-day trial

Transform your legal research with vLex

  • Complete access to the largest collection of common law case law on one platform

  • Generate AI case summaries that instantly highlight key legal issues

  • Advanced search capabilities with precise filtering and sorting options

  • Comprehensive legal content with documents across 100+ jurisdictions

  • Trusted by 2 million professionals including top global firms

  • Access AI-Powered Research with Vincent AI: Natural language queries with verified citations

vLex

Unlock full access with a free 7-day trial

Transform your legal research with vLex

  • Complete access to the largest collection of common law case law on one platform

  • Generate AI case summaries that instantly highlight key legal issues

  • Advanced search capabilities with precise filtering and sorting options

  • Comprehensive legal content with documents across 100+ jurisdictions

  • Trusted by 2 million professionals including top global firms

  • Access AI-Powered Research with Vincent AI: Natural language queries with verified citations

vLex

Unlock full access with a free 7-day trial

Transform your legal research with vLex

  • Complete access to the largest collection of common law case law on one platform

  • Generate AI case summaries that instantly highlight key legal issues

  • Advanced search capabilities with precise filtering and sorting options

  • Comprehensive legal content with documents across 100+ jurisdictions

  • Trusted by 2 million professionals including top global firms

  • Access AI-Powered Research with Vincent AI: Natural language queries with verified citations

vLex

Unlock full access with a free 7-day trial

Transform your legal research with vLex

  • Complete access to the largest collection of common law case law on one platform

  • Generate AI case summaries that instantly highlight key legal issues

  • Advanced search capabilities with precise filtering and sorting options

  • Comprehensive legal content with documents across 100+ jurisdictions

  • Trusted by 2 million professionals including top global firms

  • Access AI-Powered Research with Vincent AI: Natural language queries with verified citations

vLex
39 cases
  • Law Society of Singapore v Tan Guat Neo Phyllis
    • Singapore
    • High Court (Singapore)
    • 4 December 2007
    ... ... rule or principle adopted in or derived from English law is not permissible if thereby the true and actual meaning of the statute under construction be varied, or denied effect ... Similarly, in Public Prosecutor v Yuvaraj [1969] 2 MLJ 89 , the Privy Council held ( per Lord Diplock at 90) ... ...
  • Tan Kiam Peng v Public Prosecutor
    • Singapore
    • Court of Appeal (Singapore)
    • 28 September 2007
    ... ... (Cap 1, 2002 Rev Ed), “export” and “import” are, “unless there is something in the subject or context inconsistent with such construction or unless it is therein otherwise expressly provided”, assigned the following respective meanings: “export”, with its ... ...
  • Tan Kiam Peng v Public Prosecutor
    • Singapore
    • High Court (Singapore)
    • 29 November 2006
    ... ... Prima facie, as a matter of ordinary construction, when the word ‘knowingly’ is so introduced in a provision of this kind, it required [ sic ] knowledge by the accused of each of the facts ... ...
  • Public Prosecutor v Tsang Yuk Chung
    • Singapore
    • High Court (Singapore)
    • 20 September 1988
  • Get Started for Free
1 books & journal articles
  • Bankruptcy and insolvency
    • United Kingdom
    • Construction Law. Volume III - Third Edition
    • 13 April 2020
    ...Tests in Section 254 of the Companies Act” [2011] Singapore Journal of Legal Studies 486. 225 Re Mechanised Construction Pte Ltd [1989] SLR 533; Re Sanpete Builders (S) Pte Ltd [1989] 1 SLR(R) 5 at [41]–[43], per Chao Hick Tin JC. 226 Metalform Asia Pte Ltd v Holland Leedon Pte Ltd [2007] S......