PT Perusahaan Gas Negara (Persero) TBK v CRW Joint Operation (Indonesia) and another matter
Jurisdiction | Singapore |
Court | High Court (Singapore) |
Judge | Vinodh Coomaraswamy J |
Judgment Date | 16 July 2014 |
Neutral Citation | [2014] SGHC 146 |
Citation | [2014] SGHC 146 |
Subject Matter | Setting aside,Arbitration,Recourse against award |
Published date | 21 July 2014 |
Defendant Counsel | Mr Cavinder Bull SC, Ms Foo Yuet Min, Ms Lim May Jean and Mr Ho Ping Darryl (Drew & Napier LLC) |
Plaintiff Counsel | Mr Philip Antony Jeyaretnam SC and Ms Wong Wai Han (Rodyk & Davidson LLP) |
Docket Number | Originating Summons No 683 of 2013, Originating Summons No 585 of 2013 (Summons No 3923 of 2013) |
Date | 2014 |
Hearing Date | 10 October 2013,09 October 2013 |
In the two applications before me, PT Perusahaan Gas Negara (Persero) TBK (“PGN”) applies to set aside: (1) a majority arbitral award dated 22 May 2013 issued in favour of CRW Joint Operation (Indonesia) (“CRW”); and (2) an order permitting that award to be enforced as though it were a judgment of the High Court. Having received and considered both parties’ written and oral submissions, I dismissed both of PGN’s applications.
PGN has appealed to the Court of Appeal against my decision. In brief, it is my view that the majority’s award is entirely consistent with the parties’ contract and with the manner in which that contract was interpreted by the Court of Appeal in earlier litigation between the same parties on the same contract. It is also my view that the majority’s award is not prohibited by Singapore’s international arbitration legislation, whether explicitly or by implication. I now set out the grounds for my decision.
Background The parties, their contract and their disputesPGN is a listed, state-owned company established under Indonesian law. It owns and operates gas transmission systems in Indonesia.1 CRW is also an entity established under Indonesian law. It comprises three Indonesian limited liability companies.2
By a contract entered into in 2006, PGN engaged CRW to design, procure, install, test and pre-commission a pipeline to convey natural gas from South Sumatra to West Java.3 In early 2008, CRW and PGN found themselves in dispute on a number of variation claims made by CRW under their contract. The parties referred their disputes for decision by a neutral body constituted by their contract for precisely that purpose. That body is known as a dispute adjudication board (“DAB”).
In due course, the DAB rendered a series of decisions dealing with all of the parties’ disputes. PGN accepted all of the DAB’s decisions except for its decision delivered on 25 November 2008. In that decision, the DAB held that as at 25 November 2008, CRW had “become entitled to” the total sum of US$17,298,834.57.4 PGN has failed to pay to CRW pursuant to that DAB decision.
PGN accepts that it has been under a contractual obligation since 25 November 2008 to comply promptly with that DAB decision by paying CRW that sum. PGN further accepts, as it must, that its failure to do so is a breach of contract. I shall refer to the parties’ underlying dispute which forms the subject-matter of the DAB decision as the “primary dispute”. I shall refer to the dispute which arises from PGN’s failure to pay CRW, whether promptly or at all, pursuant to the DAB decision as the “secondary dispute”.
The phrase “secondary
Court: … is it common ground between the parties that PGN is in breach in not paying [CRW] pursuant to [the DAB decision] notwithstanding the notice of dissatisfaction and the pending arbitration?
Mr Jeyaretnam: Your Honour, the--- I think we really would not be able to resist that… conclusion on the contract.
The contract… provides for… the DAB decision to be binding andDAB Decision has been granted .…And that … has been our legal position . But the question is what is the enforcement options available and those enforcement options depend on the law and on the procedural provision in Singapore… [I]nevitably the Court’s sympathies must lie with the party who has not received payment under a form of contract such as this…. [b]ut regardless of that, the question remains what actually is the legal position.[emphasis added]
It is true that one’s sympathies inevitably lie with CRW and not with PGN, whose arguments have evolved over the course of the parties’ protracted dispute. But it is my task to judge the parties’ arguments on their merits and not on my sympathies. It is on the merits that I have dismissed PGN’s applications, for the detailed reasons which follow.
The 2009 arbitrationThe parties’ contract contains an arbitration agreement. CRW has made two attempts through arbitration to compel PGN to pay the sum awarded by the DAB. CRW’s first attempt was an arbitration commenced in 2009. That attempt failed. Its second attempt is an arbitration commenced in 2011. It is from this 2011 arbitration that the two applications before me arise.
For a variety of evolving reasons, PGN has maintained throughout the 2009 arbitration, throughout the 2011 arbitration and throughout all the associated litigation (including the two applications now before me) that it cannot be compelled to comply promptly with the DAB decision unless its primary dispute with CRW has been heard and determined on its merits and with finality.
In the 2009 arbitration, CRW placed before the tribunal
By a majority, the 2009 tribunal rejected PGN’s argument. The majority issued what it described as a “Final Award” requiring PGN to comply with the DAB decision and noting expressly that PGN was at liberty to commence a
Rebuffed but undaunted, CRW commenced the second arbitration in 2011. In the 2011 arbitration, CRW adjusted its approach specifically to meet PGN’s earlier argument. It did so by placing before the 2011 tribunal
The 2011 tribunal has, by a majority, rejected PGN’s argument. It has therefore issued an interim or partial award compelling PGN to comply with the DAB decision. CRW has obtained leave to enforce that award against PGN as though it were a judgment of the High Court. PGN applies now to set aside the 2011 tribunal’s interim or partial award and, with it, the order permitting CRW to enforce that award. PGN makes these applications even though: (1) the majority’s award simply requires PGN to pay promptly a sum to CRW
Mr Jeyaretnam puts the central issue before me in the following way:
The central issue to be decided is whether CRW is entitled to enforce [the DAB decision] by way of an interim award, which is final and binding, without the [tribunal] first determining the underlying merits of the [DAB decision].6
PGN’s arguments on this central issue, put simply, are as follows:
To continue reading
Request your trial-
PTPerusahaan Gas Negara (Persero) TBK v CRW Joint Operation
...the Interim Award and dismissed both SUM 3923 and OS 683 (see PTPerusahaan Gas Negara (Persero) TBKv CRW Joint Operation (Indonesia) [2014] SGHC 146 (‘Persero HC (2014) ’)). He considered a provisional award to be one which granted relief that was intended to be effective only for a limited......